[A] 101.1 Title

AMENDMENT
This section has been amended at the state or city level.
The 2012 International Mechanical Code and this Section shall be known as the 2012 International Mechanical Code portion of the 2016 State Building Code, hereinafter referred to as "the code" or "this code".

[A] 101.2 Scope

AMENDMENT
This section has been amended at the state or city level.
This code shall regulate the design, installation, maintenance, alteration and inspection of mechanical systems that are permanently installed and utilized to provide control of environmental conditions and related processes within buildings. This code shall also regulate those mechanical systems, system components, equipment and appliances specifically addressed herein. The installation of fuel gas distribution piping and equipment, fuel gas-fired appliances and fuel gas-fired appliance venting systems shall be in accordance with Section 101.2.2.

Exceptions:
  1. Detached one- and two-family dwellings and multiple single-family dwellings (townhouses) not more than three stories high with separate means of egress and their accessory structures shall comply with the International Residential Code.
  2. Mechanical systems in existing buildings undergoing repair, alteration, addition or change of occupancy shall be permitted to comply with the International Existing Building Code.

[A] 101.2.1 Appendices

AMENDMENT
This section has been amended at the state or city level.
The provisions of Appendix A shall be considered applicable to the utilization of this code.

101.2.2 Gas

AMENDMENT
This section has been amended at the state or city level.
The International Fuel Gas Code is not adopted by the State of Connecticut. Any references to the International Fuel Gas Code within the body of this code shall be considered references to requirements of NFPA 2, Hydrogen Technologies Code, NFPA 54, National Fuel Gas Code and NFPA 58, Liquefied Petroleum Gas Code, as incorporated in the Connecticut State Fire Safety and the Connecticut Fire Prevention Codes. These requirements apply to liquid petroleum storage systems, gas piping systems extending from the point of delivery to the inlet connections of appliances, the installation and operation of residential and commercial gas appliances and related accessories as covered by this code.

101.2.3 Oil-Burning Equipment, Piping and Storage

AMENDMENT
This section has been amended at the state or city level.
In addition to the requirements of this code, the installation of oil burners, equipment, and appliances used in connection therewith, including tanks, piping, pumps, control devices and accessories shall comply with NFPA 31, as incorporated in the Connecticut Fire Safety Code and the Connecticut Fire Prevention Code.

101.2.4 Electrical

AMENDMENT
This section has been amended at the state or city level.
The provisions of NFPA 70, National Electrical Code, shall apply to the installation of electrical systems, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances thereto.

101.2.5 Fire Prevention

AMENDMENT
This section has been amended at the state or city level.
References to the International Fire Code within the body of the model document shall be considered to be references to the Connecticut State Fire Safety Code.
The purpose of this code is to provide minimum standards to safeguard life or limb, health, property and public welfare by regulating and controlling the design, construction, installation, quality of materials, location, operation and maintenance or use of mechanical systems.
If a section, subsection, sentence, clause or phrase of this code is, for any reason, held to be unconstitutional, such decision shall not affect the validity of the remaining portions of this code.
Where there is a conflict between a general requirement and a specific requirement, the specific requirement shall govern. Where, in a specific case, different sections of this code specify different materials, methods of construction or other requirements, the most restrictive shall govern.
Except as otherwise provided for in this chapter, a provision in this code shall not require the removal, alteration or abandonment of, nor prevent the continued utilization and maintenance of, a mechanical system lawfully in existence at the time of the adoption of this code.
Mechanical systems, both existing and new, and parts thereof shall be maintained in proper operating condition in accordance with the original design and in a safe and sanitary condition. Devices or safeguards which are required by this code shall be maintained in compliance with the code edition under which they were installed. The owner or the owner's designated agent shall be responsible for maintenance of mechanical systems. To determine compliance with this provision, the code official shall have the authority to require a mechanical system to be reinspected. The inspection for maintenance of HVAC systems shall be done in accordance with ASHRAE/ACCA/ANSI Standard 180.
Additions, alterations, renovations or repairs to a mechanical system shall conform to that required for a new mechanical system without requiring the existing mechanical system to comply with all of the requirements of this code. Additions, alterations or repairs shall not cause an existing mechanical system to become unsafe, hazardous or overloaded.

