3308.1.5 Horizontal Netting and Tarpaulins
Related Code Sections
3308.1.5 Safeguards During Construction or Demolition, Horizontal Netting and Tarpaulins
When tarpaulins encase one or more floors immediately below the finished concrete floor in order to maintain temporary heat, the horizontal nets may ...
NYC Building Code 2008 > 33 Safeguards During Construction or Demolition > 3308 Safety Netting > 3308.1 Safety Netting During Construction or Demolition Operations > 3308.1.5 Horizontal Netting and Tarpaulins
3308.6.1.1 Safeguards During Construction or Demolition, During Construction
walkable floor reaches a height of six stories or 75 feet (22 860 mm) above the level of the ground or an adjoining roof, horizontal safety netting shall ...
NYC Building Code 2014 > 33 Safeguards During Construction or Demolition > 3308 Protection of Unenclosed Perimeters > 3308.6 Horizontal Safety Netting Systems > 3308.6.1 Where Required > 3308.6.1.1 During Construction
3308.6.1.1 Safeguards During Construction or Demolition, During Construction
or more floors immediately below the finished
concrete floor in order to maintain temporary heat, the horizontal netting may be located
no more than ...
NYC Building Code 2022 > 33 Safeguards During Construction or Demolition > 3308 Unenclosed Perimeter Protection > 3308.6 Horizontal Safety Netting Systems > 3308.6.1 Where Required > 3308.6.1.1 During Construction
3308.6 Safeguards During Construction or Demolition, Horizontal Safety Netting Systems
Horizontal safety netting shall meet the requirements of Sections 3308.6.1 through 3308.6.4 ...
NYC Building Code 2022 > 33 Safeguards During Construction or Demolition > 3308 Unenclosed Perimeter Protection > 3308.6 Horizontal Safety Netting Systems
Appendix A Selected Rules of the Department of Buildings [PDF] (page 76)
horizontal net. The record shall include the following information: Net serial number Date installed Dates inspected and all removal orders, per ยง26 ...