// CODE SNIPPET
1926.1404(q) Outriggers and Stabilizers
JUMP TO FULL CODE CHAPTER
When the load to be handled and the operating radius require the use of outriggers or stabilizers, or at any time when outriggers or stabilizers are used, all of the following requirements must be met (except as otherwise indicated):
The outriggers or stabilizers must be either fully extended or, if manufacturer procedures permit, deployed as specified in the load chart.
The outriggers must be set to remove the equipment weight from the wheels, except for locomotive cranes (see paragraph (q)(6) of this section for use of outriggers on locomotive cranes). This provision does not apply to stabilizers.
When outrigger floats are used, they must be attached to the outriggers. When stabilizer floats are used, they must be attached to the stabilizers.
Each outrigger or stabilizer must be visible to the operator or to a signal person during extension and setting.
Meet the requirements in paragraphs (h)(2) and (h)(3) of this section.
Be placed only under the outrigger or stabilizer float/pad of the jack or, where the outrigger or stabilizer is designed without a jack, under the outer bearing surface of the extended outrigger or stabilizer beam.
For locomotive cranes, when using outriggers or stabilizers to handle loads, the manufacturer's procedures must be followed. When lifting loads without using outriggers or stabilizers, the manufacturer's procedures must be met regarding truck wedges or screws.
Related Code Sections
1926.1404(q) Cranes & Derricks in Construction, Outriggers and Stabilizers
When the load to be handled and the operating radius require the use of outriggers or stabilizers, or at any time when outriggers or stabilizers ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1404 Assembly/Disassembly--General Requirements (Applies to All Assembly and Disassembly Operations) > 1926.1404(q) Outriggers and Stabilizers
1926.1416(e)(5)(i) Cranes & Derricks in Construction,
Outrigger/stabilizer position (horizontal beam extension) sensor/monitor if the equipment has outriggers or stabilizers. Temporary alternative ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1416 Operational Aids > 1926.1416(e) Category II Operational Aids and Alternative Measures > 1926.1416(e)(5) > 1926.1416(e)(5)(i)
1926.1431(c)(2) Cranes & Derricks in Construction,
Equipment with outriggers or stabilizers must have them all extended and locked. The amount of extension must be the same for all outriggers ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1431 Hoisting Personnel > 1926.1431(c) Equipment Set-Up > 1926.1431(c)(2)
1926.1431(c) Cranes & Derricks in Construction, Equipment Set-Up
or stabilizers must have them all extended and locked. The amount of extension must be the same for all outriggers and stabilizers and in accordance ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1431 Hoisting Personnel > 1926.1431(c) Equipment Set-Up
1926.1404(q)(3) Cranes & Derricks in Construction,
When outrigger floats are used, they must be attached to the outriggers. When stabilizer floats are used, they must be attached to the stabilizers ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1404 Assembly/Disassembly--General Requirements (Applies to All Assembly and Disassembly Operations) > 1926.1404(q) Outriggers and Stabilizers > 1926.1404(q)(3)