  1. General. No additional fee is charged upon submission of revisions to the approved plans and specifications, provided that the entire matter is actually one transaction having to do with the same essential services building and the revisions do not require substantial review for safety of design. If the original plans are abandoned and the plans and specifications submitted in lieu thereof are in fact for a new project rather than an identical building or where a modified set of plans is for an essentially different structural concept, it is necessary that a new application be filed and fee paid. This is regardless of the fact that the building may have the same name, be of the same general size and be situated at the same location as the essential services building for which the original application was submitted.
  2. Addenda. Changes or alterations of the approved plans or specifications prior to letting a construction contract for the work involved shall be made by means of addenda. Addenda shall be stamped and signed by the architect or registered engineer in general responsible charge of preparation of the plans and specifications, and by the architect or registered engineer delegated responsibility for the portion affected by the addenda. Addenda shall be submitted to DSA for review and approval and as such become part of the approved contract documents.
  3. Construction change documents. Changes or alterations of the approved plans or specifications after a contract for the work has been let shall be made by means of construction change documents. Construction change documents shall state the reason for the change and shall be accompanied by supplementary drawings and calculations where necessary. All construction change documents shall be stamped and signed by the architect or registered engineer in general responsible charge of the work of construction of the project, and by the architect or registered engineer delegated responsibility for observation of the portion of the work of construction affected by the construction change documents. Construction change documents shall be submitted to DSA for review and approval and as such become part of the approved contract documents.
Authority: Health and Safety Code Section 16022.
Reference: Health and Safety Code Section 16009.
Upcodes Diagrams

Related Code Sections