CODES

ADOPTS WITH AMENDMENTS:

International Plumbing Code 2015 (IPC 2015)

Chapter 1 Scope and Administration

Chapter 1 SCOPE AND ADMINISTRATION

Chapter 2 Definitions

Chapter 3 General Regulations

Chapter 4 Fixtures, Faucets and Fixture Fittings

Chapter 5 Water Heaters

Chapter 6 Water Supply and Distribution

Chapter 7 Sanitary Drainage

Chapter 8 Indirect/Special Waste

Chapter 9 Vents

Chapter 10 Traps, Interceptors and Separators

Chapter 11 Storm Drainage

Chapter 12 Special Piping and Storage Systems

Chapter 13 Nonpotable Water Systems

Chapter 13 NONPOTABLE WATER SYSTEMS

Chapter 14 Subsurface Landscape Irrigation Systems

Chapter 14 SUBSURFACE LANDSCAPE IRRIGATION SYSTEMS

Chapter 15 Referenced Standards

Chapter 15 REFERENCED STANDARDS

Appendix A Plumbing Permit Fee Schedule

Appendix B Rates of Rainfall for Various Cities

Appendix C Structural Safety

Appendix D Degree Day and Design Temperatures

Appendix E Sizing of Water Piping System

301.1 Scope

STATE AMENDMENT
The provisions of this chapter shall govern the general regulations regarding the design and installation of plumbing not specific to other chapters.
Plumbing shall be installed with due regard to preservation of the strength of structural members and prevention of damage to walls and other surfaces through fixture usage.
Plumbing fixtures, drains, appurtenances and appliances used to receive or discharge liquid waste or sewage shall be directly connected to the sanitary drainage system of the building or premises, in accordance with the requirements of this code and the requirements of the department of the city engineer, in cities having such departments, the boards of health of health districts, or the sewer purveyor, as appropriate (see division (D) of Section 3781.03 of the Revised Code). This section shall not be construed to prevent indirect waste systems required by Chapter 8.

Exception: Bathtubs,showers, lavatories, clothes washers and laundry trays shall not be required to discharge to the sanitary drainage system where such fixtures discharge to an approved system in accordance with Chapters 13 and 14.
  1. Bathtubs, showers, lavatories, clothes washers and laundry trays shall not be required to discharge to the sanitary drainage system where such fixtures discharge to a recycled water system approved by the "Ohio Environmental Protection Agency" in accordance with Chapter 3745-42 of the Administrative Code or approved by the "Ohio Department of Health" in accordance with Chapter 3701-28 of the Administrative Code.
  2. Wastes from dental or cuspidor fountains, drinking fountains, bar sinks, soda fountains, floor drains or shower drains may be indirectly connected by means of an air break to the sanitary drainage system. Each indirectly connected item listed above shall individually discharge to a directly connected floor drain, waste receptor or standpipe.
Every plumbing fixture, device or appliance requiring or using water for its proper operation shall be directly or indirectly connected to the water supply system in accordance with the provisions of this code.
Unless otherwise indicated, the pipe, tube and fitting sizes specified in this code are expressed in nominal or standard sizes as designated in the referenced material standards.

301.6 Prohibited Locations

STATE AMENDMENT
Plumbing systems shall not be located in an elevator shaft or in an elevator equipment room.

Exception: Floor drains, sumps and sump pumps shall be permitted at the base of the shaft, provided that they are indirectly connected to the plumbing system. and comply with Section 1003.4.
In instances where conflicts occur between this code and the manufacturer's installation instructions, the more restrictive provisions shall apply.
Ashes, cinders or rags; flammable, poisonous or explosive liquids or gases; oil, grease or any other insoluble material capable of obstructing, damaging or overloading the building drainage or sewer system, or capable of interfering with the normal operation of the sewage treatment processes, shall not be deposited, by any means, into such systems.

