Chapter 16 Structural Design

Chapter 16A Structural Design

Chapter 17 Special Inspections and Tests

Chapter 17A Special Inspections and Tests

Chapter 18 Soils and Foundations

Chapter 18A Soils and Foundations

Chapter 19 Concrete

Chapter 19A Concrete

Chapter 20 Aluminum

Chapter 21 Masonry

Chapter 21A Masonry

Chapter 22 Steel

Chapter 22A Steel

Chapter 23 Wood

Chapter 24 Glass and Glazing

Chapter 25 Gypsum Board, Gypsum Panel Products and Plaster

Chapter 26 Plastic

Chapter 27 Electrical

Chapter 28 Mechanical Systems

Chapter 29 Plumbing Systems

Chapter 30 Elevators and Conveying Systems

Chapter 31 Special Construction

Chapter 31A Systems for Window Cleaning or Exterior Building Maintenance

Chapter 31B [DPH] Public Pools

Chapter 31C [DPH] Radiation

Chapter 31D [DPH] Food Establishments

Chapter 31E Reserved

Chapter 31F [SLC] Marine Oil Terminals

Chapter 32 Encroachments Into the Public Right-Of-Way

Chapter 33 Safeguards During Construction

Chapter 34 Reserved

Chapter 34A Existing Structures

Chapter 35 Referenced Standards

Appendix A Employee Qualifications

Appendix B Board of Appeals

Appendix C Group U—agricultural Buildings

Appendix D Fire Districts

Appendix E Reserved

Appendix F Rodentproofing

Appendix G Flood-Resistant Construction

Appendix H Signs

History Note Appendix

Appendix I Patio Covers

Appendix J Grading

Appendix K Group R-3 and Group R-3.1 Occupancies Protected by the Facilities of the Central Valley Flood Protection Plan

Appendix L Earthquake Recording Instrumentation

Appendix M Tsunami-Generated Flood Hazard

The provisions of this chapter shall govern the quality, workmanship and requirements for materials covered. Materials of construction and tests shall conform to the applicable standards listed in this code.

The scope of application of Chapter 17A is as follows:

  1. Structures regulated by the Division of the State Architect-Structural Safety, which include those applications listed in Sections 1.9.2.1 (DSA-SS), and 1.9.2.2 (DSA-SS/CC). These applications include public elementary and secondary schools, community colleges and state-owned or state-leased essential services buildings.
  2. Structures regulated by the Office of Statewide Health Planning and Development (OSHPD), which include those applications listed in Sections 1.10.1, and 1.10.4. These applications include hospitals, skilled nursing facilities, intermediate care facilities and correctional treatment centers.

    Exception: [OSHPD 2] Single-story Type V skilled nursing or intermediate care facilities utilizing wood-frame or light-steel-frame construction as defined in Health and Safety Code Section 129725, which shall comply with Chapter 17 and any applicable amendments therein.

DSA-SS adopts this chapter and all amendments.

Exceptions: Amendments adopted by only one agency appear in this chapter preceded with the appropriate acronym of the adopting agency, as follows:

  1. Division of the State Architect - Structural Safety:

    [DSA-SS] For applications listed in Section 1.9.2.1.

    [DSA-SS/CC] For applications listed in Section 1.9.2.2.

  2. Office of Statewide Health Planning and Development:

    [OSHPD 1] – For applications listed in Section 1.10.1.

    [OSHPD 4] – For applications listed in Section 1.10.4.

[DSA-SS/CC] Where reference within this chapter is made to sections in Chapters 16A, 19A, 21A, and 22A, the provisions in Chapters 16, 19, 21 and 22, respectively, shall apply instead.

New building materials, equipment, appliances, systems or methods of construction not provided for in this code, and any material of questioned suitability proposed for use in the construction of a building or structure, shall be subjected to the tests prescribed in this chapter and in the approved rules to determine character, quality and limitations of use.

[OSHPD 1 and 4] In addition to the inspector(s) of record required by the California Administrative Code (CCR, Title 24, Part 1), Section 7-144, the owner shall employ one or more approved agencies to provide special inspections and tests during construction on the types of work listed under Chapters 17A, 18A, 19A, 20, 21A, 22A, 23, 25, 34A, and noted in the Test, Inspection, and Observation (TIO) program required by Sections 7-141, 7-145 and 7-149, of the California Administrative Code. Test, Inspection and Observation (TIO) program shall satisfy requirements of Section 1704A.

[DSA-SS & DSA-SS/ CC] In addition to the project inspector required by the California Administrative Code (CCR, Title 24, Part 1), Section 4-333, the owner shall employ one or more approved agencies to provide special inspections and tests as required by the enforcement agency during construction on the types of work listed under Chapters 17A, 18A, 19A, 20, 21A, 22A, 23, and 25 and the California Existing Building Code and noted in the special test, inspection and observation plan required by Section 4-335 of the California Administrative Code.

The following terms are defined in Chapter 2, except those defined below which shall, for the purposes of this chapter, have the meanings shown herein.

APPROVED AGENCY.

APPROVED FABRICATOR.

CERTIFICATE OF COMPLIANCE.

DESIGNATED SEISMIC SYSTEM.

FABRICATED ITEM.

INTUMESCENT FIRE-RESISTANT COATINGS.

MAIN WINDFORCE-RESISTING SYSTEM.

MASTIC FIRE-RESISTANT COATINGS.

PROJECT INSPECTOR. [DSA-SS, DSA-SS/CC] The person approved to provide inspection in accordance with the California Administrative Code, Section 4-333(b). The term “project inspector” is synonymous with “inspector of record.”

Quality Assurance (QA). Special inspections and testing provided by an approved agency employed by the Owner. Project specific testing required by approved construction documents shall be performed by the approved agency responsible for Quality Assurance (QA), unless approved otherwise by the building official.

Quality Control (QC). Inspections and materials/functionality testing provided by the fabricator, erector, manufacturer or other responsible contractor as applicable.

SPECIAL INSPECTION.

Continuous special inspection. The full-time observation of work requiring special inspection by an approved special inspector who is present in the area where the work is being performed.

Periodic special inspection.The part-time or intermittent observation of work requiring special inspection by an approved special inspector who is present in the area where the work has been or is being performed and at the completion of the work.

  • SPECIAL INSPECTOR.
  • SPRAYED FIRE-RESISTANT MATERIALS.
  • STRUCTURAL OBSERVATION.
An approved agency shall provide all information as necessary for the building official to determine that the agency meets the applicable requirements specified in Sections 1703A.1.1 through 1703A.1.3.
An approved agency shall be objective, competent and independent from the contractor responsible for the work being inspected. The agency shall also disclose to the building official and the registered design professional in responsible charge possible conflicts of interest so that objectivity can be confirmed.
An approved agency shall have adequate equipment to perform required tests. The equipment shall be periodically calibrated.
An approved agency shall employ experienced personnel educated in conducting, supervising and evaluating tests and special inspections.
Any material, appliance, equipment, system or method of construction meeting the requirements of this code shall be approved in writing after satisfactory completion of the required tests and submission of required test reports.
For any material, appliance, equipment, system or method of construction that has been approved, a record of such approval, including the conditions and limitations of the approval, shall be kept on file in the building official’s office and shall be available for public review at appropriate times.

Specific information consisting of test reports conducted by an approved agency in accordance with the appropriate referenced standards, or other such information as necessary, shall be provided for the building official to determine that the product, material or assembly meets the applicable code requirements.

[OSHPD 1 & 4] Tests performed by an independent approved testing agency/laboratory having accreditation to the International Standards Organization (ISO) accreditation Standard 17025 or under the responsible charge of a competent approved independent Registered Design Professional shall be deemed to comply with requirements of this section. Test reports for structural tests shall be reviewed and accepted by an independent California licensed structural engineer.

