1910.119(j) Mechanical Integrity
JUMP TO FULL CODE CHAPTER
Paragraphs (j)(2) through (j)(6) of this section apply to the following process equipment:
Pressure vessels and storage tanks;
Relief and vent systems and devices;
Emergency shutdown systems;
Controls (including monitoring devices and sensors, alarms, and interlocks) and,
Piping systems (including piping components such as valves);
The employer shall establish and implement written procedures to maintain the on-going integrity of process equipment.
The employer shall train each employee involved in maintaining the on-going integrity of process equipment in an overview of that process and its hazards and in the procedures applicable to the employee's job tasks to assure that the employee can perform the job tasks in a safe manner.
Inspections and tests shall be performed on process equipment.
The frequency of inspections and tests of process equipment shall be consistent with applicable manufacturers' recommendations and good engineering practices, and more frequently if determined to be necessary by prior operating experience.
The employer shall document each inspection and test that has been performed on process equipment. The documentation shall identify the date of the inspection or test, the name of the person who performed the inspection or test, the serial number or other identifier of the equipment on which the inspection or test was performed, a description of the inspection or test performed, and the results of the inspection or test.
Inspection and testing procedures shall follow recognized and generally accepted good engineering practices.
The employer shall correct deficiencies in equipment that are outside acceptable limits (defined by the process safety information in paragraph (d) of this section) before further use or in a safe and timely manner when necessary means are taken to assure safe operation.
In the construction of new plants and equipment, the employer shall assure that equipment as it is fabricated is suitable for the process application for which they will be used.
The employer shall assure that maintenance materials, spare parts and equipment are suitable for the process application for which they will be used.
Appropriate checks and inspections shall be performed to assure that equipment is installed properly and consistent with design specifications and the manufacturer's instructions.
Related Code Sections
1910.119(j) Hazardous Materials, Mechanical Integrity
establish and implement written procedures to maintain the on-going integrity of process equipment ...
OSHA 1910 General Industry > H Hazardous Materials > 1910.119 Process Safety Management of Highly Hazardous Chemicals > 1910.119(j) Mechanical Integrity
1910.119(j)(6) Hazardous Materials, Quality Assurance
In the construction of new plants and equipment, the employer shall assure that equipment as it is fabricated is suitable for the process application ...
OSHA 1910 General Industry > H Hazardous Materials > 1910.119 Process Safety Management of Highly Hazardous Chemicals > 1910.119(j) Mechanical Integrity > 1910.119(j)(6) Quality Assurance
1910.119(j)(1)(i) Hazardous Materials,
Pressure vessels and storage tanks ...
OSHA 1910 General Industry > H Hazardous Materials > 1910.119 Process Safety Management of Highly Hazardous Chemicals > 1910.119(j) Mechanical Integrity > 1910.119(j)(1) Application > 1910.119(j)(1)(i)
1910.119(j)(1)(ii) Hazardous Materials,
Piping systems (including piping components such as valves ...
OSHA 1910 General Industry > H Hazardous Materials > 1910.119 Process Safety Management of Highly Hazardous Chemicals > 1910.119(j) Mechanical Integrity > 1910.119(j)(1) Application > 1910.119(j)(1)(ii)