Where unit masonry is laid with less head joint offset than in Section 2109.6.5.1, the minimum area of horizontal reinforcement placed in mortar bed joints or in bond beams spaced not more than 48 inches (1219 mm) apart, shall be 0.0003 times the vertical cross-sectional area of the wall.
Upcodes Diagrams

Related Code Sections

2109.6.5.2 Masonry, Masonry Laid in Stack Bond
Where unit masonry is laid with less head joint offset than in Section 2109.6.5.1, the minimum area of horizontal reinforcement placed in mortar bed ...
Reference Standard 10 Structural Work [PDF] (page 12)
in section 7.2. 7.7 MASONRY LAID IN STACK BOND.-Where unit masonry is laid in stack bond, continuous prefabricated joint reinforcement or other steel ...
Reference Standard 10 Structural Work [PDF] (page 8)
construction. b Direction of stress is parallel to bed joints. If masonry is laid in stack bond, tensile stress values for tension parallel to bed ...
Reference Standard 10 Structural Work [PDF] (page 13)
be provided by lapping units in alternate vertical courses. Where masonry units are laid in stack bond, continuous joint reinforcement shall be used ...
Section 2102 Masonry, Definitions and Notations
of this code, requirements for stack bond shall apply to masonry laid in other than running bond. STONE MASONRY. Masonry composed of field, quarried ...