1910.66(h)(4) Periodic Reshackling of Suspension Wire Ropes
JUMP TO FULL CODE CHAPTER
The hoisting ropes shall be reshackled at the nondrum ends at intervals not exceeding 24 months. When reshackling the ropes, a sufficient length shall be cut from the end of the rope to remove damaged or fatigued portions.
Related Code Sections
1910.66(h)(4) Powered Platforms, Manlifts, and Vehicle-Mounted Work Platforms, Periodic Reshackling of Suspension Wire Ropes
The hoisting ropes shall be reshackled at the nondrum ends at intervals not exceeding 24 months. When reshackling the ropes, a sufficient length ...
OSHA 1910 General Industry > F Powered Platforms, Manlifts, and Vehicle-Mounted Work Platforms > 1910.66 Powered Platforms for Building Maintenance > 1910.66(h) Maintenance > 1910.66(h)(4) Periodic Reshackling of Suspension Wire Ropes
1910.66(g) Powered Platforms, Manlifts, and Vehicle-Mounted Work Platforms,
Suspension wire rope shall be maintained and used in accordance ...
OSHA 1910 General Industry > F Powered Platforms, Manlifts, and Vehicle-Mounted Work Platforms > 1910.66 Powered Platforms for Building Maintenance > 1910.66(g)
1910.66(f)(3)(ii) Powered Platforms, Manlifts, and Vehicle-Mounted Work Platforms, Transportable Outriggers
transportable outrigger shall be so located that the suspension wire ropes for two point suspended working platforms are hung parallel ...
OSHA 1910 General Industry > F Powered Platforms, Manlifts, and Vehicle-Mounted Work Platforms > 1910.66 Powered Platforms for Building Maintenance > 1910.66(f) Powered Platform Installations-Equipment > 1910.66(f)(3) Suspension Methods > 1910.66(f)(3)(ii) Transportable Outriggers
1910.66(f)(5)(ii)(M) Powered Platforms, Manlifts, and Vehicle-Mounted Work Platforms,
employee on a working platform suspended by two or more wire ropes, if the failure of one wire rope or suspension attachment will cause the platform to upset ...
OSHA 1910 General Industry > F Powered Platforms, Manlifts, and Vehicle-Mounted Work Platforms > 1910.66 Powered Platforms for Building Maintenance > 1910.66(f) Powered Platform Installations-Equipment > 1910.66(f)(5) Suspended Equipment > 1910.66(f)(5)(ii) Two and Four-Point Suspended Working Platforms > 1910.66(f)(5)(ii)(M)
1910.268(n)(5) Special Industries, Test Requirements for Cable Suspension Strand
, shall be thrown over the strand. On joint lines, the rope shall be passed over the strand using tree pruner handles or a wire raising tool. If two ...