The building official shall give permission to energize the electrical service equipment of a one-family or two-family dwelling unit when all of the following requirements have been approved:
  1. The service wiring and equipment, including the meter socket enclosure, shall be installed and the service wiring terminated.
  2. The grounding electrode system shall be installed and terminated.
  3. At least one receptacle outlet on a ground fault protected circuit shall be installed and the circuit wiring terminated.
  4. Service equipment covers shall be installed.
  5. The building roof covering shall be installed.
  6. Temporary electrical service equipment shall be suitable for wet locations unless the interior is dry and protected from the weather.

Related Code Sections

2701.1.2 Electrical, Temporary Connection to Dwelling Units
The building official shall give permission to energize the electrical service equipment of a one- or two-family dwelling unit when all ...
2701.1.2 Electrical, Temporary Connection to Dwelling Units
The building official shall give permission to energize the electrical service equipment of a one- or two-family dwelling unit when all ...
2701.1.2 Electrical, Temporary Connection to Dwelling Units
The building official shall give permission to energize the electrical service equipment of a one-family or two-family dwelling unit when all ...
220.82 Wiring and Protection, Dwelling Unit
This section applies to a dwelling unit having the total connected load served by a single 120/240-volt or 208Y/120-volt set of 3-wire service ...
106.18 Scope and Administration, Temporary Connection
The code official shall have the authority to authorize the temporary connection of the building or system to the utility source for the purpose ...