The results of the investigation and evaluation as required in Section 3412.4, along with proposed compliance alternatives, shall be submitted to the building official.

Related Code Sections

104.11.2 Scope and Administration, Submittal
The registered design professional shall indicate on the permit application that the system is an alternative engineered design. The permit ...
105.4.1 Scope and Administration, Submittals
Construction documents and supporting data shall be submitted in two or more sets with each application for a permit and in such form and detail ...
105.4.1 Scope and Administration, Submittals
Construction documents and supporting data shall be submitted in two or more sets with each application for a permit and in such form and detail ...
1301.4.2 Performance Compliance Methods, Submittal
The results of the investigation and evaluation as required in Section 1301.4, along with proposed compliance alternatives, shall be submitted ...
1401.4.2 Performance Compliance Methods, Submittal
The results of the investigation and evaluation as required in Section 1401.4, along with proposed compliance alternatives, shall be submitted ...