Part I — Administration

Part II — Definitions

Part III — Building Planning and Construction

Part IV — Energy Conservation

Part V — Mechanical

Part VI — Fuel Gas

Part VII — Plumbing

Part VIII — Electrical

Part IX — Referenced Standards

Heads up: There are no amended sections in this chapter.
The provisions of this chapter shall establish the general administrative requirements applicable to plumbing systems and inspection requirements of this code.
In addition to the general administration requirements of Chapter 1, the administrative provisions of this chapter shall also apply to the plumbing requirements of Chapters 25 through 32.
Plumbing systems lawfully in existence at the time of the adoption of this code shall be permitted to have their use and maintenance continued if the use, maintenance or repair is in accordance with the original design and if no hazard to life, health or property is created by such plumbing system.
All plumbing systems, materials and appurtenances, both existing and new, and all parts thereof shall be maintained in proper operating condition in accordance with the original design in a safe and sanitary condition.
The holder of the permit shall be responsible for the scheduling of the following inspections.
  1. Underground inspection and testing shall be made after trenches or ditches are excavated and bedded, piping installed, and before any backfill is put in place.
  2. Rough-in inspection and testing shall be made of completed portions of all sanitary, storm and water distribution piping, after the framing, fireblocking, firestopping, draftstopping and bracing for that portion is in place, and prior to the installation of wall or ceiling membranes.
  3. Final inspections and testing shall be made after the building is complete, all plumbing fixtures are in place and properly connected, and the structure is ready for occupancy.
A plumbing or drainage system, or part thereof, shall not be covered, concealed or put into use until it has been tested.
The building sewer shall be tested by insertion of a test plug at the point of connection with the public sewer and filling the building sewer with water, testing with not less than a 10-foot (3048 mm) head of water and be able to maintain such pressure for 15 minutes.
Rough and finished plumbing installations shall be tested in accordance with Sections P2503.5.1 and P2503.5.2.
DWV systems shall be tested on completion of the rough piping installation by water or air with no evidence of leakage. Plumbing system pipe shall be tested in accordance with the manufacturer's installation instructions. Either test shall be applied to the drainage system in its entirety or in sections after rough piping has been installed, as follows:
  1. Water test. Each section shall be filled with water to a point not less than 10 feet (3048 mm) above the highest fitting connection in that section, or to the highest point in the completed system. Water shall be held in the section under test for a period of 15 minutes. The system shall prove leak free by visual inspection.
  2. Air test. The portion under test shall be maintained at a gauge pressure of 5 pounds per square inch (psi) (34 kPa) or 10 inches of mercury column (34 kPa). This pressure shall be held without introduction of additional air for a period of 15 minutes.
After the plumbing fixtures have been set and their traps filled with water, their connections shall be tested and proved gas tight and/or water tight as follows:
  1. Water tightness. Each fixture shall be filled and then drained. Traps and fixture connections shall be proven water tight by visual inspection.
  2. Gas tightness. When required by the local administrative authority, a final test for gas tightness of the DWV system shall be made by the smoke or peppermint test as follows:
    1. Smoke test. Introduce a pungent, thick smoke into the system. When the smoke appears at vent terminals, such terminals shall be sealed and a pressure equivalent to a 1-inch water column (249 Pa) shall be applied and maintained for a test period of not less than 15 minutes.
    2. Peppermint test. Introduce 2 ounces (59 mL) of oil of peppermint into the system. Add 10 quarts (9464 mL) of hot water and seal all vent terminals. The odor of peppermint shall not be detected at any trap or other point in the system.
Upon completion of the water-supply system or a section of it, the system or portion completed shall be tested and proved tight under a water pressure of not less than the working pressure of the system or by an air test of not less than 50 psi (345 kPa). This pressure shall be held for not less than 15 minutes. The water used for tests shall be obtained from a potable water source. Water supply pipe shall be tested in accordance with the manufacturer's installation instructions.
Inspection and testing of backflow prevention devices shall comply with Sections P2503.7.1 and P2503.7.2.
Inspections shall be made of all backflow prevention assemblies to determine whether they are operable.
Reduced pressure principle backflow preventers, double check valve assemblies, double-detector check valve assemblies and pressure vacuum breaker assemblies shall be tested at the time of installation, immediately after repairs or relocation and at least annually.
Gauges used for testing shall be as follows:
  1. Tests requiring a pressure of 10 psi or less shall utilize a testing gauge having increments of 0.10 psi (0.69 kPa) or less.
  2. Tests requiring a pressure higher than 10 psi (0.69 kPa) but less than or equal to 100 psi (690 kPa) shall use a testing gauge having increments of 1 psi (6.9 kPa) or less.
  3. Tests requiring a pressure higher than 100 psi (690 kPa) shall use a testing gauge having increments of 2 psi (14 kPa) or less.
UpCodes Premium
Leverage the most sophisticated code compliance platform.
TRY FREE FOR TWO WEEKS VISIT PRICING