• Codes
  • Features

    Features Overview

    Go to features
    Reference

    Reference.

    A reliable and up-to-date source of codes.
    Research

    Research.

    Rapidly and efficiently calculate project parameters.
    Collaboration

    Collaboration.

    Get everyone on the same page and streamline code research.
    Workflows
    Architects General Contractor Building Official & Plans Examiner Inspectors Owner Subcontractors Code Consultants
  • Pricing
  • Login
  • Sign Up
Sign Up
Login
  • Code Library
  • Features
  • Pricing
  • About
  • Careers
  • Help
  • Contact
  • Terms
  • Privacy
Sign Up
Upgrade to Premium
Code calculators: Code Calculators automatically generates a detailed list of requirements.
REFERENCE
Amendment Styling
Industry-leading search
Suggested code sections
Code diagrams
RESEARCH
Code calculators
Filter by topic
Code compare
Code sheet exports
COLLABORATION
Team projects
Bookmarks
Comments
START 2 WEEK FREE TRIAL
Have an account? Sign in
// CODE SNIPPET

611.3 Functional and Performance Testing

Green Construction Code 2015 > 6 Energy Conservation, Efficiency and Co2e Emission Reduction > 611 Energy Systems Commissioning and Completion > 611.3 Functional and Performance Testing
JUMP TO FULL CODE CHAPTER
Functional and performance testing shall be performed in accordance with the requirements of Sections 611.3.1, 611.3.2 and 611.3.3.

611.3.1 Equipment

Equipment functional and performance testing shall demonstrate that the installation and operation of components, systems, and system-to-system interfacing relationships is in accordance with approved plans and specifications so that operation, function, performance and maintenance serviceability for each of the commissioned systems is confirmed. Testing shall include all specified modes of control and sequence of operation, including under full-load, part-load and all of the following emergency conditions:
  1. Each mode as described in the sequence of operation.
  2. Redundant or automatic backup mode.
  3. Performance of alarms.
  4. Mode of operation upon a loss of power and restoration of power.

611.3.2 Controls

Control systems shall be tested to document that control devices, components, equipment, and systems are calibrated, adjusted and operated in accordance with the approved plans and specifications.

611.3.3 Sequence of Operation

The sequence of operation shall be verified to document that the sequence operates in accordance with the approved plans and specifications. This verified sequence of operation shall be the final record of system operation, and shall be included on the control "record documents," and as part of the education and Systems Manual operation and maintenance document that is provided to the owner.

Related Code Sections


611.3 Energy Conservation, Efficiency and Co2e Emission Reduction, Functional and Performance Testing
Functional and performance testing shall be performed in accordance with the requirements of Sections 611.3.1, 611.3.2 and 611.3.3 ...
Green Construction Code 2015 > 6 Energy Conservation, Efficiency and Co2e Emission Reduction > 611 Energy Systems Commissioning and Completion > 611.3 Functional and Performance Testing
611.1.3 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION, Functional Performance Testing
Functional performance testing shall be in accordance with the requirements of Sections 611.1.3.1, 611.1.3.2 and 611.1.3.3 ...
Green Construction Code 2012 > 6 ENERGY CONSERVATION, EFFICIENCY AND CO2e EMISSION REDUCTION > 611 Energy Systems Commissioning and Completion > 611.1 Mechanical Systems Commissioning and Completion Requirements > 611.1.3 Functional Performance Testing
C408.2.3 [CE] Commercial Energy Efficiency, Functional Performance Testing
Functional performance testing specified in Sections C408.2.3.1 through C408.2.3.3 shall be conducted ...
Energy Conservation Code 2012 > 4 [CE] Commercial Energy Efficiency > C408 System Commissioning > C408.2 Mechanical Systems Commissioning and Completion Requirements > C408.2.3 Functional Performance Testing
C408.2.3 [CE] Commercial Energy Efficiency, Functional Performance Testing
Functional performance testing specified in Sections C408.2.3.1 through C408.2.3.3 shall be conducted ...
Energy Conservation Code 2015 > 4 [CE] Commercial Energy Efficiency > C408 System Commissioning > C408.2 Mechanical Systems and Service Water-Heating Systems Commissioning and Completion Requirements > C408.2.3 Functional Performance Testing
902.5.1 Commissioning, Inspections, Operation and Maintenance, Final Commissioning Report
the following: A copy of the final commissioning plan, including functional and performance test procedures used during the commissioning process ...
Green Construction Code 2015 > 9 Commissioning, Inspections, Operation and Maintenance > 902 Special Inspection and Commissioning > 902.5 Final Commissioning Report > 902.5.1 Final Commissioning Report
Help Contact Us Privacy Terms
Shared projects
Shared projects
Projects provide a dedicated space to collaborate on code research.
Code Compare
Code Compare
Highlight differences between any two building codes.
Code Calculators
Code Calculators
Code calculators automatically generate a detailed list of requirements.
Search
Search
Don't miss relevant code. Quickly locate sections across your jurisdiction.
Code sheet exports
Code sheet exports
Generate a code sheet that integrates with your drawing set.
Code diagrams
Code diagrams
Unpack the code through illustrations and descriptions.
UpCodes Premium
Leverage the most sophisticated code compliance platform.
TRY FREE FOR TWO WEEKS VISIT PRICING
UpCodes Premium
Leverage the full code compliance platform.
START 2 WEEK FREE TRIAL LEARN MORE