Fuel gas piping and equipment installed within a permanent building in a manufactured home community shall comply with nationally recognized appliance and fuel gas piping codes and standards adopted by the Authority Having Jurisdiction. Where the state or other political subdivision does not assume jurisdiction, such fuel gas piping and equipment installations shall be designed and installed in accordance with the applicable provisions of NFPA 54 or NFPA 58. [NFPA 501A:4.6.1.1 — 4.6.1.2]

Related Code Sections

G2421.5 Fuel Gas, (410.5) Flashback Arrestor Check Valve
check valve shall be installed at an approved location on both the fuel gas and oxygen supply lines. Where the pressure of the piped fuel gas supply ...
1202.3 Fuel Gas Piping, Applications
reactions. LP-Gas installations at utility gas plants. Liquefied natural gas (LNG) installations. Fuel gas piping in electric utility power plants ...
301.6 General Regulations, Fuel Gas Appliances and Equipment
The approval and installation of fuel gas distribution piping and equipment, fuel gas-fired appliances and fuel gas-fired appliance venting systems ...
101.2 Scope and Administration, Scope
, system components, equipment and appliances specifically addressed herein. The installation of fuel gas distribution piping and equipment, fuel gas ...