CODES

ADOPTS WITH AMENDMENTS:

International Existing Building Code 2015 (IEBC 2015)

Chapter 1 Scope and Administration

Chapter 2 Definitions

Chapter 3 Provisions for all Compliance Methods

Chapter 4 Prescriptive Compliance Method

Chapter 5 Classification of Work

Chapter 6 Repairs

Chapter 7 Alterations ‒ Level 1

Chapter 8 Alterations ‒ Level 2

Chapter 9 Alterations ‒ Level 3

Chapter 10 Change of Occupancy

Chapter 11 Additions

Chapter 12 Historic Buildings

Chapter 13 Relocated or Moved Buildings

Chapter 14 Performance Compliance Methods

Chapter 15 Construction Safeguards

Chapter 16 Referenced Standards

Appendix A Guidelines for the Seismic Retrofit of Existing Buildings

Chapter A1 Seismic Strengthening Provisions for Unreinforced Masonry Bearing Wall Buildings

Chapter A2 Earthquake Hazard Reduction in Existing Reinforced Concrete and Reinforced Masonry Wall Buildings with Flexible Diaphragms

Chapter A3 Prescriptive Provisions for Seismic Strengthening of Cripple Walls and Sill Plate Anchorage of Light, Wood-Frame Residential Buildings

Chapter A4 Earthquake Risk Reduction in Wood-Frame Residential Buildings with Soft, Weak or Open Front Walls

Chapter A5 Earthquake Hazard Reduction in Existing Concrete Buildings

Chapter A6 Referenced Standards

Resource A Guidelines on Fire Ratings of Archaic Materials and Assemblies

Level 1 alterations as described in Section 503 shall comply with the requirements of this chapter. Level 1 alterations to historic buildings shall comply with this chapter, except as modified in Chapter 12.
An existing building or portion thereof shall not be altered such that the building becomes less safe than its existing condition.

Exception: Where the current level of safety or sanitation is proposed to be reduced, the portion altered shall conform to the requirements of the International Building Code.
In flood hazard areas, alterations that constitute substantial improvement shall require that the building comply with Section 1612 of the International Building Code, or Section R322 of the International Residential Code, as applicable.
All newly installed interior wall and ceiling finishes shall comply with Chapter 8 of the International Building Code.
New interior floor finish, including new carpeting used as an interior floor finish material, shall comply with Section 804 of the International Building Code.
All newly installed interior trim materials shall comply with Section 806 of the International Building Code.
In group R-2 or R-3 buildings containing dwelling units, window opening control devices complying with ASTM F2090 shall be installed where an existing window is replaced and where all the following apply to the replacement window:
  1. The window is operable.
  2. The window replacement includes replacement of the sash and the frame.
  3. In group R-2 or R-3 buildings containing dwelling units, the top of the sill of the window opening is at a height less than 36 inches (915 mm) above the finished floor, or in one- and two-family dwellings and townhouses regulated by the international residential code, the top of the sill of the window opening is at a height less than 24 inches (610 mm) above the finished floor.
  4. The window will permit openings that will allow passage of a 4-inch diameter (102 mm) sphere when the window is in its largest opened position.
  5. The vertical distance from the top of the sill of the window opening to the finished grade or other surface below, on the exterior of the building, is greater than 72 inches (1829 mm).
     The window opening control device, after operation to release the control device allowing the window to fully open, shall not reduce the minimum net clear opening area of the window unit to less than the area required by the international building code.

Exceptions:
  1. Operable windows where the top of the sill of the window opening is located more than 75 feet (22 860 mm) above the finished grade or other surface below, on the exterior of the room, space or building, and that are provided with window fall prevention devices that comply with ASTM F2006.
  2. Operable windows with openings that are provided with window fall prevention devices that comply with ASTM F2090.
R 408.30575
Where windows are required to provide emergency escape and rescue openings in Group R-2 and R-3 occupancies and oneand two-family dwellings and townhouses regulated by the International Residential Code, replacement windows shall be exempt from the requirements of Sections 1030.2, 1030.3 and 1030.5 of the International Building Code and Sections R310.21 and R310.2.3 of the International Residential Code accordingly, provided the replacement window is the manufacturer's largest standard size window that will fit within the existing frame or existing rough opening. The replacement window shall be permitted to be of the same operating style as the existing window or a style that provides for an equal or greater window opening area than the existing window.

     Window opening control devices complying with ASTM F 2090 shall be permitted for use on windows required to provide emergency escape and rescue openings.
All new work shall comply with the materials and methods requirements in the International Building Code, International Energy Conservation Code, International Mechanical Code, and International Plumbing Code, as applicable, that specify material standards, detail of installation and connection, joints, penetrations, and continuity of any element, component, or system in the building.
The following sections of the International Fuel Gas Code shall constitute the fuel gas materials and methods requirements for Level 1 alterations.
  1. All of Chapter 3, entitled "General Regulations ," except Sections 303.7 and 306.
  2. All of Chapter 4, entitled "Gas Piping Installations," except Sections 401.8 and 402.3.