Minor additions, alterations, renovations and repairs to existing mechanical systems shall meet the provisions for new construction, unless such work is done in the same manner and arrangement as was in the existing system, is not hazardous and is approved.

It shall be unlawful to make a change in the occupancy of any structure which will subject the structure to any special provision of this code applicable to the new occupancy without approval. The code official shall certify that such structure meets the intent of the provisions of law governing building construction for the proposed new occupancy and that such change of occupancy does not result in any hazard to the public health, safety or welfare.

[A] 102.6 Historic Buildings

AMENDMENT
This section has been amended at the state or city level.
Pursuant to section 29-259 of the Connecticut General Statutes, exemptions may be granted to the provisions of this code for historic structures, as defined by section 10-410 of the Connecticut General Statutes, which have been classified as such in the State Register of Historic Places, as long as the provisions of subsection (b) of section 29-259 of the Connecticut General Statutes are adhered to and provided that such exemptions shall not affect the safe design, use or construction of such property.
Except as determined by Section 102.2, mechanical systems that are a part of buildings or structures moved into or within the jurisdiction shall comply with the provisions of this code for new installations.
The codes and standards referenced herein shall be those that are listed in Chapter 15 and such codes and standards shall be considered as part of the requirements of this code to the prescribed extent of each such reference and as further regulated in Sections 102.8.1 and 102.8.2.
Exception: Where enforcement of a code provision would violate the conditions of the listing of the equipment or appliance, the conditions of the listing and the manufacturer's installation instructions shall apply.
Where conflicts occur between provisions of this code and the referenced standards, the provisions of this code shall apply.
Where the extent of the reference to a referenced code or standard includes subject matter that is within the scope of this code, the provisions of this code, as applicable, shall take precedence over the provisions in the referenced code or standard.
Requirements necessary for the strength, stability or proper operation of an existing or proposed mechanical system, or for the public safety, health and general welfare, not specifically covered by this code, shall be determined by the code official.
The provisions of this code shall not be deemed to nullify any provisions of local, state or federal law.
Reference to chapter section numbers, or to provisions not specifically identified by number, shall be construed to refer to such chapter, section or provision of this code.

Part 2 — Administration and Enforcement

Section 103 Department of Mechanical Inspection

AMENDMENT
This section has been amended at the state or city level.

Section 103 Enforcement Agency

AMENDMENT
This section has been amended at the state or city level.

[A] 103.1 General

AMENDMENT
This section has been amended at the state or city level.

103.1 Creation of Enforcement Agency

AMENDMENT
This section has been amended at the state or city level.
Each town, city and borough shall create an agency whose function is to enforce the provisions of this code. The official in charge thereof shall be known as the building official.

[A] 103.2 Appointment

AMENDMENT
This section has been amended at the state or city level.

103.2 Appointment

AMENDMENT
This section has been amended at the state or city level.
The chief executive officer of any town, city or borough shall appoint an officer to administer this code, and this officer shall be known as the "building official" in accordance with section 29-260 of the Connecticut General Statutes, and referred to herein as the building official, local building official, or code official.

[A] 103.3 Deputies

AMENDMENT
This section has been amended at the state or city level.

103.3 Employees

AMENDMENT
This section has been amended at the state or city level.
In accordance with the prescribed procedures and regulations of the town, city or borough and with the concurrence of the appointing authority, the building official shall have the authority to appoint an assistant building official, related technical officers, inspectors, plan examiners and other employees. Such employees shall have the powers as regulated by the town, city or borough, and by the State of Connecticut.

[A] 103.4 Liability

AMENDMENT
This section has been amended at the state or city level.

103.4 Restriction of Employees

AMENDMENT
This section has been amended at the state or city level.
An official or employee connected with the agency created to enforce the provisions of this code pursuant to Section 103.1, except one whose only connection with it is that of a member of the board of appeals established under the provisions of Section 109, shall not be engaged in or directly or indirectly connected with the furnishing of labor, materials or appliances for the construction, addition, alteration, repair or maintenance of a building located in the town, city or borough in which such official or employee is employed, or the preparation of construction documents therefore, unless that person is the owner of the building. Such officer or employee shall not engage in any work that conflicts with official duties or with the interests of the agency.

