3305.2.8 Permanent Flooring and Steel Erection in Tiered Buildings
JUMP TO FULL CODE CHAPTER
The permanent floors of such buildings or other structures shall be installed as soon as possible as the erection of structural steel members progresses. In no case shall there be more than eight stories, floors or equivalent levels or 120 feet (36 576 mm), whichever is less, between the working deck and the uppermost permanent floor.
Exception: Where otherwise designed, in accordance with the approved construction documents, by the registered design professional of record.
Exception: Where otherwise designed, in accordance with the approved construction documents, by the registered design professional of record.
Related Code Sections
2205.6.4.5 Steel, Permanent Flooring and Steel Erection in Tiered Buildings
The permanent floors of such buildings or other structures shall be installed as soon as possible as the erection of structural steel members ...
NYC Building Code 2008 > 22 Steel > 2205 Structural Steel > 2205.6 Fabrication, Erection and Quality Control > 2205.6.4 Structural Steel Erection > 2205.6.4.5 Permanent Flooring and Steel Erection in Tiered Buildings
3305.2.8 Safeguards During Construction or Demolition, Permanent Flooring and Steel Erection in Tiered Buildings
The permanent floors of such buildings or other structures shall be installed as soon as possible as the erection of structural steel members ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3305 Material Placement and Installation > 3305.2 Structural Steel Assembly > 3305.2.8 Permanent Flooring and Steel Erection in Tiered Buildings
3305.2.8 Safeguards During Construction or Demolition, Permanent Flooring and Steel Erection in Tiered Buildings
The permanent floors of such buildings or other structures shall be installed as soon as possible as the erection of structural steel members ...
NYC Building Code 2022 > 33 Safeguards During Construction or Demolition > 3305 Material Placement and Installation > 3305.2 Structural Steel Assembly > 3305.2.8 Permanent Flooring and Steel Erection in Tiered Buildings
Appendix A Selected Rules of the Department of Buildings [PDF] (page 76)
(a) Permanent flooring and skeleton steel construction in tiered buildings. The permanent floors of such buildings or other structures shall be installed ...
3303.11.1 Safeguards During Construction or Demolition, Temporary Stairways in Unoccupied Buildings
or alteration and the highest floor accessible to a temporary or permanent stair shall be no more than 40 feet or 4 floors. In concrete construction ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3303 Safeguards and Maintenance of Site > 3303.11 Maintenance of Exits During Construction or Demolition > 3303.11.1 Temporary Stairways in Unoccupied Buildings