[A] 108.2 Required Inspections and Testing
Go To Full Code Chapter
The code official, upon notification from the permit holder or the permit holder's agent, shall make the following inspections and such other inspections as necessary, and shall either release that portion of the construction or shall notify the permit holder or an agent of any violations that must be corrected. The holder of the permit shall be responsible for the scheduling of such inspections.
- Underground inspection shall be made after trenches or ditches are excavated and bedded, piping installed, and before any backfill is put in place.
- Rough-in inspection shall be made after the roof, framing, fireblocking, firestopping, draftstopping and bracing is in place and all sanitary, storm and water distribution piping is roughed-in, and prior to the installation of wall or ceiling membranes.
- Final inspection shall be made after the building is complete, all plumbing fixtures are in place and properly connected, and the structure is ready for occupancy.
[A] 108.2.1 Other Inspections
In addition to the inspections specified in Section 108.2, the code official shall be authorized to make or require other inspections of any construction work to ascertain compliance with the provisions of this code and other laws that are enforced.
[A] 108.2.2 Inspection Requests
It shall be the duty of the holder of the permit or their duly authorized agent to notify the code official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspections of such work that are required by this code.
[A] 108.2.3 Approval Required
Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the code official. The code official, upon notification, shall make the requested inspections and shall either indicate the portion of the construction that is satisfactory as completed, or notify the permit holder or his or her agent wherein the same fails to comply with this code. Any portions that do not comply shall be corrected and such portion shall not be covered or concealed until authorized by the code official.
[A] 108.2.4 Approved Agencies
The code official is authorized to accept reports of approved inspection agencies, provided that such agencies satisfy the requirements as to qualifications and reliability.
[A] 108.2.5 Evaluation and Follow-Up Inspection Services
Prior to the approval of a closed, prefabricated plumbing system and the issuance of a plumbing permit, the code official shall require the submittal of an evaluation report on each prefabricated plumbing system indicating the complete details of the plumbing system, including a description of the system and its components, the basis on which the plumbing system is being evaluated, test results and similar information, and other data as necessary for the code official to determine conformance to this code.
[A] 108.2.5.1 Evaluation Service
The code official shall designate the evaluation service of an approved agency as the evaluation agency, and review such agency's evaluation report for adequacy and conformance to this code.
[A] 108.2.5.2 Follow-Up Inspection
Except where ready access is provided to all plumbing systems, service equipment and accessories for complete inspection at the site without disassembly or dismantling, the code official shall conduct the frequency of in-plant inspections necessary to ensure conformance to the approved evaluation report or shall designate an independent, approved inspection agency to conduct such inspections. The inspection agency shall furnish the code official with the follow-up inspection manual and a report of inspections on request, and the plumbing system shall have an identifying label permanently affixed to the system indicating that factory inspections have been performed.
[A] 108.2.5.3 Test and Inspection Records
Required test and inspection records shall be available to the code official at all times during the fabrication of the plumbing system and the erection of the building, or such records as the code official designates shall be filed.
Upcodes Diagrams
Related Code Sections
107.2 Scope and Administration, Required Inspections and Testing
performed. Required test and inspection records shall ...
107.2 Scope and Administration, Required Inspections and Testing
Required test and inspection records shall be available to the code official at all times during ...
107.2 Scope and Administration, Required Inspections and Testing
Required test and inspection records shall be available to the code official at all ...
107.2 Scope and Administration, Required Inspections and Testing
Required test and inspection records shall be available to the code official at all times during the fabrication ...
107.2 Scope and Administration, Required Inspections and Testing
All required test and inspection records shall be available to the code official at all times during the fabrication ...