User note:

About this appendix: Appendix L is intended to provide guidance to building departments in their efforts to set fees for building permits. This appendix provides examples that may be used as a reference when setting fee schedules and are not intended to be literally applied.


TOTAL VALUATION FEE
$1 to $500 $24
$501 to $2,000
$24 for the first $500; plus $3 for each additional $100 or fraction thereof, up
to and including $2,000
$2,001 to $40,000
$69 for the first $2,000; plus $11 for each additional $1,000 or fraction
thereof, up to and including $40,000
$40,001 to $100,000
$487 for the first $40,000; plus $9 for each additional $1,000 or fraction
thereof, up to and including $100,000
$100,001 to $500,000
$1,027 for the first $100,000; plus $7 for each additional $1,000 or fraction
thereof, up to and including $500,000
$500,001 to $1,000,000
$3,827 for the first $500,000; plus $5 for each additional $1,000 or fraction
thereof, up to and including $1,000,000
$1,000,001 to $5,000,000
$6,327 for the first $1,000,000; plus $3 for each additional $1,000 or fraction
thereof, up to and including $5,000,000
$5,000,001 and over
$18,327 for the first $5,000,000; plus $1 for each additional $1,000 or fraction
thereof