Sufficient technical data shall be submitted to the building official to substantiate the proposed use of any product, material or assembly. If it is determined that the evidence submitted is satisfactory proof of performance for the use intended, the building official shall approve the use of the product, material or assembly subject to the requirements of this code. The costs, reports and investigations required under these provisions shall be paid by the owner or the owner’s authorized agent.
Supporting data, where necessary to assist in the approval of products, materials or assemblies not specifically provided for in this code, shall consist of valid research reports from approved sources.
Products, materials or assemblies required to be labeled shall be labeled in accordance with the procedures set forth in Sections 1703A.5.1 through 1703A.5.4.
An approved agency shall test a representative sample of the product, material or assembly being labeled to the relevant standard or standards. The approved agency shall maintain a record of the tests performed. The record shall provide sufficient detail to verify compliance with the test standard.
The approved agency shall periodically perform an inspection, which shall be in-plant if necessary, of the product or material that is to be labeled. The inspection shall verify that the labeled product, material or assembly is representative of the product, material or assembly tested.
The label shall contain the manufacturer’s identification, model number, serial number or definitive information describing the performance characteristics of the product, material or assembly and the approved agency’s identification.
Information required to be permanently identified on the product, material or assembly shall be acid etched, sand blasted, ceramic fired, laser etched, embossed or of a type that, once applied, cannot be removed without being destroyed.
Where structural components or other items regulated by this code are not visible for inspection after completion of a prefabricated assembly, the owner or the owner’s authorized agent shall submit a report of each prefabricated assembly. The report shall indicate the complete details of the assembly, including a description of the assembly and its components, the basis upon which the assembly is being evaluated, test results and similar information and other data as necessary for the building official to determine conformance to this code. Such a report shall be approved by the building official.
The owner or the owner’s authorized agent shall provide for special inspections of fabricated items in accordance with Section 1704A.2.5.
Copies of necessary test and special inspection records shall be filed with the building official.
Special inspections and tests, statements of special inspections, responsibilities of contractors, submittals to the building official and structural observations shall meet the applicable requirements of this section.

Where application is made to the building official for construction as specified in Section 105, the owner shall employ one or more approved agencies to provide special inspections and tests during construction on the types of work specified in Section 1705A and identify the approved agencies to the building official. These special inspections and tests are in addition to the inspections by the building official that are identified in Section 110.

[OSHPD 1 & 4] An inspection agency having accreditation to the International Standards Organization (ISO) accreditation Standard 17020 shall be deemed to comply with the requirements for an approved inspection agency.

The inspectors shall act under the direction of the architect or structural engineer or both, and be responsible to the Owner. Where the California Administrative Code (CAC) Section 7-115 (a) 2 permits construction documents to be prepared under the responsible charge of a mechanical, electrical or civil engineer, inspectors shall be permitted to work under the direction of engineer in appropriate branch as permitted therein.

Exceptions:

  1. Special inspections and tests are not required for construction of a minor nature or as warranted by conditions in the jurisdiction as approved by the building official.
  2. [DSA-SS, DSA-SS/CC] Reference to Section 105 and Section 110 shall be to the California Administrative Code instead.

Prior to the start of the construction, the approved agencies shall provide written documentation to the building official demonstrating the competence and relevant experience or training of the special inspectors who will perform the special inspections and tests during construction. Experience or training shall be considered relevant where the documented experience or training is related in complexity to the same type of special inspection or testing activities for projects of similar complexity and material qualities. These qualifications are in addition to qualifications specified in other sections of this code.

The registered design professional in responsible charge and engineers of record involved in the design of the project are permitted to act as the approved agency and their personnel are permitted to act as special inspectors for the work designed by them, provided they qualify as special inspectors.

The construction or work for which special inspection or testing is required shall remain accessible and exposed for special inspection or testing purposes until completion of the required special inspections or tests.

The applicant shall submit a statement of special inspections prepared by the registered design professional in general responsible charge in accordance with Section 107.1 as a condition for construction documents review. This statement shall be in accordance with Section 1704A.3.

[DSA-SS, DSA-SS/CC] Reference to Section 107.1 shall be to the California Administrative Code instead.

The inspector(s) of record and approved agencies shall keep records of inspections. The inspector of record and approved agency shall furnish inspection reports to the building official, and to the registered design professional in responsible charge. Reports shall indicate that work inspected was or was not completed in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. If they are not corrected, the discrepancies shall be brought to the attention of the building official and to the registered design professional in responsible charge prior to the completion of that phase of the work. A final report documenting required special inspections and tests, and correction of any discrepancies noted in the inspections or tests, shall be submitted at a point in time agreed upon prior to the start of work by the owner or the owner’s authorized agent to the building official.

Where fabrication of structural, load-bearing or lateral load-resisting members or assemblies is being conducted on the premises of a fabricator’s shop, special inspections of the fabricated items shall be performed during fabrication.

Exception: [OSHPD 1 & 4] Special inspections during fabrication are not required where the fabricator maintains approved detailed fabrication and quality control procedures that provide a basis for control of the workmanship and the fabricator’s ability to conform to approved construction documents and this code. Approval shall be based upon review of fabrication and quality control procedures and periodic inspection of fabrication practices by the special inspector and/or building official, as determined by the building official.

Where special inspections or tests are required by Section 1705A, the registered design professional in responsible charge shall prepare a statement of special inspections in accordance with Section 1704A.3.1 for submittal by the applicant in accordance with Section 1704A.2.3.

Exception: The statement of special inspections is permitted to be prepared by a qualified person approved by the building official for construction not designed by a registered design professional.

The statement of special inspections shall identify the following:

  1. The materials, systems, components and work required to have special inspections or tests by the building official or by the registered design professional responsible for each portion of the work.
  2. The type and extent of each special inspection.
  3. The type and extent of each test.
  4. Additional requirements for special inspections or tests for seismic or wind resistance as specified in Sections 1705A.11, 1705A.12 and 1705A.13.
  5. For each type of special inspection, identification as to whether it will be continuous special inspection, periodic special inspection or performed in accordance with the notation used in the referenced standard where the inspections are defined.
Where Section 1705A.12 or 1705A.13 specifies special inspections or tests for seismic resistance, the statement of special inspections shall identify the equipment/components that require special seismic certification and seismic force-resisting systems that are subject to the special inspections or tests.
Where Section 1705A.11 specifies special inspection for wind resistance, the statement of special inspections shall identify the main windforce-resisting systems and wind-resisting components that are subject to special inspections.
Each contractor responsible for the construction of a main wind- or seismic force-resisting system, installation of equipment/components requiring special seismic certification or a wind- or seismic force-resisting component listed in the statement of special inspections shall submit a written statement of responsibility to the building official and the owner or the owner’s authorized agent prior to the commencement of work on the system or component. The contractor’s statement of responsibility shall contain acknowledgement of awareness of the special requirements contained in the statement of special inspections.

In addition to the submittal of reports of special inspections and tests in accordance with Section 1704A.2.4, reports and certificates shall be submitted by the owner or the owner’s authorized agent to the building official for each of the following:

  1. [OSHPD 1 & 4] Certificates of compliance for the fabrication of structural, load-bearing or lateral load-resisting members or assemblies on the premises of an approved fabricator in accordance with Section 1704A.2.5.
  2. Certificates of compliance for the manufacturer’s certification of nonstructural components, supports and attachments in accordance with Section 1705A.13.2.
  3. Certificates of compliance for equipment/components requiring special seismic certification in accordance with Section 1705A.13.3.
  4. Reports of preconstruction tests for shotcrete in accordance with Section 1908.5.
  5. Certificates of compliance for open web steel joists and joist girders in accordance with Section 2207.5.
  6. Reports of material properties verifying compliance with the requirements of AWS D1.4 for weldability as specified in Section 26.5.4 of ACI 318 for reinforcing bars in concrete complying with a standard other than ASTM A706 that are to be welded; and
  7. Reports of mill tests in accordance with Section 20.2.2.5 of ACI 318 for reinforcing bars complying with ASTM A615 and used to resist earthquake-induced flexural or axial forces in the special moment frames, special structural walls or coupling beams connecting special structural walls of seismic force-resisting systems in structures assigned to Seismic Design Category B, C, D, E or F.

The owner shall employ a registered design professional to perform structural observations. Structural observation does not include or waive the responsibility for the inspections in Section 110 or the special inspections in Section 1705A or other sections of this code.

Prior to the commencement of observations, the structural observer shall submit to the building official a written statement identifying the frequency and extent of structural observations.

