7-129 Time Limitations
- Final construction documents shall be submitted to the Office within one year of the date of the Office's report on preliminary plans and outline specifications or the application shall become void unless an extension has been requested and approved. The architect or engineer in responsible charge may request one extension of up to 180 calendar days; however, the Office may require that the construction documents meet current regulations. The extension must be requested in writing and justifiable cause demonstrated.
The procedures leading to obtaining written approval of final construction documents shall be carried to conclusion without suspension or unnecessary delay. Unless an extension has been approved by the Office, the application shall become void when either paragraph 1 or 2 occurs:
- Prints from corrected construction documents are not filed for backcheck within 90 calendar days after the date of return of checked construction documents to the architect or engineer in responsible charge. Backcheck submittals that do not contain a written response to all comments in accordance with Section 7-125 (c) shall not be considered an official submittal to the Office. The architect or engineer in responsible charge may request one extension of up to 90 calendar days; however, the Office may require the construction documents be revised to meet current regulations. The extension must be requested in writing and justifiable cause demonstrated.
- A set of prints of the stamped construction documents are not submitted to the Office within 45 calendar days after the date shown with the identification stamp by the Office.
- Construction, in accordance with the approved construction documents, shall commence within one year after obtaining the written approval of construction documents, or this approval shall become void. Prior to the approval becoming void, the applicant may apply for one extension of up to one year. The Office may require that the construction documents be revised to meet current regulations before granting an extension. The extensions must be requested in writing and justifiable cause demonstrated.
If the work of construction is suspended or abandoned for any reason for a period of one year following its commencement, the Office's approval shall become void. Prior to the approval becoming void, the applicant may apply for one extension of up to one year. The Office may require that the construction documents be revised to meet current regulations before granting an extension. The extensions must be requested in writing and justifiable cause demonstrated.
Exception: The time limitations and deadlines specified in Section 7-129 shall not apply to managed projects as defined in Section 7-111. This includes, but is not limited to, projects approved for phased plan review, as described in Section 7-130, or incremental review, as described in Section 7-131.
Authority: Health and Safety Code Sections 18929 and 129675—130070.
Reference: Health and Safety Code Section 129850.