611.4 Pre-Certificate of Occupancy Commissioning Report
JUMP TO FULL CODE CHAPTER
A pre-certificate of occupancy report of commissioning test procedures and results shall be completed and certified by the registered design professional or approved agency and shall be provided to the building owner prior to final inspection. The report shall be identified as "Pre-Certificate of Occupancy Commissioning Report" and shall be assembled in accordance with Section 903.4.1
Buildings, or portions thereof, shall not pass the final mechanical inspection until such time as the code official has received a letter of transmittal from the building owner acknowledging that the building owner has received the pre-certificate of occupancy commissioning report.
At the request of the code official, a copy of the pre-certificate of occupancy commissioning report shall be made available for review.
The approved agency conducting commissioning shall verify that commissioned systems have been installed and perform in accordance with the approved construction documents. Any discrepancies shall be reviewed for compliance with requirements of the International Energy Conservation Code and this code.
A Systems Manual assembled in accordance with industry-accepted standards and Section 903.6.1 shall be provided to the owner before project completion.
Related Code Sections
611.4 Energy Conservation, Efficiency and Co2e Emission Reduction, Pre-Certificate of Occupancy Commissioning Report
A pre-certificate of occupancy report of commissioning test procedures and results shall be completed and certified by the registered design ...
Green Construction Code 2015 > 6 Energy Conservation, Efficiency and Co2e Emission Reduction > 611 Energy Systems Commissioning and Completion > 611.4 Pre-Certificate of Occupancy Commissioning Report
902.4.1 Commissioning, Inspections, Operation and Maintenance, Pre-Certificate of Occupancy Commissioning Report
The pre-certificate of occupancy commissioning report shall include the following: Performance of commissioned operations, equipment, systems ...
Green Construction Code 2015 > 9 Commissioning, Inspections, Operation and Maintenance > 902 Special Inspection and Commissioning > 902.4 Pre-Certificate of Occupancy Report Requirement > 902.4.1 Pre-Certificate of Occupancy Commissioning Report
Section 611 Energy Conservation, Efficiency and Co2e Emission Reduction, Energy Systems Commissioning and Completion
A pre-certificate of occupancy report of commissioning test ...
Green Construction Code 2015 > 6 Energy Conservation, Efficiency and Co2e Emission Reduction > 611 Energy Systems Commissioning and Completion
Section 902 Commissioning, Inspections, Operation and Maintenance, Special Inspection and Commissioning
The approved agency shall keep records of the pre-certificate of occupancy special inspection and commissioning required ...
Green Construction Code 2015 > 9 Commissioning, Inspections, Operation and Maintenance > 902 Special Inspection and Commissioning
903.1.2 Commissioning, Operation and Maintenance, Post-Occupancy Report Requirement
Post-occupancy commissioning shall occur as specified in the applicable sections of this code. A post-occupancy commissioning report shall ...
Green Construction Code 2012 > 9 Commissioning, Operation and Maintenance > 903 Commissioning > 903.1 General > 903.1.2 Post-Occupancy Report Requirement