3102F.3.5.1.1 Above Water Structural Inspection
The above water inspection shall include all accessible components above and below deck that are reachable without the need for excavation or extensive removal of materials that may impair visual inspection. The above water inspection shall include, but not be limited to, the following:
  1. Piles
  2. Pile caps
  3. Beams
  4. Deck soffit
  5. Bracing
  6. Retaining walls and bulkheads
  7. Connections
  8. Seawalls
  9. Slope protection
  10. Deck topsides and curbing
  11. Expansion joints
  12. Fender system components
  13. Dolphins and deadmen
  14. Mooring points and hardware
  15. Navigation aids
  16. Platforms, ladders, stairs, handrails and gangways
  17. Backfill (sinkholes/differential settlement)
3102F.3.5.1.2 Underwater Structural Inspection
The underwater inspection shall include all components below deck to the mudline, including the slope and slope protection, in areas immediately surrounding the MOT. The water depth at the berth(s) shall be evaluated, verifying the maximum or loaded draft specified in the MOT's Operations Manual (2 CCR 2385) [2.1].
The underwater structural inspection shall include the Level I, II and III inspection efforts, as shown in Tables 31F-2-2 and 31F-2-3. The underwater inspection levels of effort are described below, per [2.2]:
Level I—Includes a close visual examination, or a tactile examination using large sweeping motions of the hands where visibility is limited. Although the Level I effort is often referred to as a "swim-by" inspection, it must be detailed enough to detect obvious major damage or deterioration due to overstress or other severe deterioration. It should confirm the continuity of the full length of all members and detect undermining or exposure of normally buried elements. A Level I effort may also include limited probing of the substructure and adjacent channel bottom.
Level II—A detailed inspection which requires marine growth removal from a representative sampling of components within the structure. For piles, a 12-inch high band shall be cleaned at designated locations, generally near the low waterline, at the mudline, and midway between the low waterline and the mudline. On a rectangular pile, the marine growth removal should include at least three sides; on an octagon pile, at least six sides; on a round pile, at least three-fourths of the perimeter. On large diameter piles, 3 ft or greater, marine growth removal should be effected on 1 ft by 1 ft areas at four locations approximately equally spaced around the perimeter, at each elevation. On large solid faced elements such as retaining structures, marine growth removal should be effected on 1 ft by 1 ft areas at the three specified elevations. The inspection should also focus on typical areas of weakness, such as attachment points and welds. The Level II effort is intended to detect and identify damaged and deteriorated areas that may be hidden by surface biofouling. The thoroughness of marine growth removal should be governed by what is necessary to discern the condition of the underlying structural material. Removal of all biofouling staining is generally not required.
Level III—A detailed inspection typically involving nondestructive or partially-destructive testing, conducted to detect hidden or interior damage, or to evaluate material homogeneity. Level III testing is generally limited to key structural areas, areas which are suspect or areas which may be representative of the underwater structure.

Related Code Sections

3102F.3.5.1 [SLC] Marine Oil Terminals, Structural Inspections
CCR 2385) [2.1]. The underwater structural inspection shall include the Level I, II and III inspection efforts, as shown in Tables 31F-2-2 and 31F-2-3 ...
3102F.3.5.1 [SLC] Marine Oil Terminals, Structural Inspections
Operations Manual (2 CCR 2385) [2.1]. The underwater structural inspection shall include the Level I, II and III inspection efforts, as shown ...
3102F.3.5.1 [SLC] Marine Oil Terminals, Structural Inspections
CCR 2385) [2.1]. The underwater structural inspection shall include the Level I, II and III inspection efforts, as shown in Tables 31F-2-2 and 31F-2-3 ...