302.2 Industrial Wastes

STATE AMENDMENT
Waste products from manufacturing or industrial operations shall not be introduced into the public sewer until it has been determined by the code official building official or other authority having jurisdiction that the introduction thereof will not damage the public sewer system or interfere with the functioning of the sewage treatment plant.
Each length of pipe and each pipe fitting, trap, fixture, material and device utilized in a plumbing system shall bear the identification of the manufacturer and any markings required by the applicable referenced standards.
All materials used shall be installed in strict accordance with the standards under which the materials are accepted and approved. In the absence of such installation procedures, the manufacturer's instructions shall be followed. Where the requirements of referenced standards or manufacturer's installation instructions do not conform to minimum provisions of this code, the provisions of this code shall apply.
All plastic pipe, fittings and components shall be third-party certified listed as conforming to NSF 14.
All plumbing products and materials shall be listed by a third-party certification an approved agency as complying with the applicable referenced standards. Products and materials shall be identified in accordance with Section 303.1.
Plumbing systems shall be designed and installed in accordance with Sections 304.2 through 304.4 to prevent rodents from entering structures.
All strainer plates on drain inlets shall be designed and installed so that all openings are not greater than 1/2 inch (12.7 mm) in least dimension.
Meter boxes shall be constructed in such a manner that rodents are prevented from entering a structure by way of the water service pipes connecting the meter box and the structure.
In or on structures where openings have been made in walls, floors or ceilings for the passage of pipes, the annular space between the pipe and the sides of the opening shall be sealed with caulking materials or closed with gasketing systems compatible with the piping materials and locations.
Pipes passing through concrete or cinder walls and floors or other corrosive material shall be protected against external corrosion by a protective sheathing or wrapping or other means that will withstand any reaction from the lime and acid of concrete, cinder or other corrosive material. Sheathing or wrapping shall allow for movement including expansion and contraction of piping. The wall thickness of the material shall be not less than 0.025 inch (0.64 mm).
Piping in a plumbing system shall be installed so as to prevent strains and stresses that exceed the structural strength of the pipe. Where necessary, provisions shall be made to protect piping from damage resulting from expansion, contraction and structural settlement.
Any pipe that passes through a foundation wall shall be provided with a relieving arch, or a pipe sleeve pipe shall be built into the foundation wall. The sleeve shall be two pipe sizes greater than the pipe passing through the wall.

305.4 Freezing

STATE AMENDMENT
Water, soil and waste pipes shall not be installed outside of a building, in attics or crawl spaces, concealed in outside walls, or in any other place subjected to freezing temperatures unless adequate a provision is made to protect such pipes from freezing. by insulation or heat or both Exterior water supply system piping shall be installed not less than 6 inches (152 mm) below the frost line and not less than 12 inches (305 mm) below grade.

305.4.1 Sewer Depth

STATE AMENDMENT
Building sewers that connect to private sewage disposal systems shall be installed not less than [NUMBER] inches (mm) below finished grade at the point of septic tank connection. Building sewers shall be installed not less than [NUMBER] inches (mm) below grade.
Joints at the roof and around vent pipes shall be made water tight by the use of lead, copper, galvanized steel, aluminum, plastic or other approved flashings or flashing material. Exterior wall openings shall be made water tight.
In concealed locations where piping, other than cast-iron or galvanized steel, is installed through holes or notches in studs, joists, rafters or similar members less than 11/2 inches (38 mm) from the nearest edge of the member, the pipe shall be protected by steel shield plates. Such shield plates shall have a thickness of not less than 0.0575 inch (1.463 mm) (No. 16 gage). Such plates shall cover the area of the pipe where the member is notched or bored, and shall extend not less than 2 inches (51 mm) above sole plates and below top plates.
Components of a plumbing system installed along alleyways, driveways, parking garages or other locations exposed to damage shall be recessed into the wall or otherwise protected in an approved manner.
Buried piping shall be supported throughout its entire length.
Where trenches are excavated such that the bottom of the trench forms the bed for the pipe, solid and continuous load-bearing support shall be provided between joints. Bell holes, hub holes and coupling holes shall be provided at points where the pipe is joined. Such pipe shall not be supported on blocks to grade. In instances where the materials manufacturer's installation instructions are more restrictive than those prescribed by the code, the material shall be installed in accordance with the more restrictive requirement.
Where trenches are excavated below the installation level of the pipe such that the bottom of the trench does not form the bed for the pipe, the trench shall be backfilled to the installation level of the bottom of the pipe with sand or fine gravel placed in layers not greater than 6 inches (152 mm) in depth and such backfill shall be compacted after each placement.
Where rock is encountered in trenching, the rock shall be removed to not less than 3 inches (76 mm) below the installation level of the bottom of the pipe, and the trench shall be backfilled to the installation level of the bottom of the pipe with sand tamped in place so as to provide uniform load-bearing support for the pipe between joints. The pipe, including the joints, shall not rest on rock at any point.
If soft materials of poor load-bearing quality are found at the bottom of the trench, stabilization shall be achieved by overexcavating not less than two pipe diameters and backfilling to the installation level of the bottom of the pipe with fine gravel, crushed stone or a concrete foundation. The concrete foundation shall be bedded with sand tamped into place so as to provide uniform load-bearing support for the pipe between joints.
Backfill shall be free from discarded construction material and debris. Loose earth free from rocks, broken concrete and frozen chunks shall be placed in the trench in 6-inch (152 mm) layers and tamped in place until the crown of the pipe is covered by 12 inches (305 mm) of tamped earth. The backfill under and beside the pipe shall be compacted for pipe support. Backfill shall be brought up evenly on both sides of the pipe so that the pipe remains aligned. In instances where the manufacturer's instructions for materials are more restrictive than those prescribed by the code, the material shall be installed in accordance with the more restrictive requirement.
Where pipe is to be installed by tunneling, jacking or a combination of both, the pipe shall be protected from damage during installation and from subsequent uneven loading. Where earth tunnels are used, adequate supporting structures shall be provided to prevent future settling or caving.

