// CODE SNIPPET
Section 306 Trenching, Excavation and Backfill
JUMP TO FULL CODE CHAPTER
Buried piping shall be supported throughout its entire length.
Where trenches are excavated such that the bottom of the trench forms the bed for the pipe, solid and continuous load-bearing support shall be provided between joints. Bell holes, hub holes and coupling holes shall be provided at points where the pipe is joined. Such pipe shall not be supported on blocks to grade. In instances where the materials manufacturer's installation instructions are more restrictive than those prescribed by the code, the material shall be installed in accordance with the more restrictive requirement.
Where trenches are excavated below the installation level of the pipe such that the bottom of the trench does not form the bed for the pipe, the trench shall be backfilled to the installation level of the bottom of the pipe with sand or fine gravel placed in layers not greater than 6 inches (152 mm) in depth and such backfill shall be compacted after each placement.
Where rock is encountered in trenching, the rock shall be removed to not less than 3 inches (76 mm) below the installation level of the bottom of the pipe, and the trench shall be backfilled to the installation level of the bottom of the pipe with sand tamped in place so as to provide uniform load-bearing support for the pipe between joints. The pipe, including the joints, shall not rest on rock at any point.
If soft materials of poor load-bearing quality are found at the bottom of the trench, stabilization shall be achieved by overexcavating not less than two pipe diameters and backfilling to the installation level of the bottom of the pipe with fine gravel, crushed stone or a concrete foundation. The concrete foundation shall be bedded with sand tamped into place so as to provide uniform load-bearing support for the pipe between joints.
Backfill shall be free from discarded construction material and debris. Loose earth free from rocks, broken concrete and frozen chunks shall be placed in the trench in 6-inch (152 mm) layers and tamped in place until the crown of the pipe is covered by 12 inches (305 mm) of tamped earth. The backfill under and beside the pipe shall be compacted for pipe support. Backfill shall be brought up evenly on both sides of the pipe so that the pipe remains aligned. In instances where the manufacturer's instructions for materials are more restrictive than those prescribed by the code, the material shall be installed in accordance with the more restrictive requirement.
Where pipe is to be installed by tunneling, jacking or a combination of both, the pipe shall be protected from damage during installation and from subsequent uneven loading. Where earth tunnels are used, adequate supporting structures shall be provided to prevent future settling or caving.
Related Code Sections
10.9 Underground Piping, Backfilling
trenches cut through rock, tamped backfill shall be used for at least 6 in. (150 mm) under and around the pipe and for at least 2 ft (0.6 m) above the pipe ...
Standard for the Installation of Sprinkler Systems 2013 of Colorado > 10 Underground Piping > 10.9 Backfilling
(E) Wiring Methods and Materials, Backfill
Backfill containing large rocks, paving materials, cinders, large or sharply angular substances, or corrosive materials shall not be placed ...
National Electrical Code 2020 of Colorado > 3 Wiring Methods and Materials > 300 General Requirements for Wiring Methods and Materials > 300.50 Underground Installations > (E) Backfill
1804.3 Soils and Foundations, Placement of Backfill
The excavation outside the foundation shall be backfilled with soil that is free of organic material, construction debris, cobbles and boulders ...
Building Code of the Department of Personnel & Administration/Office of the State Architect (DPA/OSA) > 18 Soils and Foundations > 1804 Excavation, Grading and Fill > 1804.3 Placement of Backfill
1804.3 Soils and Foundations, Placement of Backfill
The excavation outside the foundation shall be backfilled with soil that is free of organic material, construction debris, cobbles and boulders ...