3314.4.3.5 Pre-Shift Inspection for a Supported Scaffold
JUMP TO FULL CODE CHAPTER
Prior to each shift the supported scaffold shall be inspected by the competent person supervising the use of the scaffold in accordance with Section 3314.4.2.2 to verify the scaffold remains in a safe condition for use. The results of the inspection shall be documented in a pre-shift inspection report signed and dated by the person who performed the inspection. The scaffold shall not be used until it has passed such inspection and the pre-shift inspection report has been completed.
Exception: An inspection report is not required for a supported scaffold that is not required to be designed under Section 3314.3.1.
Exception: An inspection report is not required for a supported scaffold that is not required to be designed under Section 3314.3.1.
Related Code Sections
3314.4.3.5 Safeguards During Construction or Demolition, Pre-Shift Inspection for a Supported Scaffold
Prior to each shift the supported scaffold shall be inspected by the competent person supervising the use of the scaffold in accordance with Section ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3314 Scaffolds > 3314.4 Installation, Inspection, Repair, Maintenance, Adjustment, Use, and Removal of Scaffolds > 3314.4.3 Inspections > 3314.4.3.5 Pre-Shift Inspection for a Supported Scaffold
3314.4.3.4.1 Safeguards During Construction or Demolition, Responsibility for Performing the Inspection and Signing the Checklist
The inspection required by Section 3314.4.3.4 shall be performed by, and the checklist required by Section 3314.4.3.4.2 shall be signed and dated ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3314 Scaffolds > 3314.4 Installation, Inspection, Repair, Maintenance, Adjustment, Use, and Removal of Scaffolds > 3314.4.3 Inspections > 3314.4.3.4 Pre-Shift Inspection for a Suspended Scaffold > 3314.4.3.4.1 Responsibility for Performing the Inspection and Signing the Checklist
3314.10 Safeguards During Construction or Demolition, Suspended Scaffold
on them by the scaffold operating at the rated load of the hoist. The support shall be inspected prior to installation in accordance with the requirements ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3314 Scaffolds > 3314.10 Suspended Scaffold
Section 3314 Safeguards During Construction or Demolition, Scaffolds
sidewalk sheds; or a registered architect or professional engineer who is using a supported scaffold to perform inspections, as long as the architect ...
3314.10.2 Safeguards During Construction or Demolition, Support
of supporting at least 4 times the load imposed on them by the scaffold operating at the rated load of the hoist. The support shall be inspected ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3314 Scaffolds > 3314.10 Suspended Scaffold > 3314.10.2 Support