307.1 General

STATE AMENDMENT
In the process of installing or repairing any part of a plumbing and drainage installation, the finished floors, walls, ceilings, tile work or any other part of the building or premises that must be changed or replaced shall be left in a safe structural condition in accordance with the requirements of the International Building Code.
A framing member shall not be cut, notched or bored in excess of limitations specified in the International Building Code.
Penetrations of floor/ceiling assemblies and assemblies required to have a fire-resistance rating shall be protected in accordance with the International Building Code.
Truss members and components shall not be cut, drilled, notched, spliced or otherwise altered in any way without written concurrence and approval of a registered design professional. Alterations resulting in the addition of loads to any member (e.g., HVAC equipment, water heater) shall not be permitted without verification that the truss is capable of supporting such additional loading.
Trenching installed parallel to footings and walls shall not extend into the bearing plane of a footing or wall. The upper boundary of the bearing plane is a line that extends downward, at an angle of 45 degrees (0.79 rad) from horizontal, from the outside bottom edge of the footing or wall.

307.6 Trench location

STATE AMENDMENT
Trenches installed parallel to footings shall not extend below the 45-degree (0.79 rad) bearing plane of the footing or wall.
Piping materials exposed within plenums shall comply with the provisions of the International Mechanical Code.

307.8 Enforcement

STATE AMENDMENT
Enforcement of the provisions of this section is the responsibility of the certified building official of the certified municipal, county, or township building department having jurisdiction or the superintendent of the division of industrial compliance.
Plumbing piping shall be supported in accordance with this section.
Where earthquake loads are applicable in accordance with the building code, plumbing piping supports shall be designed and installed for the seismic forces in accordance with the International Building Code.
Hangers, anchors and supports shall support the piping and the contents of the piping. Hangers and strapping material shall be of approved material that will not promote galvanic action.
Hangers and anchors shall be attached to the building construction in an approved manner.

308.5 Interval of Support

STATE AMENDMENT
Pipe shall be supported in accordance with Table 308.5.

Exception: The interval of support for piping systems designed to provide for expansion/contraction shall conform to the engineered design in accordance with Section 316.1. 106.5 of the building code.

TABLE 308.5 HANGER SPACING

PIPING MATERIAL MAXIMUM
HORIZONTAL
SPACING (feet)
MAXIMUM
VERTICAL
SPACING (feet)
Acrylonitrile butadiene
styrene (ABS) pipe
4 10b
Aluminum tubing 10 15
Brass pipe 10 10
Cast-iron pipe 5a 15
Chlorinated polyvinyl chloride
(CPVC) pipe and tubing, 1
inch and smaller
3 10b
Chlorinated polyvinyl chloride
(CPVC) pipe and tubing,11/4
inches and larger
4 10b
Copper or copper-alloy pipe 12 10
Copper or copper-alloy tubing,
11/4-inch diameter and
smaller
6 10
Copper or copper-alloy tubing,
11/2-inch diameter and
larger
10 10
Cross-linked polyethylene
(PEX) pipe
2.67
(32 inches)
10b
Cross-linked polyethylene/
aluminum/cross-linked
polyethylene (PEX-AL-
PEX) pipe
2.67
(32 inches)
4
Lead pipe Continuous 4
Polyethylene/aluminum/
polyethylene (PE-AL-PE)
pipe
2.67
(32 inches)
4
Polyethylene of raised
temperature (PE-RT) pipe
2.67
(32 inches)
10b
Polypropylene (PP) pipe or
tubing 1 inch and smaller
2.67
(32 inches)
10b
Polypropylene (PP) pipe or
tubing, 11/4 inches and larger
4 10b
Polyvinyl chloride (PVC) pipe 4 10b
Stainless steel drainage
systems
10 10b
Steel pipe 12 15

For SI: 1 inch = 25.4 mm, 1 foot = 304.8 mm.
a. The maximum horizontal spacing of cast-iron pipe hangers shall be increased to 10 feet where 10-foot lengths of pipe are installed.
b. For sizes 2 inches and smaller, a guide shall be installed midway between required vertical supports. Such guides shall prevent pipe movement in a direction perpendicular to the axis of the pipe.
Rigid support sway bracing shall be provided at changes in direction greater than 45 degrees (0.79 rad) for pipe sizes 4 inches (102 mm) and larger.
Anchorage shall be provided to restrain drainage piping from axial movement.
For pipe sizes greater than 4 inches (102 mm), restraints shall be provided for drain pipes at all changes in direction and at all changes in diameter greater than two pipe sizes. Braces, blocks, rodding and other suitable methods as specified by the coupling manufacturer shall be utilized.
Expansion joint fittings shall be used only where necessary to provide for expansion and contraction of the pipes. Expansion joint fittings shall be of the typical material suitable for use with the type of piping in which such fittings are installed.
Piping bundles for manifold systems shall be supported in accordance with Table 308.5. Support at changes in direction shall be in accordance with the manufacturer's instructions. Where hot water piping is bundled, with cold or hot water piping, each hot water pipe shall be insulated.

