*3319.8.3 Pre-Jump Safety Meeting
JUMP TO FULL CODE CHAPTER
The general contractor must coordinate a pre-jump safety meeting no more than 24 hours prior to each instance of a tower or climber crane jump or climb. No work related to the jumping or climbing of the tower or climber crane may be performed without the pre-jump safety meeting having taken place. The following parties must be present at the pre-jump safety meeting:
- General contractor or designee;
- Licensed master, tower or climber crane rigger and rigger foreman;
- Site safety manager or coordinator, if required for the job by Chapter 33 of the building code;
- Licensed crane operator and oiler;
- "Jumping" crew and back-up personnel;
- Flagman/woman where required;
- Signalman/woman and communications personnel; and
- Any other parties the department deems necessary.
Related Code Sections
*3319.8.3 Safeguards During Construction or Demolition, Pre-Jump Safety Meeting
The general contractor must coordinate a pre-jump safety meeting no more than 24 hours prior to each instance of a tower or climber crane jump ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3319 Cranes and Derricks > 3319.8 Special Provisions for Tower and Climber Cranes > *3319.8.3 Pre-Jump Safety Meeting
3319.8.3 Safeguards During Construction or Demolition, Pre-Jump Safety Meeting
The general contractor must coordinate a pre-jump safety meeting no more than 24 hours prior to each instance of a tower or climber crane jump ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3319 Cranes and Derricks > 3319.8 Special Provisions for Tower and Climber Cranes > 3319.8.3 Pre-Jump Safety Meeting
3319.8.6 Safeguards During Construction or Demolition, Meeting Log
a log on site and available to the department at all times that shall include: The dates and times of all safety coordination meetings and pre-jump ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3319 Cranes and Derricks > 3319.8 Special Provisions for Tower and Climber Cranes > 3319.8.6 Meeting Log
3319.8.6 Safeguards During Construction or Demolition, Meeting Log
a log on site and available to the department at all times that shall include: the dates and times of all safety coordination meetings and pre-jump ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3319 Cranes and Derricks > 3319.8 Special Provisions for Tower and Climber Cranes > 3319.8.6 Meeting Log
3319.8 Safeguards During Construction or Demolition, Special Provisions for Tower and Climber Cranes
contractor must coordinate a pre-jump safety meeting no more than 24 hours prior to each instance of a tower or climber crane jump or climb. No work ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3319 Cranes and Derricks > 3319.8 Special Provisions for Tower and Climber Cranes