611.3.3.3 Time Switch and Programmable Schedule Controls
Green Construction Code 2012 of Maryland > 6 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION > 611 Energy Systems Commissioning and Completion > 611.3 Lighting and Electrical Systems Commissioning and Completion Requirements > 611.3.3 Commissioning > 611.3.3.3 Time Switch and Programmable Schedule Controls
Go To Full Code Chapter
Lighting controls installed in accordance with Section 608 shall be programmed. Scheduling shall incorporate weekday, weekend and holiday operating times, including leap year and daylight savings time corrections. It shall be verified that system overrides work and are located in compliance with Section C405.2 of the International Energy Conservation Code.
Upcodes Diagrams
Related Code Sections
611.3.3.3 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION, Time Switch and Programmable Schedule Controls
Lighting controls installed in accordance with Section 608 shall be programmed. Scheduling shall incorporate weekday, weekend and holiday operating ...
Green Construction Code 2012 of Maryland > 6 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION > 611 Energy Systems Commissioning and Completion > 611.3 Lighting and Electrical Systems Commissioning and Completion Requirements > 611.3.3 Commissioning > 611.3.3.3 Time Switch and Programmable Schedule Controls
9.4.3 Lighting, Functional Testing
switches, programmable schedule controls, or photosensors are installed, at a minimum, the following procedures shall be performed: Occupant Sensors ...
9.4.3 Lighting, Functional Testing
switches, programmable schedule controls, or photosensors are installed, at a minimum, the following procedures shall be performed: Occupant Sensors ...
9.9 Lighting, Verification, Testing, and Commissioning
installation instructions. When occupancy sensors, time switches, programmable schedule controls, or photosensors are installed, at a minimum, the following ...
C403.2.4.2 [CE] Commercial Energy Efficiency, Off-Hour Controls
Each zone shall be provided with thermostatic setback controls that are controlled by either an automatic time clock or programmable control system ...