309.1 General

STATE AMENDMENT
Plumbing systems and equipment in structures erected in flood hazard areas shall be constructed in accordance with the requirements of this section and the International Building Code. All buildings and structures which have been determined to require flood-resistant construction by the local flood plain administrator, as a participant in the "National Flood Insurance Program", shall be constructed as required by the provisions of Section 1612 of the building code for approval under the "Regulations for Floodplain Management and Flood Hazard Identification" of the "National Flood Insurance Program" pursuant to "FEMA 44 CFR Parts 59-77" and the authority's "Flood Damage Prevention Ordinance".

309.2 Flood Hazard

STATE AMENDMENT
For structures located in flood hazard areas, the following systems and equipment shall be located and installed as required by Section 1612 of the International Building Code.

1. Water service pipes.

2. Pump seals in individual water supply systems where the pump is located below the design flood elevation.

3. Covers on potable water wells shall be sealed, except where the top of the casing well or pipe sleeve is elevated to not less than 1 foot (305 mm) above the design flood elevation.

42. Sanitary drainage piping.

53. Storm drainage piping.

6. Manhole covers shall be sealed, except where elevated to or above the design flood elevation.

74. Other plumbing fixtures, faucets, fixture fittings, piping systems and equipment.

85. Water heaters.

96. Vents and vent systems.

Exception: The systems listed in this section are permitted to be located below the elevation required by Section 1612 of the International Building Code for utilities and attendant equipment, provided that the systems are designed and installed to prevent water from entering or accumulating within their components and the systems are constructed to resist hydrostatic and hydrodynamic loads and stresses, including the effects of buoyancy, during the occurrence of flooding up to such elevation.
Structures located in coastal high-hazard areas and coastal A zones shall meet the requirements of Section 309.2.The plumbing systems, pipes and fixtures shall not be mounted on or penetrate through walls intended to break away under flood loads.

310.1 Light and Ventilation

STATE AMENDMENT
Washrooms and toilet rooms shall be illuminated and ventilated in accordance with the International Building Code and International Mechanical Code.
The location of plumbing fixtures and the requirements for compartments and partitions shall be in accordance with Section 405.3.

310.3 Interior Finish

STATE AMENDMENT
Interior finish surfaces of toilet rooms shall comply with the International Building Code.

310.4 Enforcement

STATE AMENDMENT
Enforcement of the provisions of this section is the responsibility of the certified building official of the certified municipal, county, or township building department having jurisdiction or the superintendent of the division of industrial compliance.

311.1 General

STATE AMENDMENT
Toilet facilities shall be provided for construction workers and such facilities shall be maintained in a sanitary condition. Construction worker toilet facilities of the nonsewer type shall conform to ANSI Z4.3.

312.1 Required Tests

STATE AMENDMENT
The permit holder shall make the applicable tests prescribed in Sections 312.2 through 312.10 to determine compliance with the provisions of this code. The permit holder shall give reasonable advance notice to the code official when the plumbing work is ready for tests. The equipment, material, power and labor necessary for the inspection and test shall be furnished by the permit holder and he or she shall be responsible for determining that the work will withstand the test pressure prescribed in the following tests. All plumbing system piping shall be tested with either water or, for piping systems other than plastic, by air. After the plumbing fixtures have been set and their traps filled with water, the entire drainage system shall be submitted to final tests. The code official shall require the removal of any cleanouts if necessary to ascertain whether the pressure has reached all parts of the system. The owner or owner's representative shall cause the applicable tests and inspections prescribed in Sections 312.2 through 312.11 to be performed to determine that the work will withstand the prescribed test without leakage and to demonstrate the integrity of the device or assembly. In accordance with OBC Section 108.8, reasonable advanced notice shall be given to the building official when the plumbing work is ready for tests. The building official may require that the tests be conducted in the presence of the building official or certified plumbing inspector. The owner or owner's representative shall keep records of the tests and inspections and shall submit such records to the building official upon request.
Gauges used for testing shall be as follows:

1. Tests requiring a pressure of 10 pounds per square inch (psi) (69 kPa) or less shall utilize a testing gauge having increments of 0.10 psi (0.69 kPa) or less.

2. Tests requiring a pressure of greater than 10 psi (69 kPa) but less than or equal to 100 psi (689 kPa) shall utilize a testing gauge having increments of 1 psi (6.9 kPa) or less.

3. Tests requiring a pressure of greater than 100 psi (689 kPa) shall utilize a testing gauge having increments of 2 psi (14 kPa) or less.
New plumbing systems and parts of existing systems that have been altered, extended, or repaired shall be tested as prescribed herein to disclose leaks and defects, except that testing is not required in the following cases:
  1. In any case that does not include addition to, replacement, alteration or relocation of any water supply, drainage or vent piping.
  2. In any case where plumbing equipment is set up temporarily for exhibition purposes.
Equipment, material, power and labor necessary for testing a plumbing system or part thereof shall be furnished by the owner or the owner's representative. Required tests shall be conducted by and at the expense of the owner or the owner's representative.