At the conclusion of the work included in the permit, the structural observer shall submit to the building official a written statement that the site visits have been made and identify any reported deficiencies that, to the best of the structural observer’s knowledge, have not been resolved.

[DSA-SS, DSA-SS/CC] Reference to Section 110 shall be to the California Administrative Code instead.

Special inspections and tests of elements and nonstructural components of buildings and structures shall meet the applicable requirements of this section.

Special inspections and tests shall be required for proposed work that is, in the opinion of the building official, unusual in its nature, such as, but not limited to, the following examples:

  1. Construction materials and systems that are alternatives to materials and systems prescribed by this code.
  2. Unusual design applications of materials described in this code.
  3. Materials and systems required to be installed in accordance with additional manufacturer’s instructions that prescribe requirements not contained in this code or in standards referenced by this code.

The special inspections and nondestructive testing of steel construction in buildings, structures, and portions thereof shall be in accordance with this section.

Exception: Special inspections of the steel fabrication process shall not be required where the fabricator does not perform any welding, thermal cutting or heating operation of any kind as part of the fabrication process. In such cases, the fabricator shall be required to submit a detailed procedure for material control that demonstrates the fabricator’s ability to maintain suitable records and procedures such that, at any time during the fabrication process, the material specification and grade for the main stress-carrying elements are capable of being determined. Mill test reports shall be identifiable to the main stress-carrying elements when required by the approved construction documents.

Special inspections and nondestructive testing of structural steel elements in buildings, structures and portions thereof shall be in accordance with the quality assurance requirements of this section, Chapter 22A and quality control requirements of AISC 360, AISC 341 and AISC 358.

Exception: Special inspection of railing systems composed of structural steel elements shall be limited to welding inspection of welds at the base of cantilevered rail posts.

AISC 360, Chapter N and AISC 341, Chapter J are adopted, except as noted below:

The following provisions of AISC 360, Chapter N are not adopted:

  1. N4., Item 2. (Quality Assurance Inspector Qualifications)
  2. N5., Item 2. (Quality Assurance)
  3. [DSA-SS, DSA-SS/CC]

    N5., Item 3. (Coordinated Inspection)

  4. [DSA-SS, DSA-SS/CC]

    N5., Item 4. (Inspection of Welding)

  5. [DSA-SS, DSA-SS/CC]

    N7 (Approved Fabricators and Erectors)

  6. [DSA-SS, DSA-SS/CC]

    N8 (Nonconforming Material and Workmanship)

In addition to the quality assurance inspection requirements contained in AISC 360, Section N5 (Minimum Requirements for Inspection of Structural Steel Buildings), the requirements of Table 1705A.2.1 of the California Building Code shall apply.

In addition to the quality assurance requirements contained in AISC 360, Section N6 (Minimum Requirements for Inspection of Composite Construction), the requirements of Table 1705A.2.1 of the California Building Code shall apply.

In addition to the quality assurance requirements contained in AISC 341, Chapter J, Section J5 (Inspection Tasks), the requirements of Section 1704A.3 and Table 1705A.2.1 of the California Building Code shall apply.

TABLE 1705A.2.1

REQUIRED VERIFICATION AND INSPECTION OF STEEL CONSTRUCTION

VERIFICATION AND INSPECTIONCONTINUOUSPERIODICREFERENCED

STANDARDa
CBC

REFERENCE
1. Material verification of high-strength bolts, nuts and washers:
a. Identification markings to conform to ASTM standards specified in the approved construction documents.XAISC 360, Section A3.3 and applicable ASTM material standards
b. Manufacturer’s certificate of compliance required.X
2. Inspection of high-strength bolting:
a. Snug-tight joints.XAISC 360, Section M2.5
b. Pretensioned and slip-critical joints using turn-of-nut with matchmarking, twist-off bolt or direct tension indicator methods of installationX
c. Pretensioned and slip-critical joints using turn-of-nut without

matchmarking or calibrated wrench methods of installation.
X
3. Material verification of structural steel and cold-formed steel deck:
a. For structural steel, identification markings to conform to AISC 360.XAISC 360,

Section A3.1
2203A.1
b. For other steel, identification markings to conform to ASTM standards specified in the approved construction documents.XApplicable ASTM material standards
c. Manufacturer’s certified test reports.X
4. Material verification of weld filler materials:
a. Identification markings to conform to AWS specification in the approved construction documents.XAISC 360, Section A3.5 and applicable AWS A5 documents
b. Manufacturer’s certificate of compliance required.X
5. Inspection of welding:
a. Structural steel and cold-formed steel deck:
1. Complete and partial joint penetration groove weldsXAWS D1.1AWS D1.81705A.2.1
2. Multipass fillet welds.X
3. Single-pass fillet welds > 5/16X
4.Plug and slot welds.X
5. Single-pass fillet welds ≤ 5/16X
6. Floor and roof deck welds.XAWS D1.3
b. Reinforcing steel:
1. Verification of weldability of reinforcing steel other than ASTM A706.XAWS D1.4, ACI 318: Sections 26.6.4.1, 18.2.8, 25.5.7.4
2. Reinforcing steel resisting flexural and axial forces in intermediate and special moment frames, and boundary elements of special structural walls of concrete and shear reinforcement.X
3. Shear reinforcement.X
4. Other reinforcing steel.X
6. Inspection of steel frame joint details for compliance:
a. Details such as bracing and stiffening.X1705A.2.1
b. Member locations.X
c. Application of joint details at each connection.X

For SI: 1 inch = 25.4 mm.

a. Where applicable, see also Section 1705A.12, Special inspections for seismic resistance.

Special inspections for cold-formed steel floor and roof deck shall be in accordance with the quality assurance inspection requirements of SDI QA/QC.

Deck weld special inspection shall also satisfy requirements in Table 1705A.2.1 and Section 1705A.2.5.

Special inspections of open-web steel joists and joist girders in buildings, structures and portions thereof shall be in accordance with Table 1705A.2.3.

TABLE 1705A.2.3

REQUIRED SPECIAL INSPECTIONS OF OPEN-WEB STEEL JOISTS AND JOIST GIRDERS

TYPECONTINUOUS

SPECIAL INSPECTION
PERIODIC SPECIAL

INSPECTION
REFERENCED STANDARDa
1. Installation of open-web steel joists and joist girders.
a. End connections - welding or bolted.XSJI specifications listed in Section 2207.1.
b. Bridging - horizontal or diagonal.
1. Standard bridging.XSJI specifications listed in Section 2207.1.
2. Bridging that differs from the SJI

specifications listed in Section 2207.1.
X

For SI: 1 inch = 25.4 mm.

  1. Where applicable, see also Section 1705A.12, Special inspections for seismic resistance.

Special inspection is required during the manufacture and welding of steel joists or joist girders. The approved agency shall verify that proper quality control procedures and tests have been employed for all materials and the manufacturing process, and shall perform visual inspection of the finished product. The approved agency shall place a distinguishing mark, and/or tag with this distinguishing mark, on each inspected joist or joist girder. This mark or tag shall remain on the joist or joist girder throughout the job site receiving and erection process.

Where a cold-formed steel truss clear span is 60 feet (18 288 mm) or greater, the special inspector shall verify that the temporary installation restraint/bracing and the permanent individual truss member restraint/bracing are installed in accordance with the approved truss submittal package.

The manufacture of cold-formed light framed steel trusses shall be continuously inspected by an approved agency. The approved agency shall verify conformance of materials and manufacture with approved plans and specifications. The approved agency shall place a distinguishing mark, and/or tag with this distinguishing mark, on each inspected truss. This mark or tag shall remain on the truss throughout the job site receiving and erection process.

Inspection of all shop and field welding operations shall be made by a qualified welding inspector approved by the enforcement agency. The minimum requirements for a qualified welding inspector shall be as those for an AWS certified welding inspector (CWI), as defined in the provisions of the AWS QC1.

Exception: [OSHPD 1 & 4] Inspection and nondestructive testing personnel meeting the requirements of AISC 341 Section J4 (in addition to AISC 360 Section N4) shall be permitted to perform quality control and quality assurance inspections at the premises of an approved fabricator’s shop.