    1. Sections 401.8 and 402.3 shall apply when the work being performed increases the load on the system such that the existing pipe does not meet the size required by code. Existing systems that are modified shall not require resizing as long as the load on the system is not increased and the system length is not increased even if the altered system does not meet code minimums.
  3. All of Chapter 5, entitled "Chimneys and Vents."
  4. All of Chapter 6, entitled "Specific Appliances."
Alterations shall be done in a manner that maintains the level of fire protection provided.
Alterations shall be done in a manner that maintains the level of protection provided for the means of egress.
A building, facility, or element that is accessible shall remain accessible in accordance with the requirements of the utilization of public facilities by physically limited, 1966 PA 1, MCL 125.1351 to 125.1356, and the Michigan building code, R 408.30401 to R 408.30499.

R 408.30574
Materials and methods of application used for recovering or replacing an existing roof covering shall comply with the requirements of Chapter 15 of the International Building Code.

Exception: Reroofing shall not be required to meet the minimum design slope requirement of one-quarter unit vertical in 12 units horizontal (2-percent slope) in Section 1507 of the International Building Code for roofs that provide positive roof drainage.
Structural roof components shall be capable of supporting the roof-covering system and the material and equipment loads that will be encountered during installation of the system.
New roof coverings shall not be installed without first removing all existing layers of roof coverings down to the roof deck where any of the following conditions occur:

  1. Where the existing roof or roof covering is water soaked or has deteriorated to the point that the existing roof or roof covering is not adequate as a base for additional roofing.
  2. Where the existing roof covering is wood shake, slate, clay, cement or asbestos-cement tile.
  3. Where the existing roof has two or more applications of any type of roof covering.
Exceptions:
  1. Complete and separate roofing systems, such as standing-seam metal roof systems, that are designed to transmit the roof loads directly to the building's structural system and that do not rely on existing roofs and roof coverings for support, shall not require the removal of existing roof coverings.
  2. Metal panel, metal shingle and concrete and clay tile roof coverings shall be permitted to be installed over existing wood shake roofs when applied in accordance with Section 706.4.
  3. The application of a new protective coating over an existing spray polyurethane foam roofing system shall be permitted without tear-off of existing roof coverings.
  4. Where the existing roof assembly includes an ice barrier membrane that is adhered to the roof deck, the existing ice barrier membrane shall be permitted to remain in place and covered with an additional layer of ice barrier membrane in accordance with Section 1507 of the International Building Code.
Where the application of a new roof covering over wood shingle or shake roofs creates a combustible concealed space, the entire existing surface shall be covered with gypsum board, mineral fiber, glass fiber or other approved materials securely fastened in place.
Existing slate, clay or cement tile shall be permitted for reinstallation, except that damaged, cracked or broken slate or tile shall not be reinstalled. Existing vent flashing, metal edgings, drain outlets, collars and metal counterflashings shall not be reinstalled where rusted, damaged or deteriorated. Aggregate surfacing materials shall not be reinstalled.
Flashings shall be reconstructed in accordance with approved manufacturer's installation instructions. Metal flashing to which bituminous materials are to be adhered shall be primed prior to installation
Where alteration work includes replacement of equipment that is supported by the building or where a reroofing permit is required, the provisions of this section shall apply.
Where addition or replacement of roofing or replacement of equipment results in additional dead loads, structural components supporting such reroofing or equipment shall comply with the gravity load requirements of the International Building Code.

Exceptions:
  1. Structural elements where the additional dead load from the roofing or equipment does not increase the force in the element by more than 5 percent.
  2. Buildings constructed in accordance with the International Residential Code or the conventional light-frame construction methods of the International Building Code and where the dead load from the roofing or equipment is not increased by more than 5 percent.
  3. Addition of a second layer of roof covering weighing 3 pounds per square foot (0.1437 kN/m2) or less over an existing, single layer of roof covering.
The requirements of this section shall apply to alteration work requiring reroof permits.
Where a permit is issued for reroofing for more than 25 percent of the roof area of a building assigned to Seismic Design Category D, E or F that has parapets constructed of unreinforced masonry, the work shall include installation of parapet bracing to resist the reduced International Building Code level seismic forces as specified in Section 301.1.4.2 of this code, unless an evaluation demonstrates compliance of such items.
Where roofing materials are removed from more than 50 percent of the roof diaphragm or section of a building located where the ultimate design wind speed, Vult, determined in accordance with Figure 1609.3(1) of the International Building Code, is greater than 115 mph (51 m/s) or in a special wind region, as defined in Section 1609 of the International Building Code, roof diaphragms, connections of the roof diaphragm to roof framing members, and roof-to-wall connections shall be evaluated for the wind loads specified in the International Building Code, including wind uplift. If the diaphragms and connections in their current condition are not capable of resisting at least 75 percent of those wind loads, they shall be replaced or strengthened in accordance with the loads specified in the International Building Code.