1910.1029(f)(6)(ii)(a)
A description of each coke oven operation by battery, including work force and operating crew, coking time, operating procedures and maintenance practices;
1910.1029(f)(6)(ii)(b)
Engineering plans and other studies used to determine the controls for the coke battery;
1910.1029(f)(6)(ii)(c)
A report of the technology considered in meeting the permissible exposure limit;
1910.1029(f)(6)(ii)(d)
Monitoring data obtained in accordance with paragraph (e) of this section;
1910.1029(f)(6)(ii)(e)
A detailed schedule for the implementation of the engineering and work practice controls required in paragraph (f) of this section; and
1910.1029(f)(6)(ii)(f) Other Relevant Information