The welding inspector shall make a systematic daily record of all welds. In addition to other required records, this record shall include:

  1. Identification marks of welders.
  2. List of defective welds.
  3. Manner of correction of defects.

The welding inspector shall check the material, details of construction and procedure, as well as workmanship of the welds. The inspector shall verify that the installation of end-welded stud shear connectors is in accordance with the requirements of AWS D1.1 and the approved plans and specifications. The approved agency shall furnish the architect, structural engineer, and the enforcement agency with a verified report that the welding has been done in conformance with AWS D1.1, D1.3, D1.8, and the approved construction documents.

Special inspections and tests of concrete construction shall be performed in accordance with this section and Table 1705A.3.

Exception: Special inspections and tests shall not be required for concrete patios, driveways and sidewalks, on grade.

TABLE 1705A.3

REQUIRED SPECIAL INSPECTIONS AND TESTS OF CONCRETE CONSTRUCTION

TYPECONTINUOUS SPECIAL INSPECTIONPERIODIC SPECIAL INSPECTIONREFERENCED STANDARDaIBC REFERENCE
1. Inspect reinforcement, including prestressing tendons, and verify placement.XACI 318 Ch. 20, 25.2, 25.3, 26.5.1-26.5.31908.4
2. Reinforcing bar welding:AWS D1.4ACI 318: 26.5.4
a. Verify weldability of reinforcing bars other than ASTM A706;X
b. Inspect single-pass fillet welds, maximum 5/16″; andX
c. Inspect all other welds.X
3. Inspect anchors cast in concrete.XACI 318: 17.8.2
4. Inspect anchors post-installed in hardened concrete members.b, c
a. Adhesive anchors installed in horizontally or upwardly inclined orientations to resist sustained tension loads.XACI 318: 17.8.2.4
b. Mechanical anchors and adhesive anchors not defined in 4.a.XACI 318: 17.8.2
5. Verify use of required design mix.XACI 318: Ch. 19, 26.4.3, 26.4.41904.1, 1904.2, 1908.2, 1908.3
6. Prior to concrete placement, fabricate specimens for strength tests, perform slump and air content tests, and determine the temperature of the concrete.XASTM C172ASTM C31ACI 318: 26.4.5, 26.121908.10
7. Inspect concrete and shotcrete placement for proper application techniques.XACI 318: 26.4.51908.6, 1908.7, 1908.8
8. Verify maintenance of specified curing temperature and techniques.XACI 318: 26.4.7-26.4.91908.9
9. Inspect prestressed concrete for:
a. Application of prestressing forces; andXACI 318: 26.9.2.1
b. Grouting of bonded prestressing tendons.XACI 318: 26.9.2.3
10. Inspect erection of precast concrete members.XACI 318: Ch. 26.8
11. Verify in-situ concrete strength, prior to stressing of tendons in post-tensioned concrete and prior to removal of shores and forms from beams and structural slabs.XACI 318: 26.10.2
12. Inspect formwork for shape, location and dimensions of the concrete member being formed.XACI 318: 26.10.1(b)

For SI: 1 inch = 25.4 mm.

  1. Where applicable, see also Section 1705.12, Special inspections for seismic resistance.
  2. Specific requirements for special inspection shall be included in the research report for the anchor issued by an approved source in accordance with 17.8.2 in ACI 318, or other qualification procedures. Where specific requirements are not provided, special inspection requirements shall be specified by the registered design professional and shall be approved by the building official prior to the commencement of the work.
  3. Installation of all adhesive anchors in horizontal and upwardly inclined positions shall be performed by an ACI/CRSI Certified Adhesive Anchor Installer, except where the factored design tension on the anchors is less than 100 lbs and those anchors are clearly noted on the approved construction documents or where the anchors are shear dowels across cold joints in slabs on grade where the slab is not part of the lateral force-resisting system.
Special inspections of welding and qualifications of special inspectors for reinforcing bars shall be in accordance with the requirements of AWS D1.4 for special inspection and of AWS D1.4 for special inspector qualification.
In the absence of sufficient data or documentation providing evidence of conformance to quality standards for materials in Chapters 19 and 20 of ACI 318, the building official shall require testing of materials in accordance with the appropriate standards and criteria for the material in Chapters 19 and 20 of ACI 318.

Except as provided under this section, the quality and quantity of materials used in transit-mixed concrete and in batched aggregates shall be continuously inspected by an approved agency at the location where materials are measured.

Continuous batch plant inspection may be waived by the registered design professional, subject to approval by the enforcement agency under either of the following conditions:

  1. The concrete plant complies fully with the requirements of ASTM C94, Sections 9 and 10, and has a current certificate from the National Ready Mixed Concrete Association or another agency acceptable to the enforcement agency. The certification shall indicate that the plant has automatic batching and recording capabilities.
  2. For single-story light-framed construction (without basement or retaining wall higher than 6’ in height measured from bottom of footing to top of wall) and isolated foundations supporting equipment only, where deep foundation elements are not used.

When continuous batch plant inspection is waived, the following requirements shall apply and shall be described in the construction documents:

  1. An approved agency shall check the first batch at the start of the day to verify materials and proportions conform to the approved mix design.
  2. A licensed weighmaster shall positively identify quantity of materials and certify each load by a batch ticket.
  3. Batch tickets, including material quantities and weights shall accompany the load, shall be transmitted to the inspector of record by the truck driver with load identified thereon. The load shall not be placed without a batch ticket identifying the mix. The inspector of record shall keep a daily record of placements, identifying each truck, its load, and time of receipt at the jobsite, and approximate location of deposit in the structure and shall maintain a copy of the daily record as required by the enforcement agency.

Batch plant inspection is not required for any of the following conditions, provided they are identified on the approved construction documents and the licensed weighmaster and batch ticket requirements of Section 1705A.3.3.1 are implemented:

  1. Site flatwork
  2. Unenclosed site structures, including but not limited to lunch or car shelters, bleachers, solar structures, flag or light poles, or retaining walls.
  3. Controlled low-strength material backfill.
  4. Single-story relocatable buildings less than 2,160 square feet.
  1. In addition to the general inspection required for concrete work, all plant fabrication of prestressed concrete members or tensioning of posttensioned members constructed at the site shall be continuously inspected by an inspector specially approved for this purpose by the enforcement agency.
  2. The prestressed concrete plant fabrication inspector shall check the materials, equipment, tensioning procedure and construction of the prestressed members and prepare daily written reports. The approved agency shall make a verified report identifying the members by mark and shall include such pertinent data as lot numbers of tendons used, tendon jacking forces, age and strength of concrete at time of tendon release and such other information that may be required.
  3. The inspector of prestressed members posttensioned at the site shall check the condition of the prestressing tendons, anchorage assemblies and concrete in the area of the anchorage, the tensioning equipment and the tensioning procedure and prepare daily written reports. The approved agency shall make a verified report of the prestressing operation identifying the members or tendons by mark and including such pertinent data as the initial cable slack, net elongation of tendons, jacking force developed, and such other information as may be required.
  4. The verified reports of construction shall show that of the inspector's own personal knowledge, the work covered by the report has been performed and materials used and installed in every material respect in compliance with the duly approved plans and specifications for plant fabrication inspection. The verified report shall be accompanied by test reports required for materials used. For site posttensioning inspections the verified report shall be accompanied by copies of calibration charts, certified by an approved testing laboratory, showing the relationship between gage readings and force applied by the jacks used in the prestressing procedure.

Concrete shall not be placed until the forms and reinforcement have been inspected, all preparations for the placement have been completed, and the preparations have been checked by the inspector of record.

A record shall be kept on the site of the time and date of placing the concrete in each portion of the structure. Such record shall be kept until the completion of the structure and shall be open to the inspection of the enforcement agency.

