Section G101 Vacuum Drainage System
JUMP TO FULL CODE CHAPTER
This appendix provides general guidelines for the requirements for vacuum drainage systems.
Vacuum drainage systems shall be designed in accordance with manufacturer's recommendations. The system layout, including piping layout, tank assemblies, vacuum pump assembly and other components/designs necessary for proper function of the system shall be per manufacturer's recommendations. Plans, specifications and other data for such systems shall be submitted to the local administrative authority for review and approval prior to installation.
Fixture units for gravity drainage systems which discharge into or receive discharge from vacuum drainage systems shall be based on values in Chapter 7 of this code.
Vacuum drainage pipe, fitting and valve materials shall be as recommended by the vacuum drainage system manufacturer and as permitted by this code.
After completion of the entire system installation, the system shall be subjected to a vacuum test of 19 inches (483 mm) of mercury and shall be operated to function as required by the administrative authority and the manufacturer. Recorded proof of all tests shall be submitted to the administrative authority.
Written instructions for the operations, maintenance, safety and emergency procedures shall be provided by the building owner as verified by the administrative authority.
Related Code Sections
Section 715 Sanitary Drainage, Vacuum Drainage Systems
Vacuum drainage systems shall be in accordance with Sections 715.2 through 715.4 ...
Section 716 Sanitary Drainage, Vacuum Drainage Systems
Vacuum drainage systems shall be in accordance with Sections 716.2 through 716.4 ...
Section G101 Vacuum Drainage System, Vacuum Drainage System
This appendix provides general guidelines for the requirements for vacuum drainage systems ...
G101.2.1 Vacuum Drainage System, System Design
Vacuum drainage systems shall be designed in accordance with manufacturer's recommendations. The system layout, including piping layout, tank ...
2010 Plumbing Code of NY > G Vacuum Drainage System > G101 Vacuum Drainage System > G101.2 General Requirements > G101.2.1 System Design