312.1.3 Test gauges

STATE AMENDMENT
Gauges used for testing shall be as follows:
  1. Tests requiring a pressure of 10 pounds per square inch (psi) (69 kPa) or less shall utilize a testing gauge having increments of 0.10 psi (0.69 kPa) or less.
  2. Tests requiring a pressure of greater than 10 psi (69 kPa) but less than or equal to 100 psi (689 kPa) shall utilize a testing gauge having increments of 1 psi (6.9 kPa) or less.
  3. Tests requiring a pressure of greater than 100 psi (689 kPa) shall utilize a testing gauge having increments of 2 psi (14 kPa) or less.

312.1.4 Test media

STATE AMENDMENT
All plumbing system piping, fittings, and shower liners shall be tested with water.

Exception: Plumbing system piping and fittings are permitted to be tested as prescribed in Sections 312.2 to 312.8 with air, another compressed gas, vacuum, or other media or method only when the manufacturer of the proposed piping, fittings and solvent cement (if applicable) allows the alternative method of testing. Where this code does not address or prescribe an alternative test method, an alternative test method prescribed by the manufacturer of the piping, fittings, or solvent cement in the published manufacturer's installation instructions will be acceptable as meeting the requirements of this code.
Where any work or installation does not pass any initial test or inspection, the necessary corrections shall be made to comply with this code.
A water test shall be applied to the drainage system either in its entirety or in sections. If applied to the entire system, all openings in the piping shall be tightly closed, except the highest opening, and the system shall be filled with water to the point of overflow. If the system is tested in sections, each opening shall be tightly plugged except the highest openings of the section under test, and each section shall be filled with water, but no section shall be tested with less than a 10-foot (3048 mm) head of water. In testing successive sections, at least the upper 10 feet (3048 mm) of the next preceding section shall be tested so that no joint or pipe in the building, except the uppermost 10 feet (3048 mm) of the system, shall have been submitted to a test of less than a 10-foot (3048 mm) head of water. This pressure shall be held for not less than 15 minutes. The system shall then be tight at all points. Drainage and vent piping and fittings shall be tested prior to the installation of the plumbing fixtures and prior to the installation of wall and ceiling coverings to verify the integrity of the system in accordance with one of the following methods prescribed in Section 312.2.1, 312.2.2, or 312.2.3:
A water test shall be applied to the drainage system either in its entirety or in sections. If applied to the entire system, all openings in the piping shall be tightly closed, except the highest opening, and the system shall be filled with water to the point of overflow. If the system is tested in sections, each opening shall be tightly plugged except the highest openings of the section under test, and each section shall be filled with water, but no section shall be tested with less than a 10-foot (3048 mm) head of water. In testing successive sections, at least the upper 10 feet (3048 mm) of the next preceding section shall be tested so that no joint or pipe in the building, except the uppermost 10 feet (3048 mm) of the system, shall have been submitted to a test of less than a 10-foot (3048 mm) head of water. This pressure shall be held for at least 15 minutes. The system shall then be tight at all points.
When permitted by the manufacturer of the piping, fittings, and solvent cement (if part of the plumbing system), an air test shall be made by forcing air into the system until there is a uniform gauge pressure of 5 psi (34.5 kPa) or sufficient to balance a 10-inch (254 mm) column of mercury. This pressure shall be held for a test period of at least 15 minutes. Any adjustments to the test pressure required because of changes in ambient temperature or the seating of gaskets shall be made prior to the beginning of the test period. Testing shall be done with dual pressure relief valves rated for 7.5 psig.
When permitted by the manufacturer of the piping, fittings, and solvent cement (if part of the plumbing system), an alternative method of testing the drainage and vent system, such as compressed gas or vacuum, may be permitted to meet the drainage and vent rough-in test requirements of this code as long as the test is conducted strictly in accordance with the requirements published in the manufacturer's installation instructions.
Plastic piping shall not be tested using air. An air test shall be made by forcing air into the system until there is a uniform gauge pressure of 5 psi (34.5 kPa) or sufficient to balance a 10-inch (254 mm) column of mercury. This pressure shall be held for a test period of not less than 15 minutes. Any adjustments to the test pressure required because of changes in ambient temperatures or the seating of gaskets shall be made prior to the beginning of the test period.

