3310.8.4.1 Recording Inspections in the Site Safety Log
JUMP TO FULL CODE CHAPTER
Inspections shall be recorded by the end of the day by the site safety manager or coordinator who performed the inspection. The site safety log, or where there is more than one log, each individual log, shall be completed and signed by the site safety manager or coordinator who performed the inspection and by the site safety manager or coordinator designated as the primary site safety manager or coordinator in accordance with Section 3310.5.1.
Exception: Where a part time site safety manager or coordinator is approved by the commissioner in accordance with Section 3310.11, the site safety manager or coordinator shall sign the log when he or she arrives at the site and leaves the site, and all entries in the site safety log shall be completed and signed prior to leaving the site.
Exception: Where a part time site safety manager or coordinator is approved by the commissioner in accordance with Section 3310.11, the site safety manager or coordinator shall sign the log when he or she arrives at the site and leaves the site, and all entries in the site safety log shall be completed and signed prior to leaving the site.
Related Code Sections
3310.8.4.1 Safeguards During Construction or Demolition, Recording Inspections in the Site Safety Log
Inspections shall be recorded by the end of the day by the site safety manager or coordinator who performed the inspection. The site safety log ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3310 Requirements for the Construction or Demolition of Major Buildings > 3310.8 Site Safety Manager's and Coordinator's Duties > 3310.8.4 Site Safety Log > 3310.8.4.1 Recording Inspections in the Site Safety Log
3308.9.3 Safeguards During Construction or Demolition, Inspections
be performed by the site safety manager or coordinator, and a written record of such inspection maintained as part of the site safety log. Where the job does ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3308 Protection of Unenclosed Perimeters > 3308.9 Unenclosed Perimeter Protection Inspection, Use, Adjustment, Maintenance, and Repair > 3308.9.3 Inspections
Appendix A Selected Rules of the Department of Buildings [PDF] (page 80)
of the Administrative Code. H. Items to be recorded in Site Safety Log. 1. Details of areas inspected by the site safety manager. 2. Companies ...
3310.8.1.1 Safeguards During Construction or Demolition, Site Safety Manager or Coordinator Standpipe Inspection Responsibilities
the standpipe, including risers, cross connections and siamese connections. A record of all such inspections shall be maintained by such site safety manager ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3310 Requirements for the Construction or Demolition of Major Buildings > 3310.8 Site Safety Manager's and Coordinator's Responsibility > 3310.8.1 Monitor Compliance > 3310.8.1.1 Site Safety Manager or Coordinator Standpipe Inspection Responsibilities
3310.8.1 Safeguards During Construction or Demolition, Monitor Compliance
, cross connections and siamese connections. A record of all such inspections shall be maintained by such site safety manager or coordinator in a log ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3310 Requirements for the Construction or Demolition of Major Buildings > 3310.8 Site Safety Manager's and Coordinator's Responsibility > 3310.8.1 Monitor Compliance