A-703.2 Issuance of Special Certificates of Inspection
JUMP TO FULL CODE CHAPTER
Special certificates of inspection shall be issued on the following basis:
- A special certificate of inspection shall be valid for no more than a single one year period, between August 1 of a given year and July 31 of the following year;
- For use at the start of such one year period on August 1, such special certificate must be obtained during the nine month period between November 1 and August 1 immediately preceding the beginning of the one year period;
- A certificate obtained after the one year period has started on August 1 is valid only for the remainder of that one year period;
- The Department shall not issue a special certificate of inspection unless the building has been inspected for fire, safety, electrical, lead paint, water quality and all other property-related hazards and:
- the Commissioner of Licenses and Inspections has certified that the building is in substantial compliance with the fire, safety and all other property-related requirements of this Code and that the building can be occupied safely without endangering life or public safety or welfare;
- the Health Department or a testing agency certified by the Pennsylvania Department of Environmental Protection has certified, within the previous five years, that the building is in substantial compliance with applicable water quality requirements of the Board of Health, provided that in no event shall applicable water quality requirements be deemed to permit lead in water at an outlet such as a sink or water fountain that is in service at 10 ppb or more. Any water outlet determined to exceed any such water quality requirements shall be taken out of service within 24 hours of notification of the relevant test. The owner of the educational occupancy shall post the results of the most recent water quality testing at each particular educational occupancy to a generally available website within ten days of receipt of the results.
- the owner of the building or its agent has provided either a certification from an Electrical Inspection Agency licensed by the City or, if the owner of the structure employs, on a full-time basis, an electrician licensed by the City, a certification from such electrician that is also signed by a person with supervisory authority over the electrician, such as a facilities manager, operations manager, or chief operating officer, that the building is in substantial compliance with the provisions of the Philadelphia Electrical Code.
- the owner of the building or its agent has provided certification that the building either (i) was built subsequent to 1978; or (ii) is not regularly occupied by students; or (iii) all areas of the building that are frequented by students have been inspected and determined to be safe from lead based paint hazards.
(.1) An area of a building shall be determined to be safe from lead based paint hazards only if it is free of any lead contaminated debris, such as dust, chips or other paint particulate, on surfaces; and it is free of any condition that may cause exposure to lead from lead-contaminated paint dust or debris, including, but not limited to: flaking, peeling, spalling or efflorescing paint. Flaking or peeling means that paint is visibly flaking from the surface or a person is able to get a fingernail under a paint layer. Spalling means moisture intrusion causing plaster to delaminate from substrate. Efflorescing means that crystalline deposits or white powdery residue is on plaster surfaces.
(.2) A building area shall be certified as safe from lead based paint hazards based on the visual observation of a certified lead inspector. A "certified lead inspector" shall be as defined in Section 6-802.
- All inspections relating to lead paint, including any assessments or evaluations, performed pursuant to subsection (.1) or otherwise, shall be performed in accordance with the following:
- No fewer than ten (10) days prior to the inspection, the person responsible for management of the building shall ensure that notice of the pending inspection and the scope of work involved is given to staff and parents of children in the school, or their representatives.
- No more than ten (10) days after the completion of any inspection, the person responsible for management of the building shall ensure that the results of the inspection, including the location, amount and condition of any lead paint that was found, is posted on the website of the entity responsible for operation of the building.
- The person responsible for management of the building shall ensure that advance notice of any remediation, abatement or clean-up work be given to staff and parents of children in the school, or their representatives, and posted on the entity's website, as promptly as practicable; and that the results of the work be posted on the website within ten (10) days after completion.
- All inspections relating to lead paint, including any assessments or evaluations, performed pursuant to subsection (.1) or otherwise, shall be performed in accordance with the following:
- The contents of special certificates of inspection issued under this subsection shall be made available for inspection by the Department and shall contain the following information:
- The name of the owner of the building;
- The address of the building;
- The location of automatic fire sprinkler system(s), if any;
- Location and type of fire alarm system(s), if any;
- Location of fire standpipe system(s), if any;
- If provided for only a portion of the building, a description of the portion of the building covered by the certificate of inspection;
- The time period for which it has been issued.
- Upon the request of the owner of the structure, a partial special certificate of inspection shall be issued to occupy a portion of the premises upon certification by the Commissioner of Licenses and Inspections that such portion of the premises has been certified to be in substantial compliance with fire, safety, electrical, lead paint, water quality and other property-related requirements provided that such portion or portions can be occupied safely prior to correction of the defect preventing full certification without endangering life or public safety or welfare. Such issuance shall be in accordance with procedures established by the Department and the code official shall notify the applicant of any limitations or restrictions imposed by the partial occupancy; and
- No fee shall be charged by the City for the issuance of special certificates of inspection or the inspections performed by the City in connection therewith.
Related Code Sections
A-703.2 Certificates and Approvals, Issuance of Special Certificates of Inspection
Special certificates of inspection shall be issued on the following basis:
A special certificate of inspection shall be valid for no more than ...
Philadelphia Administrative Code > 7 Certificates and Approvals > A-703 Special Certificate of Inspection > A-703.2 Issuance of Special Certificates of Inspection
A-701.3 Certificates and Approvals, Issuance
Upon successful completion of the final inspection in accordance with Section A-402.5 and within five business days thereafter, the certificate ...
Philadelphia Administrative Code > 7 Certificates and Approvals > A-701 Certificate of Occupancy > A-701.3 Issuance
A-902.6 Fees, Certificate Fee Schedule
, 2017. For the issuance of a Certificate ...
Philadelphia Administrative Code > 9 Fees > A-902 Building, Fuel Gas and Mechanical Code Fees > A-902.6 Certificate Fee Schedule
A-304.2 Permits, Special Inspections
The special inspection requirements shall be determined prior to the issuance of the building permit and shall be a requisite ...
Philadelphia Administrative Code > 3 Permits > A-304 Registered Design Professional Services > A-304.2 Special Inspections
A-402.5 Inspections, Final Inspection
Upon completion of the work authorized by the permit and before issuance of the certificate of occupancy or final approval, a final inspection shall ...