3310.5.1 Notification to the Department of the Primary Manager or Coordinator
JUMP TO FULL CODE CHAPTER
The department shall be notified of the primary site safety manager or coordinator prior to the commencement of work. In the event that an alternate site safety manager or coordinator will be acting as the primary site safety manager or coordinator for a period longer than two consecutive weeks, the department must be so notified. Any permanent change of the primary site safety manager or coordinator requires immediate notification to the department.
Related Code Sections
3310.5.1 Safeguards During Construction or Demolition, Notification to the Department of the Primary Manager or Coordinator
, the department must be so notified. Any permanent change of the primary site safety manager or coordinator requires immediate notification ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3310 Requirements for the Construction or Demolition of Major Buildings > 3310.5 Site Safety Manager or Coordinator to Be Designated > 3310.5.1 Notification to the Department of the Primary Manager or Coordinator
3310.5.1 Safeguards During Construction or Demolition, Notification to the Department of the Primary Manager or Coordinator
weeks, the department must be so notified. Any permanent change of the primary
site safety manager or coordinator requires immediate notification ...
NYC Building Code 2022 > 33 Safeguards During Construction or Demolition > 3310 Requirements for the Construction or Demolition of Major Buildings > 3310.5 Site Safety Manager or Coordinator to Be Designated > 3310.5.1 Notification to the Department of the Primary Manager or Coordinator
3310.6 Safeguards During Construction or Demolition, Designation of Site Safety Manager and Site Safety Coordinator
requires immediate notification of the department. No proposed alternate manager or coordinator shall have as his or her primary duty the job of site ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3310 Requirements for the Construction or Demolition of Major Buildings > 3310.6 Designation of Site Safety Manager and Site Safety Coordinator
Section 3310 Safeguards During Construction or Demolition, Requirements for the Construction or Demolition of Major Buildings
change of the primary
site safety manager or coordinator requires immediate notification to the department ...
NYC Building Code 2022 > 33 Safeguards During Construction or Demolition > 3310 Requirements for the Construction or Demolition of Major Buildings
Section 3310 Safeguards During Construction or Demolition, Requirements for the Construction or Demolition of Major Buildings
immediate notification of the department. No proposed alternate manager or coordinator shall have as his or her primary duty the job of site safety ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3310 Requirements for the Construction or Demolition of Major Buildings