1926.754(b) The Following Additional Requirements Shall Apply for Multi-Story Structures:

Jump To Full Code Chapter
1926.754(b)(1)
The permanent floors shall be installed as the erection of structural members progresses, and there shall be not more than eight stories between the erection floor and the upper-most permanent floor, except where the structural integrity is maintained as a result of the design.
1926.754(b)(2)
At no time shall there be more than four floors or 48 feet (14.6 m), whichever is less, of unfinished bolting or welding above the foundation or uppermost permanently secured floor, except where the structural integrity is maintained as a result of the design.
1926.754(b)(3)
A fully planked or decked floor or nets shall be maintained within two stories or 30 feet (9.1 m), whichever is less, directly under any erection work being performed.

Related Code Sections

1926.750(a) Steel Erection,
, alteration, and/or repair of single and multi-story buildings, bridges, and other structures where steel erection occurs. The requirements ...
1926.760(a)(2) Steel Erection, Perimeter Safety Cables
On multi-story structures, perimeter safety cables shall be installed at the final interior and exterior perimeters of the floors as soon ...
1926.452(v) Scaffolds, Multi-Level Suspended Scaffolds
Scaffolds shall be equipped with additional independent support lines, equal in number to the number of points supported, and of equivalent strength ...
1926.1101(d) Toxic and Hazardous Substances, Multi-Employer Worksites
On multi-employer worksites, an employer performing work requiring the establishment of a regulated area shall inform other employers on the site ...