110.9 Satisfactory Inspection Report Required

Go To Full Code Chapter
Portions of work requiring inspection may be sequenced or phased to allow continuing progress of that work provided that work shall not be done beyond the point indicated in each successive required inspection for that phase. The inspector shall either indicate the portion of the construction that is satisfactory as completed, or notify the permit holder or the superintendent of construction wherein the same fails to comply with this code. Any portions that do not comply shall be corrected and such portion shall not be covered or concealed until corrected. The person performing the inspection shall complete a report of satisfactory inspection. Refer to Chapter 1 of Title 28 of the Administrative Code.
Upcodes Diagrams

Related Code Sections

109.9 Administration, Satisfactory Inspection Report Required
shall complete a report of satisfactory inspection. Refer to Chapter 1 of Title 28 of the Administrative Code ...
110.9 Administration, Satisfactory Inspection Report Required
shall complete a report of satisfactory inspection. Refer to Chapter 1 of Title 28 of the Administrative Code ...
110.9 Administration, Satisfactory Inspection Report Required
shall complete a report of satisfactory inspection. Refer to Chapter 1 of Title 28 of the Administrative Code ...
§28-116.4 Administration, Sign-Off of Completed Work
Upon submission of a satisfactory report of final inspection and all required submittal documents, the department shall document the sign-off ...
§28-116.4 Administration, Sign-Off of Completed Work
Upon submission of a satisfactory report of final inspection and all required submittal documents, the department shall document the sign-off ...