The controlling contractor shall ensure that the following is provided and maintained:
1926.752(c)(1)
Adequate access roads into and through the site for the safe delivery and movement of derricks, cranes, trucks, other necessary equipment, and the material to be erected and means and methods for pedestrian and vehicular control. Exception: this requirement does not apply to roads outside of the construction site.
1926.752(c)(2)
A firm, properly graded, drained area, readily accessible to the work with adequate space for the safe storage of materials and the safe operation of the erector's equipment.

Related Code Sections

1926.752(c) Steel Erection, Site Layout
: Adequate access roads into and through the site for the safe delivery and movement of derricks, cranes, trucks ...
1926.752(b) Steel Erection, Commencement of Steel Erection
A steel erection contractor shall not erect steel unless it has received written notification that the concrete in the footings, piers and walls ...
1926.752(a)(1) Steel Erection,
The concrete in the footings, piers and walls and the mortar in the masonry piers and walls has attained, on the basis of an appropriate ASTM standard ...