Section 104 Duties and Powers of the Code Official

AMENDMENT
This section has been amended at the state or city level.

[A] 104.1 General

AMENDMENT
This section has been amended at the state or city level.

[A] 104.2 Applications and Permits

AMENDMENT
This section has been amended at the state or city level.

[A] 104.3 Inspections

AMENDMENT
This section has been amended at the state or city level.

[A] 104.4 Right of Entry

AMENDMENT
This section has been amended at the state or city level.

[A] 104.5 Identification

AMENDMENT
This section has been amended at the state or city level.

[A] 104.6 Notices and Orders

AMENDMENT
This section has been amended at the state or city level.

[A] 104.7 Department Records

AMENDMENT
This section has been amended at the state or city level.

Section 104 Duties and Powers of Building Official

AMENDMENT
This section has been amended at the state or city level.

104.1 General

AMENDMENT
This section has been amended at the state or city level.
The duties and powers of the building official shall be in accordance with the provisions of Sections 104.1 through 104.8 of the International Building Code portion of the State Building Code.

[A] 105.1 Modifications

AMENDMENT
This section has been amended at the state or city level.
The State Building Inspector may grant modifications, variations or exemptions from, or approve equivalent or alternative compliance with, the State Building Code where strict compliance with the State Building Code would entail practical difficulty or unnecessary hardship, or is otherwise adjudged unwarranted, provided the intent of the law shall be observed and public welfare and safety be assured. Any person aggrieved by any decision of the State Building Inspector may appeal to the Codes and Standards Committee within 30 days after mailing of the decision

105.1.1 Action on Application

AMENDMENT
This section has been amended at the state or city level.
The application for modification, variation, exemption from or approval of equivalent or alternative compliance with the requirements of the State Building Code shall be made on a form supplied by the State Building Inspector available from the local building official or the Office of the State Building Inspector, which shall be forwarded by the applicant to the local building official. Any such application received by a local building official shall be forwarded to the State Building Inspector within 15 business days of receipt by such local building official. The application shall include the local building official's comments on the merits of the application, and shall be signed by the local building official, acting building official or provisional building official.

105.1.2 Records

AMENDMENT
This section has been amended at the state or city level.
The application for modification, variation, exemption or approval of equivalent or alternative compliance and the decision of the State Building Inspector shall be in writing and shall be officially recorded with the application for a building permit in the permanent records of the building department.

105.1.3 Accessibility Exemption

AMENDMENT
This section has been amended at the state or city level.
Any variation of or exemption from any provisions relating to accessibility to, use of and egress from, buildings and structures as required herein shall be permitted only when approved by the State Building Inspector and the Executive Director of the Office of Protection and Advocacy for Persons with Disabilities, acting jointly, pursuant to subsection (b) of section 29-269 of the Connecticut General Statutes. Any person aggrieved by the joint decision of the State Building Inspector and the Executive Director of the Office of Protection and Advocacy for Persons with Disabilities may appeal to the Codes and Standards Committee within 30 days after such decision has been rendered in accordance with subsection (b) of section 29-269 of the Connecticut General Statutes.
The provisions of this code are not intended to prevent the installation of any material or to prohibit any method of construction not specifically prescribed by this code, provided that any such alternative has been approved. An alternative material or method of construction shall be approved where the code official finds that the proposed design is satisfactory and complies with the intent of the provisions of this code, and that the material, method or work offered is, for the purpose intended, at least the equivalent of that prescribed in this code in quality, strength, effectiveness, fire resistance, durability and safety.
Supporting data, where necessary to assist in the approval of materials or assemblies not specifically provided for in this code, shall consist of valid research reports from approved sources.
Whenever there is insufficient evidence of compliance with the provisions of this code, or evidence that a material or method does not conform to the requirements of this code, or in order to substantiate claims for alternative materials or methods, the code official shall have the authority to require tests as evidence of compliance to be made at no expense to the jurisdiction.
Test methods shall be as specified in this code or by other recognized test standards. In the absence of recognized and accepted test methods, the code official shall approve the testing procedures.
All tests shall be performed by an approved agency.
Reports of tests shall be retained by the code official for the period required for retention of public records.
Materials, equipment and devices approved by the code official shall be constructed and installed in accordance with such approval.
Materials, equipment, appliances and devices shall not be reused unless such elements have been reconditioned, tested and placed in good and proper working condition and approved.

