Before beginning a crane/derrick operation in which more than one crane/derrick will be supporting the load, the operation must be planned. The planning must meet the following requirements:
The plan must be developed by a qualified person.
The plan must be designed to ensure that the requirements of this subpart are met.
Where the qualified person determines that engineering expertise is needed for the planning, the employer must ensure that it is provided.
The multiple-crane/derrick lift must be directed by a person who meets the criteria for both a competent person and a qualified person, or by a competent person who is assisted by one or more qualified persons (lift director).
The lift director must review the plan in a meeting with all workers who will be involved with the operation.
[75 FR 48162, August 9, 2010]
[75 FR 48162, August 9, 2010]
Related Code Sections
1926.1432 Cranes & Derricks in Construction, Multiple-Crane/Derrick Lifts--Supplemental Requirements
The multiple-crane/derrick lift must be directed by a person who meets the criteria ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1432 Multiple-Crane/Derrick Lifts--Supplemental Requirements
1926.1432(a)(1) Cranes & Derricks in Construction,
The plan must be developed by a qualified person ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1432 Multiple-Crane/Derrick Lifts--Supplemental Requirements > 1926.1432(a) Plan Development > 1926.1432(a)(1)
1926.1432(a)(3) Cranes & Derricks in Construction,
Where the qualified person determines that engineering expertise is needed for the planning, the employer must ensure that it is provided ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1432 Multiple-Crane/Derrick Lifts--Supplemental Requirements > 1926.1432(a) Plan Development > 1926.1432(a)(3)
1926.1441(a) Cranes & Derricks in Construction,
of the load) (except for § 1926.1425(c)(3) (qualified rigger)); § 1926.1426 (Free fall and controlled load lowering); § 1926.1432 (Multiple crane/derrick lifts ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1441 Equipment With a Rated Hoisting/Lifting Capacity of 2,000 Pounds or Less > 1926.1441(a)
1926.1441 Cranes & Derricks in Construction, Equipment With a Rated Hoisting/Lifting Capacity of 2,000 Pounds or Less
) (qualified rigger)); § 1926.1426 (Free fall and controlled load lowering); § 1926.1432 (Multiple crane/derrick lifts--supplemental requirements ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1441 Equipment With a Rated Hoisting/Lifting Capacity of 2,000 Pounds or Less