1926.961(c)(10) Releasing Clearances
JUMP TO FULL CODE CHAPTER
To release a clearance, the employee in charge shall:
Notify each employee under that clearance of the pending release of the clearance;
Ensure that all protective grounds protecting employees under that clearance have been removed; and
Report this information to the system operator and then release the clearance.
Ensure that all employees under that clearance are clear of the lines and equipment;
Related Code Sections
1926.961(c)(10) Electric Power Transmission and Distribution, Releasing Clearances
To release a clearance, the employee in charge shall ...
OSHA 1926 Construction > V Electric Power Transmission and Distribution > 1926.961 Deenergizing Lines and Equipment for Employee Protection > 1926.961(c) Deenergizing Lines and Equipment > 1926.961(c)(10) Releasing Clearances
1926.961(c) Electric Power Transmission and Distribution, Deenergizing Lines and Equipment
be responsible for the clearance. To release a clearance ...
OSHA 1926 Construction > V Electric Power Transmission and Distribution > 1926.961 Deenergizing Lines and Equipment for Employee Protection > 1926.961(c) Deenergizing Lines and Equipment
1926.961 Electric Power Transmission and Distribution, Deenergizing Lines and Equipment for Employee Protection
release a clearance, the employee in charge shall ...
OSHA 1926 Construction > V Electric Power Transmission and Distribution > 1926.961 Deenergizing Lines and Equipment for Employee Protection
1926.961(c)(13) Electric Power Transmission and Distribution, Reenergizing Lines and Equipment
have been removed, all crews working on the lines or equipment release their clearances, all employees are clear of the lines and equipment, and all ...
OSHA 1926 Construction > V Electric Power Transmission and Distribution > 1926.961 Deenergizing Lines and Equipment for Employee Protection > 1926.961(c) Deenergizing Lines and Equipment > 1926.961(c)(13) Reenergizing Lines and Equipment
1926.961(c)(12) Electric Power Transmission and Distribution, Removal of Tags
No one may remove tags without the release of the associated clearance as specified under paragraphs (c)(10) and (c)(11) of this section ...
OSHA 1926 Construction > V Electric Power Transmission and Distribution > 1926.961 Deenergizing Lines and Equipment for Employee Protection > 1926.961(c) Deenergizing Lines and Equipment > 1926.961(c)(12) Removal of Tags