[A] 106.1 When Required

AMENDMENT
This section has been amended at the state or city level.
Any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to move a lot line that will affect any existing building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by this code, or to cause any such work to be done, shall first make application to the building official and obtain the required permit.

106.1.1 By Whom Application Is Made

AMENDMENT
This section has been amended at the state or city level.
Pursuant to section 29-263 of the Connecticut General Statutes, application for a permit shall be made by the owner in fee or by an authorized agent. If the authorized agent is a licensed contractor, the provisions of section 20-338b of the Connecticut General Statutes shall be followed. The full names and addresses of the owner, agent and the responsible officers, if the owner or agent is a corporate body, shall be stated in the application. No permit shall be issued to a contractor who is required to be registered pursuant to chapter 400 of the Connecticut General Statutes, for work to be performed by such contractor, unless the name, business address and Department of Consumer Protection registration number of such contractor is clearly marked on the application for permit, and the contractor has presented such contractor's certificate of registration as a home improvement contractor.
Permits shall not be required for the following:
  1. Portable heating appliances;
  2. Portable ventilation appliances and equipment;
  3. Portable cooling units;
  4. Steam, hot water or chilled water piping within any heating or cooling equipment or appliances regulated by this code;
  5. The replacement of any minor part that does not alter the approval of equipment or an appliance or make such equipment or appliance unsafe;
  6. Portable evaporative coolers;
  7. Self-contained refrigeration systems that contain 10 pounds (4.5 kg) or less of refrigerant, or that are actuated by motors of 1 horsepower (0.75 kW) or less; and
  8. Portable fuel cell appliances that are not connected to a fixed piping system and are not interconnected to a power grid.

Exemption from the permit requirements of this code shall not be deemed to grant authorization for work to be done in violation of the provisions of this code or other laws or ordinances of this jurisdiction.

106.2.1 State Agency Exemptions

AMENDMENT
This section has been amended at the state or city level.
A state agency shall not be required to obtain a building permit from the local building official. A state agency shall obtain a building permit for construction or alteration of state buildings or structures from the State Building Inspector in accordance with the provisions of section 29-252a of the Connecticut General Statutes.
Each application for a permit, with the required fee, shall be filed with the code official on a form furnished for that purpose and shall contain a general description of the proposed work and its location. The application shall be signed by the owner or an authorized agent. The permit application shall indicate the proposed occupancy of all parts of the building and of that portion of the site or lot, if any, not covered by the building or structure and shall contain such other information required by the code official.
Construction documents, engineering calculations, diagrams and other data shall be submitted in two or more sets with each application for a permit. The code official shall require construction documents, computations and specifications to be prepared and designed by a registered design professional when required by state law. Where special conditions exist, the code official is authorized to require additional construction documents to be prepared by a registered design professional. Construction documents shall be drawn to scale and shall be of sufficient clarity to indicate the location, nature and extent of the work proposed and show in detail that the work conforms to the provisions of this code. Construction documents for buildings more than two stories in height shall indicate where penetrations will be made for mechanical systems, and the materials and methods for maintaining required structural safety, fire-resistance rating and fireblocking.
Exception: The code official shall have the authority to waive the submission of construction documents, calculations or other data if the nature of the work applied for is such that reviewing of construction documents is not necessary to determine compliance with this code.
Before a permit is issued, the code official is authorized to inspect and evaluate the systems, equipment, buildings, devices, premises and spaces or areas to be used.
An application for a permit for any proposed work shall be deemed to have been abandoned 180 days after the date of filing, unless such application has been pursued in good faith or a permit has been issued; except that the code official shall have the authority to grant one or more extensions of time for additional periods not exceeding 180 days each. The extension shall be requested in writing and justifiable cause demonstrated.