Special inspections and tests of masonry construction shall be performed in accordance with the quality assurance program requirements of TMS 402/ACI 530/ASCE 5, as set forth in Table 3.1.3 Level C requirements and TMS 602/ACI 530.1/ASCE 6. Special inspection and testing of post-installed anchors in masonry shall be required in accordance with requirements for concrete in Chapters 17A and 19A.
Special inspections and tests for glass unit masonry or masonry veneer designed in accordance with Section 2110A or Chapter 14, respectively, where they are part of a structure classified as Risk Categories II, III or IV shall be performed in accordance with TMS 402/ACI 530/ASCE 5, Level B Quality Assurance.
Special inspections and tests of vertical masonry foundation elements shall be performed in accordance with Section 1705A.4.
Special inspections of prefabricated wood structural elements and assemblies shall be in accordance with Section 1704A.2.5 except as modified in this section. Special inspections of site-built assemblies shall be in accordance with this section.
High-load diaphragms designed in accordance with Section 2306.2 shall be installed with special inspections as indicated in Section 1704A.2. The special inspector shall inspect the wood structural panel sheathing to ascertain whether it is of the grade and thickness shown on the approved construction documents. Additionally, the special inspector must verify the nominal size of framing members at adjoining panel edges, the nail or staple diameter and length, the number of fastener lines and that the spacing between fasteners in each line and at edge margins agrees with the approved construction documents.
Where a truss clear span is 60 feet (18 288 mm) or greater, the special inspector shall verify that the temporary installation restraint/bracing and the permanent individual truss member restraint/bracing are installed in accordance with the approved truss submittal package.

Special inspection of wood structural elements and assemblies is required, as specified in this section, to ensure conformance with approved construction documents, and applicable standards.

The approved agency shall furnish a verified report to the design professional in general responsible charge of construction observation, the structural engineer, and the enforcement agency, in accordance with the California Administrative Code and this chapter. The verified report shall list all inspected members or trusses, and shall indicate whether or not the inspected members or trusses conform with applicable standards and the approved drawings and specifications. Any nonconforming items shall be indicated on the verified report.

Manufacture of all structural glued laminated timber shall be continuously inspected by an approved agency.

The approved agency shall verify that proper quality control procedures and tests have been employed for all materials and the manufacturing process, and shall perform visual inspection of the finished product. Each inspected member shall be stamped by the approved agency with an identification mark.

Exception: Special Inspection is not required for noncustom members of 51/8 inch maximum width and 18 inch maximum depth, and with a maximum clear span of 32 feet, manufactured and marked in accordance with ANSI/AITC A 190.1 Section 6.1.1 for noncustom members.

The manufacture of open web trusses shall be continuously inspected by an approved agency.

The approved agency shall verify that proper quality control procedures and tests have been employed for all materials and the manufacturing process, and shall perform visual inspection of the finished product. Each inspected truss shall be stamped with an identification mark by the approved agency.

The installation of all split ring and shear plate timber connectors, and timber rivets shall be continuously inspected by an approved agency. The approved agency shall furnish the architect, structural engineer and the enforcement agency with a report verifying that the materials, timber connectors and workmanship conform to the approved construction documents.

Special inspections and tests of existing site soil conditions, fill placement and load-bearing requirements shall be performed in accordance with this section and Table 1705A.6. The approved geotechnical report and the construction documents prepared by the registered design professionals shall be used to determine compliance. During fill placement, the special inspector shall verify that proper materials and procedures are used in accordance with the provisions of the approved geotechnical report.

Exception: Where Section 1803 does not require reporting of materials and procedures for fill placement, the special inspector shall verify that the in-place dry density of the compacted fill is not less than 90 percent of the maximum dry density at optimum moisture content determined in accordance with ASTM D1557.

TABLE 1705A.6

REQUIRED SPECIAL INSPECTIONS AND TESTS OF SOILS

TYPECONTINUOUS SPECIAL INSPECTIONPERIODIC SPECIAL INSPECTION
1. Verify materials below shallow foundations are adequate to achieve the design bearing capacity.X
2. Verify excavations are extended to proper depth and have reached proper material.X
3. Perform classification and testing of compacted fill materials.X
4. Verify use of proper materials, densities and lift thicknesses during placement and compaction of compacted fill.X
5. Prior to placement of compacted fill, inspect subgrade and verify that site has been prepared properly.X

All fills used to support the foundations of any building or structure shall be continuously inspected by the geotechnical engineer or his or her qualified representative. It shall be the responsibility of the geotechnical engineer to verify that fills meet the requirements of the approved construction documents and to coordinate all fill inspection and testing during the construction involving such fills.

The duties of the geotechnical engineer or his or her qualified representative shall include, but need not be limited to, the inspection of cleared areas and benches prepared to receive fill; inspection of the removal of all unsuitable soils and other materials; the approval of soils to be used as fill material; the inspection of placement and compaction of fill materials; the testing of the completed fills; the inspection or review of geotechnical drainage devices, buttress fills or other similar protective measures in accordance with the approved construction documents.

A verified report shall be submitted by the geotechnical engineer as required by the California Administrative Code. The report shall indicate that all tests and inspection required by the approved construction documents were completed and that the tested materials and/or inspected work meet the requirements of the approved construction documents.

Special inspections and tests shall be performed during installation of driven deep foundation elements as specified in Table 1705A.7. The approved geotechnical report and the construction documents prepared by the registered design professionals shall be used to determine compliance.

TABLE 1705A.7

REQUIRED SPECIAL INSPECTIONS AND TESTS OF DRIVEN DEEP FOUNDATION ELEMENTS

TYPECONTINUOUS SPECIAL INSPECTIONPERIODIC SPECIAL INSPECTION
1. Verify element materials, sizes and lengths comply with the requirements.X
2. Determine capacities of test elements and conduct additional load tests, as required.X
3. Inspect driving operations and maintain complete and accurate records for each element.X
4. Verify placement locations and plumbness, confirm type and size of hammer, record number of blows per foot of penetration, determine required penetrations to achieve design capacity, record tip and butt elevations and document any damage to foundation element.X
5. For steel elements, perform additional special inspections in accordance with Section 1705A.2.
6. For concrete elements and concrete-filled elements, perform tests and additional special inspections in accordance with Section 1705A.3.
7. For specialty elements, perform additional inspections as determined by the registered design professional in responsible charge.

The installation of driven deep foundations shall be continuously observed by a qualified representative of the geotechnical engineer responsible for that portion of the project.

The representative of the geotechnical engineer shall make a report of the deep foundation pile-driving operation giving such pertinent data as the physical characteristics of the deep foundation pile-driving equipment, identifying marks for each deep foundation pile, the total depth of embedment for each deep foundation; and when the allowable deep foundation pile loads are determined by a dynamic load formula, the design formula used, and the permanent penetration under the last 10 blows. One copy of the report shall be sent to the enforcement agency.

Special inspections and tests shall be performed during installation of cast-in-place deep foundation elements as specified in Table 1705A.8. The approved geotechnical report and the construction documents prepared by the registered design professionals shall be used to determine compliance.

TABLE 1705A.8

REQUIRED SPECIAL INSPECTIONS AND TESTS OF CAST-IN-PLACE DEEP FOUNDATION ELEMENTS

TYPECONTINUOUS SPECIAL INSPECTIONPERIODIC SPECIAL INSPECTION
1. Inspect drilling operations and maintain complete and accurate records for each element.X
2. Verify placement locations and plumbness, confirm element diameters, bell diameters (if applicable), lengths, embedment into bedrock (if applicable) and adequate end-bearing strata capacity. Record concrete or grout volumes.X
3. For concrete elements, perform tests and additional special inspections in accordance with Section 1705A.3.
Continuous special inspections shall be performed during installation of helical pile foundations. The information recorded shall include installation equipment used, pile dimensions, tip elevations, final depth, final installation torque and other pertinent installation data as required by the registered design professional in responsible charge. The approved geotechnical report and the construction documents prepared by the registered design professional shall be used to determine compliance.
Special inspections of fabricated items shall be performed in accordance with Section 1704A.2.5.