312.3 Not Used

STATE AMENDMENT
The final test of the completed drainage and vent systems shall be visual and in sufficient detail to determine compliance with the provisions of this code. Where a smoke test is utilized, it shall be made by filling all traps with water and then introducing into the entire system a pungent, thick smoke produced by one or more smoke machines. When the smoke appears at stack openings on the roof, the stack openings shall be closed and a pressure equivalent to a 1-inch water column (248.8 Pa) shall be held for a test period of not less than 15 minutes. After the plumbing fixtures have been set and their traps filled with water, the entire drainage system shall be subjected to one of the following final tests as prescribed by the building official:
All plumbing fixtures shall be operated and a visual inspection of accessible piping and joints shall be petformed to determine that there are no visible leaks.
The final test of the completed drainage and vent systems shall be made, after the fixtures are connected, as follows:
  1. Close all stack openings;
  2. A manometer tube shall be placed through a trap seal to the system side and water shall be added to a fixture until an equivalent of at least 1 in. water column (248.8 Pa) is read on the manometer gauge or water-can. Water may be added to a water closet bowl or trap tailpiece extension until the water level is at least 1 inch higher than the original trap seal;
  3. Maintain the initial water column for fifteen (15) minutes;
  4. The system shall then be separated at a trap seal, AAV, or other means as directed by the plumbing inspector for verification that the entire system is interconnected.
Any other testing method equal to the 1 in. water column. Except as provided for in Section 312.4.2, compressed or stored air may not be used unless otherwise permitted by the manufacturer of piping, fittings, and solvent cement (if part of the plumbing system).
Upon completion of a section of or the entire water supply system, the system, or portion completed, shall be tested to verify the integrity of the system in accordance with one of the following methods prescribed in Section 312.5.1 or 312.5.2: and proved tight under a water pressure not less than the working pressure of the system; or, for piping systems other than plastic, by an air test of not less than 50 psi (344 kPa). This pressure shall be held for not less than 15 minutes. The water utilized for tests shall be obtained from a potable source of supply. The required tests shall be performed in accordance with this section and Section 107.
A water pressure test at not less than the working pressure under which the system is to be used shall be performed to prove the system watertight. This pressure shall be held for at least 15 minutes. The water utilized for tests shall be obtained from a potable source of supply.
When permitted by the manufacturer of the piping, fittings, and solvent cement (if part of the plumbing system), an air test of not less than 50 psi (344 kPa) shall be performed to prove the system airtight. This pressure shall be held for at least 15 minutes.

312.6 Gravity Sewer Test

STATE AMENDMENT
Gravity sewer tests shall consist of plugging the end of the building sewer at the point of connection with the public sewer, filling the building sewer with water, testing with not less than a 10-foot (3048 mm) head of water and maintaining such pressure for 15 minutes.

312.7 Forced Sewer Test

STATE AMENDMENT
Forced sewer tests shall consist of plugging the end of the building sewer at the point of connection with the public sewer and applying a pressure of 5 psi (34.5 kPa) greater than the pump rating, and maintaining such pressure for 15 minutes.
Storm drain systems within a building shall be tested by water or air in accordance with Section 312.2. or 312.3.

312.9 Shower Liner Test

STATE AMENDMENT
Where shower floors and receptors are made water tight by the application of materials required by Section 417.5.2, the completed liner installation shall be tested. The pipe from the shower drain shall be plugged water tight for the test. The floor and receptor area shall be filled with potable water to a depth of not less than 2 inches (51 mm) measured at the threshold. Where a threshold of at least 2 inches (51 mm) high does not exist, a temporary threshold shall be constructed to retain the test water in the lined floor or receptor area to a level not less than 2 inches (51 mm) deep measured at the threshold. The water shall be retained for a test period of not less than 15 minutes, and there shall not be evidence of leakage.

Exception: The shower liner test is not required for one-, two-, or three-family dwellings unless required by the shower liner manufacturer's installation instructions.
Inspection and testing shall comply with Sections 312.10.1 and 312.10.2. Inspection and testing of isolation backflow prevention devices shall comply with Sections 312.10.1 and 312.10.2. Inspection and testing requirements for containment backflow prevention devices required by the water supplier shall be in accordance with rule 3745-95-06 of the Administrative Code and enforced by the water supplier.

312.10.1 Inspections

STATE AMENDMENT
The owner shall maintain all backflow prevention assemblies and air gaps in good working condition. Annual inspections shall be made of all backflow prevention assemblies and air gaps to determine whether they are operable.

312.10.2 Testing

STATE AMENDMENT
Reduced pressure principle, double check, pressure vacuum breaker, reduced pressure detector fire protection, double check detector fire protection, and spill-resistant vacuum breaker backflow preventer prevention assemblies and hose connection backflow preventers shall be tested at the time of installation, immediately after repairs or relocation and at least annually. The testing procedure shall be performed in accordance with one of the following standards:

ASSE 5013 for reduced pressure principle and reduced pressure principle fire protection backflow prevention assemblies, ASSE 5015 for double check and double check fire protection backflow prevention assemblies, ASSE 5020 for pressure vacuum breaker assemblies, ASSE 5047 for reduced pressure detector fire protection backflow prevention assemblies, ASSE 5048 for double check detector fire protection backflow prevention assemblies, ASSE 5052 for hose connection backflow preventers, ASSE 5056 for spill resistant vacuum breaker assemblies, CSA B64.10 or CSA B64.10.1.
Although enforcement of this section is outside the scope of the plumbing code, it is important for owners to note that rule 3745-95-07 of the Administrative Code requires that the owner certify to the supplier of water that their low pressure cut-off devices, low suction throttling valves, and variable speed suction limiting controls are maintained in proper working order. Enforcement of this requirement and the referenced rule is the responsibility of the water supplier. See Section 606.5.5 of this code for additional information.

