UpCodes logo
Go To Full Code Chapter
Before employees handle the units, the employer shall short circuit each unit in series-parallel capacitor banks between all terminals and the capacitor case or its rack. If the cases of capacitors are on ungrounded substation racks, the employer shall bond the racks to ground.

Related Code Sections

1926.900(k)(1) Blasting and the Use of Explosives,
Detonators shall be short-circuited in holes which have been primed and shunted until wired into the blasting circuit ...
1926.906(j) Blasting and the Use of Explosives,
shall be made so it can be locked only in the "Off" position and shall be provided with a short-circuiting arrangement of the firing lines to the cap ...
1926.952(d)(1) Electric Power Transmission and Distribution, Short Discussion
A brief discussion is satisfactory if the work involved is routine and if the employees, by virtue of training and experience, can reasonably ...