112.5.1.1.3.11 Post-Rebuilding Clearance Testing
JUMP TO FULL CODE CHAPTER
A post-rebuilding clearance test prior to reoccupancy of the building or structure shall be conducted with the use of copper or silver coupons and the methodology outlined in the April 2, 2010, joint report by the Consumer Products Safety Commission and by the Department of Housing and Urban Development "Interim Remediation Guidance for Homes with Corrosion from Problem Drywall" or with the use of a copper probe and dosimeter. The clearance testing shall confirm that all airborne compounds associated with the defective drywall are at usual environmental background levels. The clearance testing report certifying compliance shall be submitted to the building official.
Notes:
- Where the building is served by a well and prior to conducting clearance tests, all outlets in piping served by the well should be capped or otherwise plugged to prevent contamination of the air sample.
- To prevent siphoning and evaporation of the trap seals, fixtures should be capped or otherwise plugged to prevent sewer gases from contaminating the air sample.
Related Code Sections
112.5.1.1.3.11 Administration, Post-Rebuilding Clearance Testing
A post-rebuilding clearance test prior to reoccupancy of the building or structure shall be conducted with the use of copper or silver coupons ...
2012 Virginia Construction Code (USBC, Part I) > 1 Administration > 112 Workmanship, Materials and Equipment > 112.5 Defective Materials > 112.5.1 Drywall, Performance Standard > 112.5.1.1 Remediation Standards > 112.5.1.1.3 Protocol > 112.5.1.1.3.11 Post-Rebuilding Clearance Testing
112.5 Administration, Defective Materials
A post-rebuilding clearance test prior to reoccupancy of the building or structure shall be conducted ...
2012 Virginia Construction Code (USBC, Part I) > 1 Administration > 112 Workmanship, Materials and Equipment > 112.5 Defective Materials
112.5.1.1.3 Administration, Protocol
performing pre-rebuilding or post-rebuilding clearance testing shall be independent of those responsible for all other remediation work and the agencies ...
2012 Virginia Construction Code (USBC, Part I) > 1 Administration > 112 Workmanship, Materials and Equipment > 112.5 Defective Materials > 112.5.1 Drywall, Performance Standard > 112.5.1.1 Remediation Standards > 112.5.1.1.3 Protocol
Section 112 Administration, Workmanship, Materials and Equipment
and personnel performing pre-rebuilding or post-rebuilding clearance testing shall be independent of those responsible for all other remediation work ...
2012 Virginia Construction Code (USBC, Part I) > 1 Administration > 112 Workmanship, Materials and Equipment
112.5.1.1.3.8 Administration, Pre-Rebuilding Clearance Testing
Following the steps outlined above for removal of all materials and components, cleaning and airing out, a pre-rebuilding clearance test shall ...
2012 Virginia Construction Code (USBC, Part I) > 1 Administration > 112 Workmanship, Materials and Equipment > 112.5 Defective Materials > 112.5.1 Drywall, Performance Standard > 112.5.1.1 Remediation Standards > 112.5.1.1.3 Protocol > 112.5.1.1.3.8 Pre-Rebuilding Clearance Testing