// CODE SNIPPET
1101.12.2.2.1 Separate Piping System
Go To Full Code Chapter
The secondary roof drainage system shall be a separate system of piping, independent of the primary roof drainage system. The discharge shall be above grade, in a location observable by the building occupants or maintenance personnel. Secondary roof drain systems shall be sized in accordance with Section 1101.12.1 based on the rainfall rate for which the primary system is sized.
Upcodes Diagrams
Related Code Sections
1101.12.2.2.1 Storm Drainage, Separate Piping System
The secondary roof drainage system shall be a separate system of piping, independent of the primary roof drainage system. The discharge shall ...
16.15.1.3 Installation of Piping, Valves, and Appurtenances,
Hose connections shall be supplied from one of the following: Outside hydrants Separate piping system for small hose connections Valved hose ...
8.17.5.1.3 Installation Requirements,
Hose connections shall be supplied from one of the following: Outside hydrants Separate piping system for small hose connections Valved hose ...
(1) Wiring and Protection, Metal Water Piping System(s)
The grounded conductor of each separately derived system shall be bonded to the nearest available point of the metal water piping system(s ...
G2412.6 Fuel Gas, (401.6) Interconnections
Where two or more meters are installed on the same premises but supply separate consumers, the piping systems shall not be interconnected ...