To provide a desired level of structural performance when structures are subjected to the loads that are expected during construction or alteration and throughout their intended lives.
Structures shall be designed and constructed to prevent injury to occupants due to loading of a structural element or system consistent with the design performance level determined in Chapter 3.
Structures shall be designed and constructed to prevent loss of property and amenity consistent with the design performance level determined in Chapter 3.
Structures, or portions thereof, shall remain stable and not collapse during construction or alteration and throughout their lives.
Structures shall be designed to sustain local damage, and the structural system as a whole shall remain stable and not be damaged to an extent disproportionate to the original local damage.
Structures, or portions thereof, shall have a low probability of causing damage or loss of amenity through excessive deformation, vibration or degradation during construction or alteration and throughout their lives.
Structures, or portions thereof, shall be designed and constructed taking into account all expected loads, and combination of loads, associated with the event(s) magnitude(s) that would affect their performance, including, but not limited to:
  1. Dead loads
  2. Live loads
  3. Impact loads
  4. Explosion loads
  5. Soil and hydrostatic pressure loads
  6. Flood loads (mean return period) Small: 100 years Medium: 500 years Large: Determined on a site-specific basis Very Large: Determined on a site-specific basis
  7. Wind loads (mean return period) Small: 50 years Medium: 75 years Large: 100 years Very Large: 125 years
  8. Wind-borne debris loads
  9. Snow loads (mean return period) Small: 25 years Medium: 30 years Large: 50 years Very Large: 100 years
  10. Rain loads. See Table 501.3.4
  11. Earthquake loads (mean return period) Small: 25 years Medium: 72 years Large: 475 years, but need not exceed two-thirds of the intensity of very large loads Very Large: 2,475 years. At sites where the 2,475- year, 5-percent damped spectral response acceleration at a 0.3-second period exceeds 1.5 g and at a 1-second period exceeds 0.6 g, very large ground shaking demands need not exceed a 5-percent damped response spectrum that at each period is 150 percent of the median spectral response acceleration ordinate resulting from a characteristic earthquake on any known active fault in the region.
  12. Ice loads, atmospheric icing (mean return period) Small: 25 years Medium: 50 years Large: 100 years Very Large: 200 years
  13. Hail loads
  14. Thermal loads
TABLE 501.3.4
RAIN LOADS
MAGNITUDE OF EVENT
DRAINAGE SYSTEM
MRI (YEARS)
STORM DURATION (MIN.)
Small
Primary
25
60
Small
Secondary
25
15
Medium
Primary
50
60
Medium
Secondary
50
15
Large
Primary
100
60
Large
Secondary
100
15
Very Large
Primary
100
30
Very Large
Secondary
100
10
The design of buildings and structures shall consider appropriate factors of safety to provide adequate performance from:
  1. Effects of uncertainties resulting from construction activities.
  2. Variation in the properties of materials and the characteristics of the site.
  3. Accuracy limitations inherent in the methods used to predict the stability of the building.
  4. Self-straining forces arising from differential settlements of foundations and from restrained dimensional changes due to temperature, moisture, shrinkage, creep and similar effects.
The demolition or alteration of buildings and structures shall be carried out in a way that avoids the likelihood of premature collapse.
Site work, where necessary, shall be carried out to provide stability for construction on the site and avoid the likelihood of damage to adjacent property.
Linked Resources
P
P Premium Feature

This feature is included in the premium subscription. Visit the feature page to learn more.

Learn More
Bookmarks
P
P Premium Feature

This feature is included in the premium subscription. Visit the feature page to learn more.

Learn More