Special inspections for wind resistance specified in Sections 1705A.11.1 through 1705A.11.3, unless exempted by the exceptions to Section 1704A.2, are required for buildings and structures constructed in the following areas:

  1. In wind Exposure Category B, where Vasd as determined in accordance with Section 1609.3.1 is 120 miles per hour (52.8 m/sec) or greater.
  2. In wind Exposure Category C or D, where Vasd as determined in accordance with Section 1609.3.1 is 110 mph (49 m/sec) or greater.
Continuous special inspection is required during field gluing operations of elements of the main windforce-resisting system. Periodic special inspection is required for nailing, bolting, anchoring and other fastening of elements of the main windforce-resisting system, including wood shear walls, wood diaphragms, drag struts, braces and hold-downs.
Periodic special inspection is required for welding operations of elements of the main windforce-resisting system. Periodic special inspection is required for screw attachment, bolting, anchoring and other fastening of elements of the main windforce-resisting system, including shear walls, braces, diaphragms, collectors (drag struts) and hold-downs.

Periodic special inspection is required for fastening of the following systems and components:

  1. Roof covering, roof deck and roof framing connections.
  2. Exterior wall covering and wall connections to roof and floor diaphragms and framing.
Special inspections for seismic resistance shall be required as specified in Sections 1705A.12.1 through 1705A.12.9, unless exempted by the exceptions of Section 1704A.2.
Special inspections for seismic resistance shall be in accordance with Section 1705A.12.1.1 or 1705A.12.1.2, as applicable.
Special inspections of structural steel in the seismic force-resisting systems of buildings and structures assigned to Seismic Design Category D, E or F shall be performed in accordance with the quality assurance requirements of AISC 341 as modified by Section 1705A.2.1 of this code.
Special inspections of structural steel elements in the seismic force-resisting systems of buildings and structures assigned to Seismic Design Category D, E or F other than those covered in Section 1705A.12.1.1, including struts, collectors, chords and foundation elements, shall be performed in accordance with the quality assurance requirements of AISC 341 as modified by Section 1705A.2.1 of this code.

For the seismic force-resisting systems of structures assigned to Seismic Design Category D, E or F:

  1. Continuous special inspection shall be required during field gluing operations of elements of the seismic force-resisting system.
  2. Periodic special inspection shall be required for nailing, bolting, anchoring and other fastening of elements of the seismic force-resisting system, including wood shear walls, wood diaphragms, drag struts, braces, shear panels and hold-downs.

For the seismic force-resisting systems of structures assigned to Seismic Design Category D, E or F, periodic special inspection shall be required:

  1. For welding operations of elements of the seismic force-resisting system; and
  2. For screw attachment, bolting, anchoring and other fastening of elements of the seismic force-resisting system, including shear walls, braces, diaphragms, collectors (drag struts) and hold-downs.
For structures assigned to Seismic Design Category D, E or F, the special inspector shall examine equipment and components requiring special seismic certification in accordance with Section 1705A.13.3 or ASCE 7 Section 13.2.2 and verify that the label, anchorage and mounting conform to the certificate of compliance.
Periodic special inspection is required for the erection and fastening of exterior cladding, interior and exterior nonbearing walls, ceilings and interior and exterior veneer in structures assigned to Seismic Design Category D, E or F.
Periodic special inspection is required for the anchorage of access floors in structures assigned to Seismic Design Category D, E or F.

Periodic special inspection of plumbing, mechanical and electrical components shall be required for the following:

  1. Anchorage of electrical equipment for emergency and standby power systems in structures assigned to Seismic Design Category D, E or F.
  2. Anchorage of other electrical equipment in structures assigned to Seismic Design Category E or F.
  3. Installation and anchorage of piping systems designed to carry hazardous materials and their associated mechanical units in structures assigned to Seismic Design Category D, E or F.
  4. Installation and anchorage of ductwork designed to carry hazardous materials in structures assigned to Seismic Design Category D, E or F.

  5. Installation and anchorage of vibration isolation systems in structures assigned to Seismic Design Category D, E or F where the approved construction documents require a nominal clearance of 1/4 inch (6.4 mm) or less between the equipment support frame and restraint.
Periodic special inspection is required for the anchorage of storage racks that are 8 feet (2438 mm) or greater in height in structures assigned to Seismic Design Category D, E or F.
Periodic special inspection shall be provided for seismic isolation and damping systems in structures assigned to Seismic Design Category D, E or F during the fabrication and installation of isolator units and energy dissipation devices. Continuous special inspection is required for prototype and production testing of isolator units and damping devices.
Testing for seismic resistance shall be required as specified in Sections 1705A.13.1 through 1705A.13.4, unless exempted from special inspections by the exception of Section 1704A.2.
Nondestructive testing for seismic resistance shall be in accordance with Section 1705A.13.1.1 or 1705A.13.1.2, as applicable.
Nondestructive testing of structural steel in the seismic force-resisting systems of buildings and structures assigned to Seismic Design Category D, E or F shall be performed in accordance with the quality assurance requirements of AISC 341.
Nondestructive testing of structural steel elements in the seismic force-resisting systems of buildings and structures assigned to Seismic Design Category D, E or F other than those covered in Section 1705A.13.1.1, including struts, collectors, chords and foundation elements, shall be performed in accordance with the quality assurance requirements of AISC 341.

For structures assigned to Seismic Design Category D, E or F, where requirements of Section 13.2.1 of ASCE 7 for non-structural components, supports, or attachments are met by manufacturer’s certification as specified in Item 2 therein, the registered design professional shall specify on the approved construction documents the requirements for seismic certification by analysis or testing. Certificates of compliance for the manufacturer’s certification shall be submitted to the building official as specified in Section 1704A.5.

Seismic sway braces satisfying requirements of FM 1950 shall be deemed to satisfy the requirements of this section. Component tests shall be supplemented by assembly tests, when required by the building official.

For structures assigned to Seismic Design Category D, E or F, equipment and components that are subject to the requirements of Section 13.2.2 of ASCE 7 for special seismic certification, the registered design professional shall specify on the approved construction documents the requirements to be met by analysis or testing as specified therein. Certificates of compliance documenting that the requirements are met shall be submitted to the building official as specified in Section 1704A.5.

Active or energized equipment and components shall be certified exclusively on the basis of approved shake table testing in accordance with ICC-ES AC 156. Minimum of two equipment/components shall be tested for a product line with similar structural configuration. Where a range of products are tested, the two equipment/components shall be either the largest and a small unit, or approved alternative representative equipment/components.

Exception: When a single product (and not a product line with more than one product with variations) is certified and manufacturing process is ISO 9001 certified, one test shall be permitted.

For a multi-component system, where active or energized components are certified by tests, connecting elements, attachments, and supports can be justified by supporting analysis.

Special seismic certification shall be required for the following systems, equipment, and components:

  1. emergency and standby power systems.
  2. Elevator equipment (excluding elevator cabs).
  3. Components with hazardous contents.
  4. Exhaust and smoke control fans.
  5. Switchgear and switchboards.
  6. Motor control centers.
  7. Fluoroscopy and x-ray equipment required for radiological/diagnostic imaging service (for service requirements see CBC Section 1224.18.1), and any fluoroscopy and/or radiographic system provided in support of diagnostic assessment of trauma injuries.
  8. CT (Computerized Tomography) systems used for diagnostic assessment of trauma injuries.

    Exception: CT equipment used for treatment or in hybrid operating rooms, including those used for interventional CT, unless used for diagnostic assessment of trauma injuries.

  9. Air conditioning units excluding Variable/Constant Air Volume (VAV/CAV) boxes up to 75 lbs.
  10. Air handling units.
  11. Chillers, including associated evaporators, and condensers.
  12. Cooling towers.
  13. Transformers.
  14. Electrical substations.
  15. UPS and batteries.
  16. Panelboards as defined in the California Electrical Code (CEC) Article 100.
  17. Industrial control panels as defined in the California Electrical Code (CEC) Article 100.
  18. Power isolation and correction systems.
  19. Motorized surgical lighting systems.
  20. Motorized operating table systems.
  21. Internal communication servers and routers.
  22. Medical gas and vacuum systems.
  23. Electrical busways as defined in UL 857.
  24. Electrical control panels powered by the life safety branch in accordance with the California Electrical Code (CEC) Article 517.32 or the critical branch in accordance with the California Electrical Code (CEC) Article 517.33.