[A] 106.4 Permit Issuance

AMENDMENT
This section has been amended at the state or city level.
The building official shall examine or cause to be examined applications for permits and amendments thereto within 30 days after filing and either issue or deny a permit within such 30-day period. If the application or construction documents do not conform to the requirements of this code and pertinent laws, the building official shall reject such application in writing, stating the reasons therefore. If the building official is satisfied that the proposed work conforms to the requirements of this code and applicable laws, statutes, regulations and ordinances, the building official shall issue a permit therefore as soon as practicable.
When the code official issues the permit where construction documents are required, the construction documents shall be endorsed in writing and stamped "APPROVED." Such approved construction documents shall not be changed, modified or altered without authorization from the code official. Work shall be done in accordance with the approved construction documents.

The code official shall have the authority to issue a permit for the construction of part of a mechanical system before the construction documents for the entire system have been submitted or approved, provided adequate information and detailed statements have been filed complying with all pertinent requirements of this code. The holder of such permit shall proceed at his or her own risk without assurance that the permit for the entire mechanical system will be granted.
The issuance of a permit or approval of construction documents shall not be construed to be a permit for, or an approval of, any violation of any of the provisions of this code or of other ordinances of the jurisdiction. A permit presuming to give authority to violate or cancel the provisions of this code shall be invalid.

The issuance of a permit based upon construction documents and other data shall not prevent the code official from thereafter requiring the correction of errors in said construction documents and other data or from preventing building operations from being carried on thereunder when in violation of this code or of other ordinances of this jurisdiction.
Every permit issued by the code official under the provisions of this code shall expire by limitation and become null and void if the work authorized by such permit is not commenced within 180 days from the date of such permit, or if the work authorized by such permit is suspended or abandoned at any time after the work is commenced for a period of 180 days. Before such work recommences, a new permit shall be first obtained and the fee, therefore, shall be one-half the amount required for a new permit for such work, provided no changes have been made or will be made in the original construction documents for such work, and provided further that such suspension or abandonment has not exceeded one year.
A permittee holding an unexpired permit shall have the right to apply for an extension of the time within which the permittee will commence work under that permit when work is unable to be commenced within the time required by this section for good and satisfactory reasons. The code official shall extend the time for action by the permittee for a period not exceeding 180 days if there is reasonable cause. A permit shall not be extended more than once. The fee for an extension shall be one-half the amount required for a new permit for such work.
The code official shall have the authority to suspend or revoke a permit issued under the provisions of this code wherever the permit is issued in error or on the basis of incorrect, inaccurate or incomplete information, or in violation of any ordinance or regulation or any of the provisions of this code.

[A] 106.4.6 Retention of Construction Documents

AMENDMENT
This section has been amended at the state or city level.
The building official shall retain one set of approved construction documents for a period as set forth in the records/disposition schedule adopted pursuant to chapter 188 of the Connecticut General Statutes.

Exception: In accordance with the provisions of subsection (e) of section 29-261 of the Connecticut General Statutes, upon receipt of a written request signed by the owner of plans and specifications on file for a single-family dwelling or out-building, the building official shall immediately return the original plans and specifications to the owner after a certificate of occupancy is issued with respect to the plans and specifications.
This code shall not require changes in the construction documents, construction or designated occupancy of a structure for which a lawful permit has been heretofore issued or otherwise lawfully authorized, and the construction of which has been pursued in good faith within 180 days after the effective date of this code and has not been abandoned.
The permit or a copy shall be kept on the site of the work until the completion of the project.
A permit shall not be issued until the fees prescribed in Section 106.5.2 have been paid, nor shall an amendment to a permit be released until the additional fee, if any, due to an increase of the mechanical system, has been paid.

[A] 106.5.1 Work Commencing Before Permit Issuance

AMENDMENT
This section has been amended at the state or city level.

[A] 106.5.2 Fee Schedule

AMENDMENT
This section has been amended at the state or city level.
Each municipality shall establish a schedule of fees for each construction document review, building permit, certificate of approval and certificate of occupancy. A schedule of adopted fees shall be posted in the building department for public view.

