Where employers elect, due to conditions specific to the site, to develop alternate means and methods that provide employee protection in accordance with § 1926.753(c)(5), § 1926.757(a)(4) or § 1926.757(e)(4), a site-specific erection plan shall be developed by a qualified person and be available at the work site. Guidelines for establishing a site-specific erection plan are contained in Appendix A to this subpart.

[66 FR 5267, Jan. 18, 2001]

Related Code Sections

1926.752(e) Steel Erection, Site-Specific Erection Plan
with § 1926.753(c)(5), § 1926.757(a)(4) or § 1926.757(e)(4), a site-specific erection plan shall be developed by a qualified person and be available ...
1926.752(c)(1) Steel Erection,
Adequate access roads into and through the site for the safe delivery and movement of derricks, cranes, trucks, other necessary equipment ...
1926.752(c)(2) Steel Erection,
A firm, properly graded, drained area, readily accessible to the work with adequate space for the safe storage of materials and the safe operation ...