Exceptions:

  1. Equipment and components weighing not more than 50 lbs. supported directly on structures or surface mounted on equipment or components that are not required to have special seismic certification by this section.
  2. Movable (mobile) and temporary equipment/components that are not anchored to structure or permanently attached to the building utility services such as electricity, gas or water. For the purposes of this requirement, “permanently attached” shall include all electrical connections except plugs for duplex receptacles.
  3. Pipes, ducts, conduits and cable trays, excluding in-line equipment and components.
  4. Underground tanks.
  5. Electric motors, pumps, and compressors up to 20 hp.
  6. Electrical controllers, switches, transformers, circuit breakers, and fuses up to 10 lbs. or 10 amperes.
  7. Components where importance factor, Ip, is permitted to be 1.0 by this code.
  8. Emergency generators up to 25 kilowatts.
  9. Equipment and components used for clinical trials only.

Seismic isolation and damping systems in structures assigned to Seismic Design Category D, E or F shall be tested in accordance with Section 17.8 and 18.9 of ASCE 7.

Prototype and production testing and associated acceptance criteria for isolator units and damping devices shall be subject to preapproval by the building official. Testing exemption for similar units shall require approval by the building official.

Special inspections and tests of sprayed fire-resistant materials applied to floor, roof and wall assemblies and structural members shall be performed in accordance with Sections 1705A.14.1 through 1705A.14.6. Special inspections shall be based on the fire-resistance design as designated in the approved construction documents. The tests set forth in this section shall be based on samplings from specific floor, roof and wall assemblies and structural members. Special inspections and tests shall be performed after the rough installation of electrical, automatic sprinkler, mechanical and plumbing systems and suspension systems for ceilings, where applicable.

The special inspections and tests shall include the following to demonstrate compliance with the listing and the fire-resistance rating:

  1. Condition of substrates.
  2. Thickness of application.
  3. Density in pounds per cubic foot (kg/m3).
  4. Bond strength adhesion/cohesion.
  5. Condition of finished application.
The surfaces shall be prepared in accordance with the approved fire-resistance design and the written instructions of approved manufacturers. The prepared surface of structural members to be sprayed shall be inspected by the special inspector before the application of the sprayed fire-resistant material.
The substrate shall have a minimum ambient temperature before and after application as specified in the written instructions of approved manufacturers. The area for application shall be ventilated during and after application as required by the written instructions of approved manufacturers.
No more than 10 percent of the thickness measurements of the sprayed fire-resistant materials applied to floor, roof and wall assemblies and structural members shall be less than the thickness required by the approved fire-resistance design, but in no case less than the minimum allowable thickness required by Section 1705A.14.4.1.
For design thicknesses 1 inch (25 mm) or greater, the minimum allowable individual thickness shall be the design thickness minus 1/4 inch (6.4 mm). For design thicknesses less than 1 inch (25 mm), the minimum allowable individual thickness shall be the design thickness minus 25 percent. Thickness shall be determined in accordance with ASTM E605. Samples of the sprayed fire-resistant materials shall be selected in accordance with Sections 1705A.14.4.2 and 1705A.14.4.3.
The thickness of the sprayed fire-resistant material applied to floor, roof and wall assemblies shall be determined in accordance with ASTM E605, making not less than four measurements for each 1,000 square feet (93 m2) of the sprayed area, or portion thereof, in each story.
Thickness measurements shall be selected from a square area, 12 inches by 12 inches (305 mm by 305 mm) in size. A minimum of four measurements shall be made, located symmetrically within the square area.
Thickness measurements shall be selected from a square area, 12 inches by 12 inches (305 mm by 305 mm) in size. A minimum of four measurements shall be made, located symmetrically within the square area, including one each of the following: valley, crest and sides. The average of the measurements shall be reported.
The thickness of the sprayed fire-resistant material applied to structural members shall be determined in accordance with ASTM E605. Thickness testing shall be performed on not less than 25 percent of the structural members on each floor.
At beams and girders thickness measurements shall be made at nine locations around the beam or girder at each end of a 12-inch (305 mm) length.
At joists and trusses, thickness measurements shall be made at seven locations around the joist or truss at each end of a 12-inch (305 mm) length.
At wide-flanged columns, thickness measurements shall be made at 12 locations around the column at each end of a 12-inch (305 mm) length.
At hollow structural section and pipe columns, thickness measurements shall be made at a minimum of four locations around the column at each end of a 12-inch (305 mm) length.

The density of the sprayed fire-resistant material shall not be less than the density specified in the approved fire-resistance design. Density of the sprayed fire-resistant material shall be determined in accordance with ASTM E605. The test samples for determining the density of the sprayed fire-resistant materials shall be selected as follows:

  1. From each floor, roof and wall assembly at the rate of not less than one sample for every 2,500 square feet (232 m2) or portion thereof of the sprayed area in each story.
  2. From beams, girders, trusses and columns at the rate of not less than one sample for each type of structural member for each 2,500 square feet (232 m2) of floor area or portion thereof in each story.
The cohesive/adhesive bond strength of the cured sprayed fire-resistant material applied to floor, roof and wall assemblies and structural members shall not be less than 150 pounds per square foot (psf) (7.18 kN/m2). The cohesive/adhesive bond strength shall be determined in accordance with the field test specified in ASTM E736 by testing in-place samples of the sprayed fire-resistant material selected in accordance with Sections 1705A.14.6.1 through 1705A.14.6.3.
The test samples for determining the cohesive/adhesive bond strength of the sprayed fire-resistant materials shall be selected from each floor, roof and wall assembly at the rate of not less than one sample for every 2,500 square feet (232 m2) of the sprayed area, or portion thereof, in each story.
The test samples for determining the cohesive/adhesive bond strength of the sprayed fire-resistant materials shall be selected from beams, girders, trusses, columns and other structural members at the rate of not less than one sample for each type of structural member for each 2,500 square feet (232 m2) of floor area or portion thereof in each story.
Bond tests to qualify a primer, paint or encapsulant shall be conducted when the sprayed fire-resistant material is applied to a primed, painted or encapsulated surface for which acceptable bond-strength performance between these coatings and the fire-resistant material has not been determined. A bonding agent approved by the SFRM manufacturer shall be applied to a primed, painted or encapsulated surface where the bond strengths are found to be less than required values.
Special inspections and tests for mastic and intumescent fire-resistant coatings applied to structural elements and decks shall be performed in accordance with AWCI 12-B. Special inspections and tests shall be based on the fire-resistance design as designated in the approved construction documents.

Special inspections shall be required for all EIFS applications.

Exceptions:

  1. Special inspections shall not be required for EIFS applications installed over a water-resistive barrier with a means of draining moisture to the exterior.
  2. Special inspections shall not be required for EIFS applications installed over masonry or concrete walls.
A water-resistive barrier coating complying with ASTM E2570 requires special inspection of the water-resistive barrier coating when installed over a sheathing substrate.
In high-rise buildings or in buildings assigned to Risk Category III or IV, special inspections for through-penetrations, membrane penetration firestops, fire-resistant joint systems and perimeter fire barrier systems that are tested and listed in accordance with Sections 714.3.1.2, 714.4.2, 715.3 and 715.4 shall be in accordance with Section 1705A.17.1 or 1705A.17.2.
Inspections of penetration firestop systems that are tested and listed in accordance with Sections 714.3.1.2 and 714.4.2 shall be conducted by an approved agency in accordance with ASTM E2174.
Inspection of fire-resistant joint systems that are tested and listed in accordance with Sections 715.3 and 715.4 shall be conducted by an approved agency in accordance with ASTM E2393.
Smoke control systems shall be tested by a special inspector.

The test scope shall be as follows:

  1. During erection of ductwork and prior to concealment for the purposes of leakage testing and recording of device location.
  2. Prior to occupancy and after sufficient completion for the purposes of pressure difference testing, flow measurements and detection and control verification.
Approved agencies for smoke control testing shall have expertise in fire protection engineering, mechanical engineering and certification as air balancers.

All shotcrete work shall be continuously inspected during placing by an approved agency. The special shotcrete inspector shall check the materials, placing equipment, details of construction and construction procedure. The approved agency shall furnish a verified report that of his or her own personal knowledge the work covered by the report has been performed and materials used and installed in every material respect in compliance with the duly approved plans and specifications.