[A] 106.5.3 Fee Refunds

AMENDMENT
This section has been amended at the state or city level.
The building official is authorized to establish a refund policy.
The code official is authorized to conduct such inspections as are deemed necessary to determine compliance with the provisions of this code. Construction or work for which a permit is required shall be subject to inspection by the code official, and such construction or work shall remain accessible and exposed for inspection purposes until approved. Approval as a result of an inspection shall not be construed to be an approval of a violation of the provisions of this code or of other ordinances of the jurisdiction. Inspections presuming to give authority to violate or cancel the provisions of this code or of other ordinances of the jurisdiction shall not be valid.
The code official, upon notification from the permit holder or the permit holder's agent, shall make the following inspections and other such inspections as necessary, and shall either release that portion of the construction or shall notify the permit holder or the permit holder's agent of violations that must be corrected. The holder of the permit shall be responsible for the scheduling of such inspections.
  1. Underground inspection shall be made after trenches or ditches are excavated and bedded, piping installed, and before backfill is put in place. When excavated soil contains rocks, broken concrete, frozen chunks and other rubble that would damage or break the piping or cause corrosive action, clean backfill shall be on the job site.
  2. Rough-in inspection shall be made after the roof, framing, fireblocking and bracing are in place and all ducting and other components to be concealed are complete, and prior to the installation of wall or ceiling membranes.
  3. Final inspection shall be made upon completion of the mechanical system.
Exception: Ground-source heat pump loop systems tested in accordance with Section 1208.1.1 shall be permitted to be backfilled prior to inspection.

The requirements of this section shall not be considered to prohibit the operation of any heating equipment or appliances installed to replace existing heating equipment or appliances serving an occupied portion of a structure provided that a request for inspection of such heating equipment or appliances has been filed with the department not more than 48 hours after such replacement work is completed, and before any portion of such equipment or appliances is concealed by any permanent portion of the structure.

In addition to the inspections specified above, the code official is authorized to make or require other inspections of any construction work to ascertain compliance with the provisions of this code and other laws that are enforced.
It shall be the duty of the holder of the permit or their duly authorized agent to notify the code official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspections of such work that are required by this code.
Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the code official. The code official, upon notification, shall make the requested inspections and shall either indicate the portion of the construction that is satisfactory as completed, or notify the permit holder or his or her agent wherein the same fails to comply with this code. Any portions that do not comply shall be corrected and such portion shall not be covered or concealed until authorized by the code official.
The code official is authorized to accept reports of approved agencies, provided that such agencies satisfy the requirements as to qualifications and reliability.
Prior to the approval of a prefabricated construction assembly having concealed mechanical work and the issuance of a mechanical permit, the code official shall require the submittal of an evaluation report on each prefabricated construction assembly, indicating the complete details of the mechanical system, including a description of the system and its components, the basis upon which the system is being evaluated, test results and similar information, and other data as necessary for the code official to determine conformance to this code.
The code official shall designate the evaluation service of an approved agency as the evaluation agency, and review such agency's evaluation report for adequacy and conformance to this code.
Except where ready access is provided to mechanical systems, service equipment and accessories for complete inspection at the site without disassembly or dismantling, the code official shall conduct the in-plant inspections as frequently as necessary to ensure conformance to the approved evaluation report or shall designate an independent, approved inspection agency to conduct such inspections. The inspection agency shall furnish the code official with the follow-up inspection manual and a report of inspections upon request, and the mechanical system shall have an identifying label permanently affixed to the system indicating that factory inspections have been performed.
Required test and inspection records shall be available to the code official at all times during the fabrication of the mechanical system and the erection of the building; or such records as the code official designates shall be filed.

