3303.4.5.2 Storage of Materials at Top Working Floors
JUMP TO FULL CODE CHAPTER
Storage of materials at top working floors shall comply with the following:
- Material may be stored within 2 feet (610 mm) of the edge of a building provided that such material is stored not more than two stories below the stripping operation on concrete structures, or the uppermost concrete floor on steel frame structures. Such material shall be secured against accidental movement. Storage of material on all other floors shall conform to Section 3303.4.5.1 and shall be secured when not being used.
- No material shall hang over the edge of a building unless banded and braced preparatory to relocation at the end of the workday. Where such material is so banded and braced, it may overhang the floor of the stripping operation by not more than one-third of its length so long as it is relocated on the next workday for concrete operations.
- Where the steel mill and lumber mill are located, material may overhang for relocation until the next workday. No more than two floors shall be designated as steel mills or lumber mills.
Related Code Sections
3303.4.5.2 Safeguards During Construction or Demolition, Storage of Materials at Top Working Floors
Storage of materials at top working floors shall comply with the following: Material may be stored within 2 feet (610 mm) of the edge of a building ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3303 Safeguards and Maintenance of Site > 3303.4 Housekeeping > 3303.4.5 Storage of Materials During Construction or Demolition > 3303.4.5.2 Storage of Materials at Top Working Floors
Appendix A Selected Rules of the Department of Buildings [PDF] (page 77)
when not being used. (c) Storage of materials at top working floors. (1) Material may be stored to within two feet of the edge of the building ...
3307.4.7 Safeguards During Construction or Demolition, Work or Storage Zones
Where work or storage related to the construction or demolition of a building or structure is occurring adjacent to a sidewalk shed or equivalent ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3307 Protection of Pedestrians > 3307.4 Warning Signs, Personnel, and Barriers > 3307.4.7 Work or Storage Zones
3306.9.11 Safeguards During Construction or Demolition, Storage of Material
Material shall not be stored on catch platforms, working platforms, floors, or stairways of any structure, except that any one floor of a building ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3306 Demolition > 3306.9 Full Demolition and Partial Demolition Operations > 3306.9.11 Storage of Material
3306.9.11 Safeguards During Construction or Demolition, Storage of Material
Material shall not be stored on catch platforms, working platforms, floors, or stairways of any structure, except that any one floor of a building ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3306 Demolition > 3306.9 Safeguards > 3306.9.11 Storage of Material