312.12 Inspections

STATE AMENDMENT
No part of any plumbing or drainage system shall be covered until it has been inspected, tested, and approved, except as provided in this section.

    Failure of the inspector to inspect the work within 4 days, exclusive of Saturdays, Sundays, and legal holidays, after the work is ready for inspection, allows the work to proceed.

313.1 General

STATE AMENDMENT
Equipment efficiencies shall be in accordance with the International Energy Conservation Code. applicable standard referenced in Chapter 13 of the building code or Chapter 11 of the "Residential Code of Ohio" .
Liquid combustion byproducts of condensing appliances shall be collected and discharged to an approved plumbing fixture or disposal area in accordance with the manufacturer's instructions. Condensate piping shall be of approved corrosion-resistant material and shall not be smaller than the drain connection on the appliance. Such piping shall maintain a horizontal slope in the direction of discharge of not less than one-eighth unit vertical in 12 units horizontal (1-percent slope).
Condensate drain systems shall be provided for equipment and appliances containing evaporators or cooling coils. Condensate drain systems shall be designed, constructed and installed in accordance with Sections 314.2.1 through 314.2.5.
Condensate from all cooling coils and evaporators shall be conveyed from the drain pan outlet to an approved place of disposal. Such piping shall maintain a horizontal slope in the direction of discharge of not less than one-eighth unit vertical in 12 units horizontal (1-percent slope). Condensate shall not discharge into a street, alley or other areas so as to cause a nuisance.
Components of the condensate disposal system shall be cast iron, galvanized steel, copper, cross-linked polyethylene, polyethylene, ABS, CPVC or PVC or polypropylene pipe or tubing. All components shall be selected for the pressure and temperature rating of the installation. Joints and connections shall be made in accordance with the applicable provisions of Chapter 7 relative to the material type. Condensate waste and drain line size shall be not less than 3/4 -inch (19.1 mm) internal diameter and shall not decrease in size from the drain pan connection to the place of condensate disposal. Where the drain pipes from more than one unit are manifolded together for condensate drainage, the pipe or tubing shall be sized in accordance with Table 314.2.2.

[M] TABLE 314.2.2 CONDENSATE DRAIN SIZING

EQUIPMENT CAPACITY MINIMUM CONDENSATE
PIPE DIAMETER
(inch)
Up to 20 tons of refrigeration 3/4 inch
Over 20 tons to 40 tons of refrigeration 1 inch
Over 40 tons to 90 tons of refrigeration 11/4 inch
Over 90 tons to 125 tons of refrigeration 11/2 inch
Over 125 tons to 250 tons of refrigeration 2 inch

For SI: 1 inch = 25.4 mm, 1 ton of capacity = 3.517 kW.
In addition to the requirements of Section 314.2.1, where damage to any building components could occur as a result of overflow from the equipment primary condensate removal system, one of the following auxiliary protection methods shall be provided for each cooling coil or fuelfired appliance that produces condensate:

1. An auxiliary drain pan with a separate drain shall be provided under the coils on which condensation will occur. The auxiliary pan drain shall discharge to a conspicuous point of disposal to alert occupants in the event of a stoppage of the primary drain. The pan shall have a depth of not less than 11/2 inches (38mm), shall be not less than 3 inches (76 mm) larger than the unit or the coil dimensions in width and length and shall be constructed of corrosion-resistant material. Galvanized sheet metal pans shall have a thickness of not less than 0.0236-inch (0.6010 mm) (No. 24 gage) galvanized sheet metal. Nonmetallic pans shall have a thickness of not less than 0.0625 inch (1.6 mm).

2. A separate overflow drain line shall be connected to the drain pan provided with the equipment. Such overflow drain shall discharge to a conspicuous point of disposal to alert occupants in the event of a stoppage of the primary drain. The overflow drain line shall connect to the drain pan at a higher level than the primary drain connection.

3. An auxiliary drain pan without a separate drain line shall be provided under the coils on which condensate will occur. Such pan shall be equipped with a water-level detection device conforming to UL 508 that will shut off the equipment served prior to overflow of the pan. The auxiliary drain pan shall be constructed in accordance with Item 1 of this section.

4. A water-level detection device conforming to UL 508 shall be provided that will shut off the equipment served in the event that the primary drain is blocked. The device shall be installed in the primary drain line, the overflow drain line or in the equipment-supplied drain pan, located at a point higher than the primary drain line connection and below the overflow rim of such pan.