107.2.6 Posting of Required Inspections

AMENDMENT
This section has been amended at the state or city level.
A schedule of required inspections shall be compiled by the code official. The schedule shall be posted in the building department for public view.
Mechanical systems shall be tested as required in this code and in accordance with Sections 107.3.1 through 107.3.3. Tests shall be made by the permit holder and observed by the code official.
New mechanical systems and parts of existing systems, which have been altered, extended, renovated or repaired, shall be tested as prescribed herein to disclose leaks and defects.
Apparatus, material and labor required for testing a mechanical system or part thereof shall be furnished by the permit holder.
Where any work or installation does not pass an initial test or inspection, the necessary corrections shall be made so as to achieve compliance with this code. The work or installation shall then be resubmitted to the code official for inspection and testing.
After the prescribed tests and inspections indicate that the work complies in all respects with this code, a notice of approval shall be issued by the code official.
The code official is authorized to, in writing, suspend or revoke a notice of approval issued under the provisions of this code wherever the notice is issued in error, on the basis of incorrect information supplied, or where it is determined that the building or structure, premise or portion thereof is in violation of any ordinance or regulation or any of the provisions of this code.
The code official shall have the authority to authorize the temporary connection of a mechanical system to the sources of energy for the purpose of testing mechanical systems or for use under a temporary certificate of occupancy.
No person shall make connections from a utility, source of energy, fuel or power to any building or system that is regulated by this code for which a permit is required, until authorized by the code official.

107.7 Notification of Inspection and Testing Results

AMENDMENT
This section has been amended at the state or city level.
Notification as to passage or failure, in whole or in part, of any required inspection or test shall be made in writing by the building official or his duly authorized representative and shall be left at the job site or delivered to the permit holder. It shall be the duty of the permit holder to ascertain the results of required inspections.
It shall be unlawful for a person, firm or corporation to erect, construct, alter, repair, remove, demolish or utilize a mechanical system, or cause same to be done, in conflict with or in violation of any of the provisions of this code.
The code official shall serve a notice of violation or order to the person responsible for the erection, installation, alteration, extension, repair, removal or demolition of mechanical work in violation of the provisions of this code, or in violation of a detail statement or the approved construction documents thereunder, or in violation of a permit or certificate issued under the provisions of this code. Such order shall direct the discontinuance of the illegal action or condition and the abatement of the violation.
If the notice of violation is not complied with promptly, the code official shall request the legal counsel of the jurisdiction to institute the appropriate proceeding at law or in equity to restrain, correct or abate such violation, or to require the removal or termination of the unlawful occupancy of the structure in violation of the provisions of this code or of the order or direction made pursuant thereto.

[A] 108.4 Violation Penalties

AMENDMENT
This section has been amended at the state or city level.
Any person who violates any provision of this code shall be fined not less than two hundred nor more than one thousand dollars or imprisoned not more than six months or both, pursuant to section 29-254a of the Connecticut General Statutes.

[A] 108.5 Stop Work Orders

AMENDMENT
This section has been amended at the state or city level.
Upon notice from the building official, work on any mechanical system that is being done contrary to the provisions of this code or in a dangerous or unsafe manner shall immediately cease. Such notice shall be in writing and shall be given to the owner of the property, or to the owner's agent, or to the person doing the work. The notice shall state the conditions under which the work is authorized to resume. Where an emergency exists, the building official shall not be required to give a written notice prior to stopping the work. Any person who shall continue any work in or about the structure after having been served with a stop work order, except such work as that person is directed to perform to remove a violation or unsafe condition, shall be liable for penalties in accordance with Section 108.4.
The imposition of the penalties herein prescribed shall not preclude the legal officer of the jurisdiction from instituting appropriate action to prevent unlawful construction or to restrain, correct or abate a violation, or to prevent illegal occupancy of a building, structure or premises, or to stop an illegal act, conduct, business or utilization of the mechanical system on or about any premises.
A mechanical system that is unsafe, constitutes a fire or health hazard, or is otherwise dangerous to human life, as regulated by this code, is hereby declared as an unsafe mechanical system. Use of a mechanical system regulated by this code constituting a hazard to health, safety or welfare by reason of inadequate maintenance, dilapidation, fire hazard, disaster, damage or abandonment is hereby declared an unsafe use. Such unsafe equipment and appliances are hereby declared to be a public nuisance and shall be abated by repair, rehabilitation, demolition or removal.
Whenever the code official determines that any mechanical system, or portion thereof, regulated by this code has become hazardous to life, health, property, or has become insanitary, the code official shall order in writing that such system either be removed or restored to a safe condition. A time limit for compliance with such order shall be specified in the written notice. A person shall not use or maintain a defective mechanical system after receiving such notice.

