107-24 Performance Bond
JUMP TO FULL CODE CHAPTER
When the provision of the required improvement is to be delayed for a period not to exceed five years from the date of the City Planning Commission certification, the owner of the zoning lot shall, prior to obtaining any certificate of occupancy, provide to the Comptroller of the City of New York a performance bond or City securities to ensure the future provision of either the waterfront esplanade or the public pedestrian way.
When the required improvement has been constructed, the Comptroller of the City of New York may release the bond or City securities posted to ensure such construction, provided an amount of the bond or City securities to ensure maintenance of the improvement, as set forth in the paragraph above, remains with the Comptroller.
The value of the bond or City securities tendered to ensure the future provision of the improvement shall be at the rate of $400 per 100 square feet of waterfront esplanade and at $200 per 100 square feet of public pedestrian way, if such bond or securities are tendered prior to January 1, 1980.
At five year intervals after January 1, 1980, the Commission, with the approval of the Board of Estimate, shall establish the new rates for the future provision (and maintenance) of the improvement.
Related Code Sections
105.9 Administration, Mandatory Sewer and Catch Basin Work Required by Section 24-526 of The
of Environmental Protection, its agents and contractors and the surety for a performance bond described in Item 1 above the legal right to enter ...
NYC Building Code 2008 > 1 Administration > 105 Permits > 105.9 Mandatory Sewer and Catch Basin Work Required by Section 24-526 of The
105.9 Administration, Mandatory Sewer and Catch Basin Work Required by Section 24-526 of the Administrative Code
of Environmental Protection that the applicant or owner has provided the Department of Environmental Protection with: A performance bond or other security ...
NYC Building Code 2014 > 1 Administration > 105 Permits > 105.9 Mandatory Sewer and Catch Basin Work Required by Section 24-526 of the Administrative Code
106.9 Administration, Mandatory Sewer and Catch Basin Work Required by Section 24-526 of the Administrative Code
of Environmental Protection that the applicant or owner has provided the Department of Environmental Protection with: A performance bond or other security ...
NYC Building Code 2022 > 1 Administration > 106 Permits > 106.9 Mandatory Sewer and Catch Basin Work Required by Section 24-526 of the Administrative Code
1704.11.6.3 Structural Tests and Special Inspections, Primer, Paint and Encapsulant Bond Tests
or encapsulated surface for which acceptable bond-strength performance between these coatings and the fire-resistant material has not been determined. A ...
NYC Building Code 2014 > 17 Structural Tests and Special Inspections > 1704 Special Inspections > 1704.11 Sprayed Fire-Resistant Materials > 1704.11.6 Bond Strength > 1704.11.6.3 Primer, Paint and Encapsulant Bond Tests
1705.14.6.3 Special Inspections and Tests, Primer, Paint and Encapsulant Bond Tests
or encapsulated surface for which acceptable bond-strength performance between these coatings and the fire-resistant material has not been determined. A ...
NYC Building Code 2022 > 17 Special Inspections and Tests > 1705 Required Special Inspections and Tests > 1705.14 Sprayed Fire-Resistant Materials > 1705.14.6 Bond Strength > 1705.14.6.3 Primer, Paint and Encapsulant Bond Tests