// CODE SNIPPET
1926.153(i) Multiple Container Systems
JUMP TO FULL CODE CHAPTER
Valves in the assembly of multiple container systems shall be arranged so that replacement of containers can be made without shutting off the flow of gas in the system. This provision is not to be construed as requiring an automatic changeover device.
Heaters shall be equipped with an approved regulator in the supply line between the fuel cylinder and the heater unit. Cylinder connectors shall be provided with an excess flow valve to minimize the flow of gas in the event the fuel line becomes ruptured.
Regulators and low-pressure relief devices shall be rigidly attached to the cylinder valves, clyinders, supporting standards, the building walls, or otherwise rigidly secured, and shall be so installed or protected from the elements.
Related Code Sections
1926.153(i) Fire Protection and Prevention, Multiple Container Systems
Valves in the assembly of multiple container systems shall be arranged so that replacement of containers can be made without shutting off the flow ...
OSHA 1926 Construction > F Fire Protection and Prevention > 1926.153 Liquefied Petroleum Gas (LP-gas) > 1926.153(i) Multiple Container Systems
1926.961(b)(4) Electric Power Transmission and Distribution, Multiple Crews
, or Each crew shall independently comply with this section and, if there is no system operator ...
OSHA 1926 Construction > V Electric Power Transmission and Distribution > 1926.961 Deenergizing Lines and Equipment for Employee Protection > 1926.961(b) General > 1926.961(b)(4) Multiple Crews
1926.965(f) Electric Power Transmission and Distribution, Multiple Cables
When multiple cables are present in a work area, the employer shall identify the cable to be worked by electrical means, unless its identity ...
OSHA 1926 Construction > V Electric Power Transmission and Distribution > 1926.965 Underground Electrical Installations > 1926.965(f) Multiple Cables
1926.62(j)(3)(vi) Occupational Health and Environmental Controls, Alternate Physician Determination Mechanisms
of the multiple physician review mechanism provided by paragraph (j)(3)(iii) of this section so long as the alternate mechanism is as expeditious ...
OSHA 1926 Construction > D Occupational Health and Environmental Controls > 1926.62 Lead > 1926.62(j) Medical Surveillance > 1926.62(j)(3) Medical Examinations and Consultations > 1926.62(j)(3)(vi) Alternate Physician Determination Mechanisms
1926.1434(a)(5) Cranes & Derricks in Construction, Multiple Manufacturers of Equipment Designed for Use on Marine Work Sites
The equipment is designed for marine work sites, contains major structural components from more than one manufacturer, and the requirements ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1434 Equipment Modifications > 1926.1434(a) > 1926.1434(a)(5) Multiple Manufacturers of Equipment Designed for Use on Marine Work Sites