When a rope bridle is used to suspend the personnel platform, each bridle leg must be connected to a master link or shackle (see paragraph (g)(1) of this section) in a manner that ensures that the load is evenly divided among the bridle legs.
Upcodes Diagrams

Related Code Sections

1926.1431(g)(2) Cranes and Derricks in Construction, Rope Bridle
When a rope bridle is used to suspend the personnel platform, each bridle leg must be connected to a master link or shackle (see paragraph (g)(1 ...
1926.1431(g)(5) Cranes and Derricks in Construction,
Bridles and associated rigging for suspending the personnel platform must be used only for the platform and the necessary employees, their tools ...