• Codes
  • Features

    Features Overview

    Go to features
    Reference

    Reference.

    A reliable and up-to-date source of codes.
    Research

    Research.

    Rapidly and efficiently calculate project parameters.
    Collaboration

    Collaboration.

    Get everyone on the same page and streamline code research.
    Workflows
    Architects
    Architects
    General Contractors
    General Contractors
    Building Official & Plans Examiners
    Building Official & Plans Examiners
    Inspectors
    Inspectors
    Owners
    Owners
    Subcontractors
    Subcontractors
    Code Consultants
    Code Consultants
  • Pricing
  • Login
  • Sign Up
Sign Up
Login
  • Code Library
  • Features
  • Pricing
  • About
  • Careers
  • Help
  • Contact
  • Terms
  • Privacy
Sign Up
Upgrade to Premium
Code calculators: Code Calculators automatically generates a detailed list of requirements.
REFERENCE
Amendment Styling
Industry-leading search
Code diagrams
RESEARCH
Code calculators
Filter by topic
Code compare
Code sheet exports
COLLABORATION
Team projects
Bookmarks
Comments
START 2 WEEK FREE TRIAL
Have an account? Sign in
// CODE SNIPPET

1926.1431(h)(5) Immediately Prior to Each Lift:

OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1431 Hoisting Personnel > 1926.1431(h) Trial Lift and Inspection > 1926.1431(h)(5) Immediately Prior to Each Lift:
JUMP TO FULL CODE CHAPTER

1926.1431(h)(5)(i)

The platform must be hoisted a few inches with the personnel and materials/tools on board and inspected by a competent person to ensure that it is secure and properly balanced.

1926.1431(h)(5)(ii)

The following conditions must be determined by a competent person to exist before the lift of personnel proceeds:

1926.1431(h)(5)(ii)(A)

Hoist ropes must be free of deficiencies in accordance with ยง 1926.1413(a).

1926.1431(h)(5)(ii)(B)

Multiple part lines must not be twisted around each other.

1926.1431(h)(5)(ii)(C)

The primary attachment must be centered over the platform.

1926.1431(h)(5)(ii)(D)

If the load rope is slack, the hoisting system must be inspected to ensure that all ropes are properly seated on drums and in sheaves.

Related Code Sections


1926.1431(h)(5) Cranes & Derricks in Construction, Immediately Prior to Each Lift:
conditions must be determined by a competent person to exist before the lift of personnel proceeds ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1431 Hoisting Personnel > 1926.1431(h) Trial Lift and Inspection > 1926.1431(h)(5) Immediately Prior to Each Lift:
1926.1431(h)(5)(ii)(D) Cranes & Derricks in Construction,
If the load rope is slack, the hoisting system must be inspected to ensure that all ropes are properly seated on drums and in sheaves ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1431 Hoisting Personnel > 1926.1431(h) Trial Lift and Inspection > 1926.1431(h)(5) Immediately Prior to Each Lift: > 1926.1431(h)(5)(ii) > 1926.1431(h)(5)(ii)(D)
1926.1431(h)(2) Cranes & Derricks in Construction,
The trial lift must be performed immediately prior to each shift in which personnel will be hoisted. In addition, the trial lift must be repeated ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1431 Hoisting Personnel > 1926.1431(h) Trial Lift and Inspection > 1926.1431(h)(2)
1926.1431(h) Cranes & Derricks in Construction, Trial Lift and Inspection
The trial lift must be performed immediately prior ...
OSHA 1926 Construction > CC Cranes & Derricks in Construction > 1926.1431 Hoisting Personnel > 1926.1431(h) Trial Lift and Inspection
1926.251(a) Materials Handling, Storage, Use, and Disposal, General
Rigging equipment for material handling shall be inspected prior to use on each shift and as necessary during its use to ensure that it is safe ...
OSHA 1926 Construction > H Materials Handling, Storage, Use, and Disposal > 1926.251 Rigging Equipment for Material Handling > 1926.251(a) General
Help Contact Us Privacy Terms
Code sheet exports
Code sheet exports
Generate a code sheet that integrates with your drawing set.
Shared projects
Shared projects
Projects provide a dedicated space to collaborate on code research.
Code Calculators
Code Calculators
Code calculators automatically generate a detailed list of requirements.
Code Compare
Code Compare
Highlight differences between any two building codes.
Code diagrams
Code diagrams
Unpack the code through illustrations and descriptions.
Search
Search
Don't miss relevant code. Quickly locate sections across your jurisdiction.