1926.1404(f) Working Under the Boom, Jib or Other Components
JUMP TO FULL CODE CHAPTER
When pins (or similar devices) are being removed, employees must not be under the boom, jib, or other components, except where the requirements of paragraph (f)(2) of this section are met.
Where the employer demonstrates that site constraints require one or more employees to be under the boom, jib, or other components when pins (or similar devices) are being removed, the A/D director must implement procedures that minimize the risk of unintended dangerous movement and minimize the duration and extent of exposure under the boom. (See Non-mandatory Appendix B of this subpart for an example.)
Related Code Sections
1926.1404(f) Cranes & Derricks in Construction, Working Under the Boom, Jib or Other Components
When pins (or similar devices) are being removed, employees must not be under the boom, jib, or other components, except where the requirements ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1404 Assembly/Disassembly--General Requirements (Applies to All Assembly and Disassembly Operations) > 1926.1404(f) Working Under the Boom, Jib or Other Components
Subpart CC Cranes & Derricks in Construction, App B - Assembly/Disassembly--Sample Procedures for Minimizing the Risk of Unintended Dangerous Boom Movement
constraints require one or more employees to be under the boom, jib, or other components when pins (or similar devices) are being removed. In ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > CC App B - Assembly/Disassembly--Sample Procedures for Minimizing the Risk of Unintended Dangerous Boom Movement
1926.1431(d)(5) Cranes & Derricks in Construction, Devices
prevents damage and load failure from contact between the load block, overhaul ball, or similar component, and the boom tip (or fixed upper block ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1431 Hoisting Personnel > 1926.1431(d) Equipment Criteria > 1926.1431(d)(5) Devices
1926.1431(d) Cranes & Derricks in Construction, Equipment Criteria
platform is in a stationary working position, the load and boom hoist brakes, swing brakes, and operator actuated secondary braking and locking features ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1431 Hoisting Personnel > 1926.1431(d) Equipment Criteria
1926.1404 Cranes & Derricks in Construction, Assembly/Disassembly--General Requirements (Applies to All Assembly and Disassembly Operations)
removed, employees must not be under the boom, jib, or other components, except where the requirements of paragraph (f)(2) of this section are met ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1404 Assembly/Disassembly--General Requirements (Applies to All Assembly and Disassembly Operations)