// CODE SNIPPET
§27-781 Refrigerating Systems
JUMP TO FULL CODE CHAPTER
The following test and inspection requirements shall be complied with in order to obtain an equipment use permit for a refrigerating system, except as hereinafter provided.
(a) Procedure. A refrigeration system shall be designated for test and inspection under the requirements for controlled inspection as provided in article eight of subchapter one of this chapter, except that it shall not be required that the architect or engineer be in the employ of the owner. Test information and all other information required by reference standard RS 13-6 shall be posted, and the inspection shall be made of the completed system to verify that the installation complies with the requirements of this subchapter.
(b) Temporary permits. A temporary equipment use permit shall be required for a nonoperating system in which a charge is maintained. See subchapter one of this chapter for provisions governing temporary permits.
(c) Exception. No equipment use permit or temporary equipment use permit shall be required for any refrigerating system exempted under the provisions of section 27-189 of article eighteen of subchapter one of this chapter; for any system using a group A2, B1 or B2 refrigerant and having a prime mover of one horsepower or less; or for any system using water or air as a refrigerant.
(a) Procedure. A refrigeration system shall be designated for test and inspection under the requirements for controlled inspection as provided in article eight of subchapter one of this chapter, except that it shall not be required that the architect or engineer be in the employ of the owner. Test information and all other information required by reference standard RS 13-6 shall be posted, and the inspection shall be made of the completed system to verify that the installation complies with the requirements of this subchapter.
(b) Temporary permits. A temporary equipment use permit shall be required for a nonoperating system in which a charge is maintained. See subchapter one of this chapter for provisions governing temporary permits.
(c) Exception. No equipment use permit or temporary equipment use permit shall be required for any refrigerating system exempted under the provisions of section 27-189 of article eighteen of subchapter one of this chapter; for any system using a group A2, B1 or B2 refrigerant and having a prime mover of one horsepower or less; or for any system using water or air as a refrigerant.
Related Code Sections
106.9 Administration, Refrigerating Systems
Construction documents for refrigerating systems shall contain plans that include the following data and information: The location of all machinery ...
NYC Mechanical Code 2008 > 1 Administration > 106 Construction Documents > 106.9 Refrigerating Systems
106.9 Administration, Refrigerating Systems
Construction documents for refrigerating systems shall contain plans that include the following data and information: The location of all machinery ...
NYC Mechanical Code 2014 > 1 Administration > 106 Construction Documents > 106.9 Refrigerating Systems
107.9 Administration, Refrigerating Systems
Construction documents for refrigerating systems shall contain plans that include the following data and information:
The location of all ...
NYC Mechanical Code 2022 > 1 Administration > 107 Construction Documents > 107.9 Refrigerating Systems
1106.5.1 Refrigeration, Refrigeration System
in the machinery room, other than refrigerant leak detectors and machinery room ventilation ...
NYC Mechanical Code 2008 > 11 Refrigeration > 1106 Machinery Room, Special Requirements > 1106.5 Remote Controls > 1106.5.1 Refrigeration System
1106.5.1 Refrigeration, Refrigeration System
in the machinery room, other than refrigerant leak detectors and machinery room ventilation ...
NYC Mechanical Code 2014 > 11 Refrigeration > 1106 Machinery Room, Special Requirements > 1106.5 Remote Controls > 1106.5.1 Refrigeration System