// CODE SNIPPET
1906.8.4 Location in Slabs, Beams and Girders
Go To Full Code Chapter
Construction joints in floors shall be located within the middle third of spans of slabs, beams and girders. Joints in girders shall be offset a minimum distance of two times the width of intersecting beams.
Related Code Sections
1906.8.4 Concrete, Location in Slabs, Beams and Girders
Construction joints in floors shall be located within the middle third of spans of slabs, beams and girders. Joints in girders shall be offset ...
26.5.6.2 Construction Documents and Inspection,
be located within the middle third of spans of slabs, beams, and girders unless otherwise approved by the licensed design professional. (c) Construction ...
Article 19 Reinforced Concrete and Plain Concrete Construction [PDF] (page 18)
in the bottom layer. §C26-1494.0. Splices in reinforcement of slabs, beams and girders.a. In slabs, beams and girders, splices of reinforcement at points ...
1704.11.4.3.1 Structural Tests and Special Inspections, Beams and Girders
At beams and girders thickness measurements shall be made at nine locations around the beam or girder at each end of a 12-inch (305 mm) length ...
1705.14.4.5.1 Special Inspections and Tests, Beams and Girders
At beams and girders thickness measurements shall be made at nine locations around the beam or girder at each end of one 12-inch (304.8 mm) length ...