Exception: Fuel-fired appliances that automatically shut down operation in the event of a stoppage in the condensate drainage system.
On down-flow units and all other coils that do not have a secondary drain or provisions to install a secondary or auxiliary drain pan, a water-level monitoring device shall be installed inside the primary drain pan. This device shall shut off the equipment served in the event that the primary drain becomes restricted. Devices installed in the drain line shall not be permitted.
Where appliances, equipment or insulation are subject to water damage when auxiliary drain pans fill such portions of the appliances, equipment and insulation shall be installed above the flood level rim of the pan. Supports located inside of the pan to support the appliance or equipment shall be water resistant and approved.
Condensate drains shall be trapped as required by the equipment or appliance manufacturer.
Ductless mini-split equipment that produces condensation shall be provided with an in-line check valve located in the drain line or a trap.
Condensate drain lines shall be configured to permit the clearing of blockages and performance of maintenance without requiring the drain line to be cut.

314.3 Enforcement

STATE AMENDMENT
Enforcement of the provisions of this section is the responsibility of the certified building official of the certified municipal, county, or township building department having jurisdiction or the superintendent of the division of industrial compliance.
The annular space between the outside of a pipe and the inside of a pipe sleeve or between the outside of a pipe and an opening in a building envelope wall, floor, or ceiling assembly penetrated by a pipe shall be sealed in an approved manner with caulking material, foam sealant or closed with a gasketing system. The caulking material, foam sealant or gasketing system shall be designed for the conditions at the penetration location and shall be compatible with the pipe, sleeve and building materials in contact with the sealing materials. Annular spaces created by pipes penetrating fire-resistance-rated assemblies or membranes of such assemblies shall be sealed or closed in accordance with Section 714 of the International Building Code.
The design, documentation, inspection, testing and approval of an alternative engineered design plumbing system shall comply with Sections 316.1.1 through 316.1.6. See Section 106.5 of the building code.

316.1.1 Design Criteria

STATE AMENDMENT
An alternative engineered design shall conform to the intent of the provisions of this code and shall provide an equivalent level of quality, strength, effectiveness, fire resistance, durability and safety. Material, equipment or components shall be designed and installed in accordance with the manufacturer's instructions.

316.1.2 Submittal

STATE AMENDMENT
The registered design professional shall indicate on the permit application that the plumbing system is an alternative engineered design. The permit and permanent permit records shall indicate that an alternative engineered design was part of the approved installation.

316.1.3 Technical Data

STATE AMENDMENT
The registered design professional shall submit sufficient technical data to substantiate the proposed alternative engineered design and to prove that the performance meets the intent of this code.
The registered design professional shall submit to the code official two complete sets of signed and sealed construction documents for the alternative engineering design. The construction documents shall include floor plans and a riser diagram of the work. Where appropriate, the construction documents shall indicate the direction of flow, all pipe sizes, grade of horizontal piping, loading and location of fixtures and appliances.

316.1.5 Design Approval

STATE AMENDMENT
Where the code official determines that the alternative engineered design conforms to the intent of this code, the plumbing system shall be approved. If the alternative engineered design is not approved, the code official shall notify the registered design professional in writing, stating the reasons thereof.
The alternative engineered design shall be tested and inspected in accordance with the requirements of Sections 107 and 312.

317.1 Scope

STATE AMENDMENT
This section, consistent with Section 4104.44 of the Revised Code, governs the requirements for welding and brazing of metallic building services (including medical gas) piping systems referenced by this code.
Each manufacturer or contractor of metallic building services piping systems is responsible for the welding and brazing done by his company or organization and shall specify and certify, in writing, a welding or brazing procedure that provides specific direction to the welder or brazer and complies with Section IX of the ASME Boiler and Pressure Vessel Code.
Each manufacturer or contractor is responsible for getting each procedure described in Section 317.2 qualified by an independent testing laboratory that has, on staff, a welding inspector certified by the "American Welding Society (AWS)." Qualification testing determines that the specified joint construction is capable of providing the required properties for its intended application. The procedure qualification record (PQR) documents what occurred during the welding or brazing of the test coupon, identifies all essential variables, and documents the test results. The manufacturer or contractor shall certify on the record that the tests were conducted in accordance with Section IX of the ASME Boiler and Pressure Vessel Code.
Each welder and brazer that performs a welding or brazing procedure as described in Section 317.2 shall be tested and qualified on that procedure as required in Section IX of the ASME Boiler and Pressure Vessel Code. The manufacturer or contractor shall certify on the performance qualification record that the welder or brazer prepared and welded or brazed the test coupons in accordance with Section IX and that the test coupons were tested by an independent testing laboratory that has, on staff, a welding inspector certified by the "American Welding Society (AWS)".
Each manufacturer or contractor of metallic building services piping systems referenced by this code who causes welding or brazing to be performed shall file with the superintendent of the division of industrial compliance in the department of commerce, or the superintendent's designee, certified copies of the welding and brazing procedure specifications, the procedure qualification records, and the welder and brazer performance qualifications of the welders and brazers used in the proposed construction of a new or altered piping system. The required documentation shall be submitted in accordance with rules adopted by the superintendent.