When such mechanical system is to be disconnected, written notice as prescribed in Section 108.2 shall be given. In cases of immediate danger to life or property, such disconnection shall be made immediately without such notice.
The code official shall have the authority to order disconnection of energy sources supplied to a building, structure or mechanical system regulated by this code, when it is determined that the mechanical system or any portion thereof has become hazardous or unsafe. Written notice of such order to disconnect service and the causes therefor shall be given within 24 hours to the owner and occupant of such building, structure or premises, provided, however, that in cases of immediate danger to life or property, such disconnection shall be made immediately without such notice. Where energy sources are provided by a public utility, the code official shall immediately notify the serving utility in writing of the issuance of such order to disconnect.
A person shall not make energy source connections to mechanical systems regulated by this code which have been disconnected or ordered to be disconnected by the code official, or the use of which has been ordered to be discontinued by the code official until the code official authorizes the reconnection and use of such mechanical systems.

When a mechanical system is maintained in violation of this code, and in violation of a notice issued pursuant to the provisions of this section, the code official shall institute appropriate action to prevent, restrain, correct or abate the violation.

Section 109 Means of Appeal

AMENDMENT
This section has been amended at the state or city level.

[A] 109.1 Application for Appeal

AMENDMENT
This section has been amended at the state or city level.

[A] 109.1.1 Limitation of Authority

AMENDMENT
This section has been amended at the state or city level.

[A] 109.2 Membership of Board

AMENDMENT
This section has been amended at the state or city level.

[A] 109.2.1 Qualifications

AMENDMENT
This section has been amended at the state or city level.

[A] 109.2.2 Alternate Members

AMENDMENT
This section has been amended at the state or city level.

[A] 109.2.3 Chairman

AMENDMENT
This section has been amended at the state or city level.

[A] 109.2.4 Disqualification of Member

AMENDMENT
This section has been amended at the state or city level.

[A] 109.2.5 Secretary

AMENDMENT
This section has been amended at the state or city level.

[A] 109.2.6 Compensation of Members

AMENDMENT
This section has been amended at the state or city level.

[A] 109.3 Notice of Meeting

AMENDMENT
This section has been amended at the state or city level.

[A] 109.4 Open Hearing

AMENDMENT
This section has been amended at the state or city level.

[A] 109.4.1 Procedure

AMENDMENT
This section has been amended at the state or city level.

[A] 109.5 Postponed Hearing

AMENDMENT
This section has been amended at the state or city level.

[A] 109.6 Board Decision

AMENDMENT
This section has been amended at the state or city level.

[A] 109.6.1 Resolution

AMENDMENT
This section has been amended at the state or city level.

[A] 109.6.2 Administration

AMENDMENT
This section has been amended at the state or city level.

[A] 109.7 Court Review

AMENDMENT
This section has been amended at the state or city level.

Section 109 Means of Appeal

AMENDMENT
This section has been amended at the state or city level.

109.1 Means of Appeal

AMENDMENT
This section has been amended at the state or city level.
Means of appeal shall be in accordance with Section 113 of the 2012 International Building Code portion of the State Building Code.
The code official is authorized to issue a permit for temporary equipment, systems and uses. Such permits shall be limited as to time of service, but shall not be permitted for more than 180 days. The code official is authorized to grant extensions for demonstrated cause.
Temporary equipment, systems and uses shall conform to the structural strength, fire safety, means of egress, accessibility, light, ventilation and sanitary requirements of this code as necessary to ensure the public health, safety and general welfare.
The code official is authorized to give permission to temporarily supply utilities before an installation has been fully completed and the final certificate of completion has been issued. The part covered by the temporary certificate shall comply with the requirements specified for temporary lighting, heat or power in the code.
The code official is authorized to terminate such permit for temporary equipment, systems or uses and to order the temporary equipment, systems or uses to be discontinued.
UpCodes Premium
Leverage the most sophisticated code compliance platform.
TRY FREE FOR TWO WEEKS VISIT PRICING