• Codes
  • Features

    Features Overview

    Go to features
    Reference

    Reference.

    A reliable and up-to-date source of codes.
    Research

    Research.

    Rapidly and efficiently calculate project parameters.
    Collaboration

    Collaboration.

    Get everyone on the same page and streamline code research.
    Workflows
    Architects
    Architects
    General Contractors
    General Contractors
    Building Official & Plans Examiners
    Building Official & Plans Examiners
    Inspectors
    Inspectors
    Owners
    Owners
    Subcontractors
    Subcontractors
    Code Consultants
    Code Consultants
  • Pricing
  • Login
  • Sign Up
Sign Up
Login
  • Code Library
  • Features
  • Pricing
  • About
  • Careers
  • Help
  • Contact
  • Terms
  • Privacy
Sign Up
Upgrade to Premium
Code calculators: Code Calculators automatically generates a detailed list of requirements.
REFERENCE
Amendment Styling
Industry-leading search
Code diagrams
RESEARCH
Code calculators
Filter by topic
Code compare
Code sheet exports
COLLABORATION
Team projects
Bookmarks
Comments
START 2 WEEK FREE TRIAL
Have an account? Sign in
// CODE SNIPPET

3303.10 Operations in Occupied Buildings

NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3303 Safeguards and Maintenance of Site > 3303.10 Operations in Occupied Buildings
JUMP TO FULL CODE CHAPTER
When construction or demolition activity occurs in an occupied building, barricades, signs, drop cloths, and other protective means shall be installed and maintained as necessary to provide reasonable protection for the occupants against hazard and nuisance. Such protective means shall be indicated on an occupant protection plan, or where a tenant protection plan is required by Section 3303.10.1, on a tenant protection plan.

*3303.10.1 Tenant Protection Plan

In buildings containing any occupied dwelling units, including newly constructed buildings that are partially occupied where work is still ongoing within the building, all alteration, construction or partial demolition work shall be performed in accordance with a tenant protection plan as required by Article 120 of Title 28 of the Administrative Code.

*Section 3303.10.1 was amended by Local Law 106 of 2019. This law has an effective date of March 8, 2020.

**3303.10.2 Inspections of Tenant Protection Plan

The owner shall notify the department in writing at least 72 hours prior to the commencement of any work requiring a tenant protection plan. The department shall conduct an inspection of 10 percent of such sites within seven days after the commencement of such work to verify compliance with the tenant protection plan. The department shall conduct follow up inspections of such sites every 180 days until such construction is completed to verify compliance with the building code and tenant protection plan. Thereafter, the department shall conduct an inspection within 10 days of receipt of a complaint concerning such work.

*Section 3303.10.2 was added by Local Law 154 of 2017. This law has an effective date of December 28, 2017.

**Section 3303.10.2 was amended by Local Law 116 of 2019. This law has an effective date of March 8, 2020.

*3303.10.3 Enforcement of Tenant Protection Plan

If work is not being performed in accordance with the tenant protection plan, the commissioner may issue a stop work order pursuant to section 28-207.2 of the administrative code.

*Section 3303.10.3 was added by Local Law 154 of 2017. This law has an effective date of December 28, 2017.

Related Code Sections


3303.10 Safeguards During Construction or Demolition, Operations in Occupied Buildings
When construction or demolition activity occurs in an occupied building, barricades, signs, drop cloths, and other protective means shall ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3303 Safeguards and Maintenance of Site > 3303.10 Operations in Occupied Buildings
3303.10 Safeguards During Construction or Demolition, Operations in Occupied Buildings
When construction or demolition activity occurs in an occupied building, barricades, signs, drop cloths, and other protective means shall ...
NYC Building Code 2022 > 33 Safeguards During Construction or Demolition > 3303 Safeguards and Maintenance of Site > 3303.10 Operations in Occupied Buildings
3303.10 Safeguards During Construction or Demolition, Repair and Alteration Operations in Occupied Buildings
Where repairs or alterations are conducted in occupied buildings, barricades, signs, drop cloths, and other protective means shall be erected ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3303 Safeguards and Maintenance of Site > 3303.10 Repair and Alteration Operations in Occupied Buildings
*3303.10.3 Safeguards During Construction or Demolition, Enforcement of Tenant Protection Plan
If work is not being performed in accordance with the tenant protection plan, the commissioner may issue a stop work order pursuant to Section 28 ...
NYC Building Code 2022 > 33 Safeguards During Construction or Demolition > 3303 Safeguards and Maintenance of Site > 3303.10 Operations in Occupied Buildings > *3303.10.3 Enforcement of Tenant Protection Plan
§28-110.1 Administration, Site Safety Plan
come into conflict with hoist operations; In occupied buildings, means and methods employed to protect all tenants from the adverse effect ...
NYC General Admin. Provisions 2022 > 1 Administration > 110 Site Safety Plan > §28-110.1 Site Safety Plan
Help Contact Us Privacy Terms
Search
Search
Don't miss relevant code. Quickly locate sections across your jurisdiction.
Shared projects
Shared projects
Projects provide a dedicated space to collaborate on code research.
Code sheet exports
Code sheet exports
Generate a code sheet that integrates with your drawing set.
Code diagrams
Code diagrams
Unpack the code through illustrations and descriptions.
Code Compare
Code Compare
Highlight differences between any two building codes.
Code Calculators
Code Calculators
Code calculators automatically generate a detailed list of requirements.
UpCodes Premium
Leverage the most sophisticated code compliance platform.
VISIT PRICING
UpCodes Premium
Leverage the full code compliance platform.
START 2 WEEK FREE TRIAL PRICING