3305.3.5.1 Removal Schedule
JUMP TO FULL CODE CHAPTER
Before starting construction, the contractor shall develop a procedure and schedule for removal of shores and installation of reshores and for calculating the loads transferred to the structure during the process.
The structural analysis and concrete strength data used in planning and implementing form removal and reshoring shall be furnished by the registered design professional responsible for the removal schedule to the commissioner when so requested.
No construction loads shall be supported on, nor any shoring removed from, any part of the structure under construction except when that portion of the structure in combination with the remaining forming and shoring system has sufficient strength to support safely its weight and the loads placed thereon.
Sufficient strength shall be demonstrated by structural analysis of the proposed loads, the strength of the forming and shoring system, and concrete strength data. Concrete strength data shall be based on tests of field-cured cylinders or, when approved by the commissioner, on other procedures for evaluating concrete strength.
Related Code Sections
1906.5.1 Concrete, Removal Schedule
Before starting construction, the contractor shall develop a procedure and schedule for removal of shores and installation of reshores ...
NYC Building Code 2008 > 19 Concrete > 1906 Formwork, Embedded Pipes and Construction Joints > 1906.5 Removal of Forms and Shoring > 1906.5.1 Removal Schedule
3305.3.5.1 Safeguards During Construction or Demolition, Removal Schedule
Before starting construction, the contractor shall develop a procedure and schedule for removal of shores and installation of reshores ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3305 Material Placement and Installation > 3305.3 Concrete Formwork > 3305.3.5 Removal of Forms and Shoring > 3305.3.5.1 Removal Schedule
3305.3.5.1.3 Safeguards During Construction or Demolition, Concrete Strength
Sufficient strength shall be demonstrated by structural analysis of the proposed loads, the strength of the forming and shoring system, and concrete ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3305 Material Placement and Installation > 3305.3 Concrete Formwork > 3305.3.5 Removal of Forms and Shoring > 3305.3.5.1 Removal Schedule > 3305.3.5.1.3 Concrete Strength
3305.3.5 Safeguards During Construction or Demolition, Removal of Forms and Shoring
and implementing form removal and reshoring shall be furnished by the registered design professional responsible for the removal schedule to the commissioner ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3305 Material Placement and Installation > 3305.3 Concrete Formwork > 3305.3.5 Removal of Forms and Shoring
1906.5 Concrete, Removal of Forms and Shoring
and implementing form removal and reshoring shall be furnished by the registered design professional responsible for the removal schedule to the commissioner when ...
NYC Building Code 2008 > 19 Concrete > 1906 Formwork, Embedded Pipes and Construction Joints > 1906.5 Removal of Forms and Shoring