Completed shotcrete work shall be checked visually for reinforcing bar embedment, voids, rock pockets, sand streaks and similar deficiencies by examining a minimum of three 3-inch (76 mm) cores taken from three areas chosen by the design engineer which represent the worst congestion of reinforcing bars occurring in the project. Extra reinforcing bars may be added to noncongested areas and cores may be taken from these areas. The cores shall be examined by the special inspector and a report submitted to the enforcement agency prior to final approval of the shotcrete.

Exception: Shotcrete work fully supported on earth, minor repairs, and when, in the opinion of the enforcement agency, no special hazard exists.

The design strengths and permissible stresses of any structural material that are identified by a manufacturer’s designation as to manufacture and grade by mill tests, or the strength and stress grade is otherwise confirmed to the satisfaction of the building official, shall conform to the specifications and methods of design of accepted engineering practice or the approved rules in the absence of applicable standards.
For materials that are not specifically provided for in this code, the design strengths and permissible stresses shall be established by tests as provided for in Section 1707A.
In the absence of approved rules or other approved standards, the building official shall make, or cause to be made, the necessary tests and investigations; or the building official shall accept duly authenticated reports from approved agencies in respect to the quality and manner of use of new materials or assemblies as provided for in Section 104.11. The cost of all tests and other investigations required under the provisions of this code shall be borne by the owner or the owner’s authorized agent.
Whenever there is a reasonable doubt as to the stability or load-bearing capacity of a completed building, structure or portion thereof for the expected loads, an engineering assessment shall be required. The engineering assessment shall involve either a structural analysis or an in-situ load test, or both. The structural analysis shall be based on actual material properties and other as-built conditions that affect stability or load-bearing capacity, and shall be conducted in accordance with the applicable design standard. If the structural assessment determines that the load-bearing capacity is less than that required by the code, load tests shall be conducted in accordance with Section 1708A.2. If the building, structure or portion thereof is found to have inadequate stability or load-bearing capacity for the expected loads, modifications to ensure structural adequacy or the removal of the inadequate construction shall be required.
Structural components and assemblies shall be tested in accordance with the appropriate referenced standards. In the absence of a standard that contains an applicable load test procedure, the test procedure shall be developed by a registered design professional and approved. The test procedure shall simulate loads and conditions of application that the completed structure or portion thereof will be subjected to in normal use.
In-situ load tests shall be conducted in accordance with Section 1708A.3.1 or 1708A.3.2 and shall be supervised by a registered design professional. The test shall simulate the applicable loading conditions specified in Chapter 16 as necessary to address the concerns regarding structural stability of the building, structure or portion thereof.
Where a referenced standard contains an applicable load test procedure and acceptance criteria, the test procedure and acceptance criteria in the standard shall apply. In the absence of specific load factors or acceptance criteria, the load factors and acceptance criteria in Section 1708A.3.2 shall apply.

In the absence of applicable load test procedures contained within a standard referenced by this code or acceptance criteria for a specific material or method of construction, such existing structure shall be subjected to a test procedure developed by a registered design professional that simulates applicable loading and deformation conditions. For components that are not a part of the seismic force-resisting system, at a minimum the test load shall be equal to the specified factored design loads. For materials such as wood that have strengths that are dependent on load duration, the test load shall be adjusted to account for the difference in load duration of the test compared to the expected duration of the design loads being considered. For statically loaded components, the test load shall be left in place for a period of 24 hours. For components that carry dynamic loads (e.g., machine supports or fall arrest anchors), the load shall be left in place for a period consistent with the component’s actual function. The structure shall be considered to have successfully met the test requirements where the following criteria are satisfied:

  1. Under the design load, the deflection shall not exceed the limitations specified in Section 1604.3.
  2. Within 24 hours after removal of the test load, the structure shall have recovered not less than 75 percent of the maximum deflection.
  3. During and immediately after the test, the structure shall not show evidence of failure.
Where proposed construction is not capable of being designed by approved engineering analysis, or where proposed construction design method does not comply with the applicable material design standard, the system of construction or the structural unit and the connections shall be subjected to the tests prescribed in Section 1709A. The building official shall accept certified reports of such tests conducted by an approved testing agency, provided that such tests meet the requirements of this code and approved procedures.
Where specific load test procedures, load factors and acceptance criteria are included in the applicable referenced standards, such test procedures, load factors and acceptance criteria shall apply. In the absence of specific test procedures, load factors or acceptance criteria, the corresponding provisions in Section 1709A.3 shall apply.
Where load test procedures are not specified in the applicable referenced standards, the load-bearing and deformation capacity of structural components and assemblies shall be determined on the basis of a test procedure developed by a registered design professional that simulates applicable loading and deformation conditions. For components and assemblies that are not a part of the seismic force-resisting system, the test shall be as specified in Section 1709A.3.1. Load tests shall simulate the applicable loading conditions specified in Chapter 16.

The test assembly shall be subjected to an increasing superimposed load equal to not less than two times the superimposed design load. The test load shall be left in place for a period of 24 hours. The tested assembly shall be considered to have successfully met the test requirements if the assembly recovers not less than 75 percent of the maximum deflection within 24 hours after the removal of the test load. The test assembly shall then be reloaded and subjected to an increasing superimposed load until either structural failure occurs or the superimposed load is equal to two and one-half times the load at which the deflection limitations specified in Section 1709A.3.2 were reached, or the load is equal to two and one-half times the superimposed design load. In the case of structural components and assemblies for which deflection limitations are not specified in Section 1709A.3.2, the test specimen shall be subjected to an increasing superimposed load until structural failure occurs or the load is equal to two and one-half times the desired superimposed design load. The allowable superimposed design load shall be taken as the lesser of:

  1. The load at the deflection limitation given in Section 1709A.3.2.
  2. The failure load divided by 2.5.
  3. The maximum load applied divided by 2.5.
The deflection of structural members under the design load shall not exceed the limitations in Section 1604.3.
Load-bearing wall and partition assemblies shall sustain the test load both with and without window framing. The test load shall include all design load components. Wall and partition assemblies shall be tested both with and without door and window framing.

The design pressure rating of exterior windows and doors in buildings shall be determined in accordance with Section 1709A.5.1 or 1709A.5.2. For the purposes of this section, the required design pressure shall be determined using the allowable stress design load combinations of Section 1605.3.

Exception: Structural wind load design pressures for window units smaller than the size tested in accordance with Section 1709A.5.1 or 1709A.5.2 shall be permitted to be higher than the design value of the tested unit provided such higher pressures are determined by accepted engineering analysis. All components of the small unit shall be the same as the tested unit. Where such calculated design pressures are used, they shall be validated by an additional test of the window unit having the highest allowable design pressure.

Exterior windows and sliding doors shall be tested and labeled as conforming to AAMA/WDMA/CSA101/I.S.2/A440. The label shall state the name of the manufacturer, the approved labeling agency and the product designation as specified in AAMA/WDMA/CSA101/I.S.2/A440. Exterior side-hinged doors shall be tested and labeled as conforming to AAMA/WDMA/CSA101/I.S.2/A440 or comply with Section 1709.5.2. Products tested and labeled as conforming to AAMA/WDMA/CSA 101/I.S.2/A440 shall not be subject to the requirements of Sections 2403.2 and 2403.3.
Exterior window and door assemblies shall be tested in accordance with ASTM E330. Structural performance of garage doors and rolling doors shall be determined in accordance with either ASTM E330 or ANSI/DASMA 108, and shall meet the acceptance criteria of ANSI/DASMA 108. Exterior window and door assemblies containing glass shall comply with Section 2403. The design pressure for testing shall be calculated in accordance with Chapter 16. Each assembly shall be tested for 10 seconds at a load equal to 1.5 times the design pressure.
Skylights and sloped glazing shall comply with the requirements of Chapter 24.
Test specimens and construction shall be representative of the materials, workmanship and details normally used in practice. The properties of the materials used to construct the test assembly shall be determined on the basis of tests on samples taken from the load assembly or on representative samples of the materials used to construct the load test assembly. Required tests shall be conducted or witnessed by an approved agency.